FUNCTIONAL TEST CHECKLIST
Chilled Water System (Chwsys) - ______
Specification Section 15____
Project:______Project No:______
Associated Equipment:
____AHU - _____ thru ______
____CHWP - ____ thru ____
____VFD for CHWP ______
____B-T Station ______
[______]
Related Tests: ______
1. Participants
Name
/ Firm / ParticipationParty filling out this form & witnessing ______Date of test ______
Approvals. This filled-out checklist has been reviewed. Its completion is approved. Exceptions are noted below or attached.
______
General Contractor [Construction Manager] Date
______
Commissioning Authority/Agent Date Owner’s Representative Date
2. Prerequisite Checklist
a) The prefunctional checklist for the pump(s) is complete and approved: Yes / No
b) The prefunctional checklist for the piping is complete and approved: Yes / No
c) The prefunctional checklist for the associated Bridge-Tender station is complete and approved: N/A / Yes / No
d) Testing, Adjusting and Balancing (TAB) completed and approved for the hydronic and air systems connected: Yes / No
e) TAB report provided: Yes / No
f) All A/E punchlist items for this and related equipment are corrected: Yes / No
g) Functional testing is complete and approved for the variable frequency drive for the pump(s):
N/A / Yes / No
h) Functional testing is complete and approved for the air handling units of this system:
N/A / Yes / No
i) Sequence of operation is attached: Yes / No
j) Design setpoint information included on forms: Yes / No
k) Controls:
i) DDC loops operational, temperature/pressure setpoints met without hunting: Yes / No
ii) Master transmission diagram is updated on device graph: Yes / No
iii) Graphic programming is complete and operational: Yes / No
iv) System communicates with mainframe: Yes / No
v) Bridge-Tender is set to design/final setpoints: N/A / Yes / No
vi) Local reading of setpoints agree with remote readings: Yes / No
3. Functional Testing Procedure
a. CHW System with Bridge Tender
Step / Mode / Test Procedure / Expected Response / Pass (Y/N/N/A) /
1 / Pump(s) Off / Standby check. HOA in Auto position(s). Pump(s) commanded Off by BMS. / Verify by visual inspection that:
a) Pump(s) are off, zero flow.
b) Bridge-Tender valves V-1 and V-2 are closed.
2 / Pump P-1 Startup / HOA in Auto position. Pump commanded On by BMS. / Verify by visual inspection that:
a) Bridge-Tender valve V-1 (return pipe) opens.
b) Pump, P-1, is On, other pumps are Off.
c) Bridge-Tender valve V-2 (bypass) throttles.
3 / Pump P-1 Operation / HOA in Auto position.
Pump and Bridge-Tender Verification: AHU supply air (SA) discharge setpoints at initial value 55F as a group. Through BMS raise/lower setpoints per schedule record table. / Verify by local and remote reading that:
Pump P-1 status is On, all other pump status’ are Off, B-T valves modulate allowing blending of SCHW based on change in AHU setpoints. BMS readings, local B-T panels readings and local instrument readings correspond.
4 / HOA Operation / HOA in Auto position. Move HOA switch to Off position for all pumps. Command P-1 On with HOA switch. Command P-1 Off with HOA switch. Repeat for all pumps. Reset pump, P-1, HOA switch to Auto, after start, place remaining pumps in Auto position. / All pumps turned Off by HOA switches. P-1 turns On, B-T valves modulate. When commanded by HOA switch, all other pumps turn On. After reset of pump, P-1, to Auto, P-1 starts. All other pumps remain Off.
5 / Pump P-2 Startup / HOA in Auto position. Pump, P-1, commanded Off by BMS, pump, P-2, commanded On by BMS. / Verify by visual inspection that:
a) Bridge-Tender valve V-1 (return pipe) opens.
b) Pump, P-2, is On, other pumps are Off.
c) Bridge-Tender valve V-2 (bypass) throttles.
6 / Pump P-2 Operation / HOA in Auto position.
Pump and Bridge-Tender Verification: AHU supply air (SA) discharge setpoints at initial value 55F as a group. Through BMS raise/lower setpoints per schedule record table. / Verify by local and remote reading that:
Pump P-2 status is On, all other pump status’ are Off, B-T valves modulate allowing blending of SCHW based on change in AHU setpoints. BMS readings, local B-T panels readings and local instrument readings correspond.
7 / Automatic Start upon Power Failure / HOA in Auto position. Pump, P-2, local disconnect moved to Off position (simulating power failure to pump, P-2). After pump, P-1, starts, restore power to pump, P-2. / Pump, P-2, is Off. Pump, P-1, starts automatically. B-T valves modulate. Pump, P-1, continues to run, pump, P-2, remains Off.
b. CHW System without Bridge Tender
Step / Mode / Test Procedure / Expected Response / Pass (Y/N/N/A)
1 / Pump(s) Off / Standby check. HOA in Auto position(s). Pump(s) commanded Off by BMS. / Verify by visual inspection that pump(s) are off, zero flow.
2 / Pump P-1 Startup / HOA in Auto position. Pump commanded On by BMS. / Verify by visual inspection that Pump, P-1, is On, other pumps are Off.
3 / Pump P-1 Operation / HOA in Auto position.
Pump Verification: AHU supply air (SA) discharge setpoints at initial value 55F as a group. Through BMS raise/lower setpoints per schedule record table. / Verify by local and remote reading that:
Pump P-1 status is On, all other pump status’ are Off, BMS readings and local instrument readings correspond.
4 / HOA Operation / HOA in Auto position. Move HOA switch to Off position for all pumps. Command P-1 On with HOA switch. Command P-1 Off with HOA switch. Repeat for all pumps. Reset pump, P-1, HOA switch to Auto, after start, place remaining pumps in Auto position. / All pumps turned Off by HOA switches. P-1 turns On. When commanded by HOA switch, all other pumps turn On. After reset of pump, P-1, to Auto, P-1 starts. All other pumps remain Off.
5 / Pump P-2 Startup / HOA in Auto position. Pump, P-1, commanded Off by BMS, pump, P-2, commanded On by BMS. / Verify by visual inspection that pump, P-2, is On, other pumps are Off.
6 / Pump P-2 Operation / HOA in Auto position.
Pump Verification: AHU supply air (SA) discharge setpoints at initial value 55F as a group. Through BMS raise/lower setpoints per schedule record table. / Verify by local and remote reading that:
Pump P-2 status is On, all other pump status’ are Off, BMS readings and local instrument readings correspond.
7 / Automatic Start upon Power Failure / HOA in Auto position. Pump, P-2, local disconnect moved to Off position (simulating power failure to pump, P-2). After pump, P-1, starts, restore power to pump, P-2. / Pump, P-2, is Off. Pump, P-1, starts automatically. Pump, P-1, continues to run, pump, P-2, remains Off.
Comments:
-- END OF SECTION --