Goals by IndividualAshley
- Work on self-improvement including training on public speaking, management courses
 - Read self-improvement books such as leadership books
 - Work on taking more initiative to improve self-confidence
 
Blake
- Achieve zero preventable accidents
 - Achieve zero bank corrections
 - Implement prepaid metering by March 1
 - Complete over 30,000 meter exchanges this year
 - Complete all meter equipment inspections by end of Q1
 - Have more accurate budgeting while staying 10% under budget
 
Colleen
- Have the safety department accomplish buy-in from the supervisors (idea: invite safety manager to management team meetings once per month at the strategic planning meetings)
 - Get an leadership and employee development program in place
 - Develop the manager and get organization within the communications and outreach department
 - Delegate and trust more to become more comfortable with managers’ abilities
 - Find out where all the vehicles are
 - Get T4 building project completed in 2017
 
Dane
- Mitigate all five high security risks by 7/1/2017
 - Mitigate five medium security risks by the end of the year
 - Have the Gretna and Hinson substations communicating before the go-live date (5/31)
 - Successfully deploy physical security by the end of 2017
 - Label all networking cables and clean up all communications rooms by the end of the year
 - Roll out a mobile app by the end of the year
 
Sean
- Offer digital payment to outside vendors for accounts payable by July 2017
 - Visit two key accounts per month beginning in February
 - Visit all five warehouses beginning in February
 - Delegate more tasks to key staff
 - Cross-train in billing department
 - Provide staking sheet training
 
Tim
- Improve communication internally and externally
 - Delegate (and be specific about what tasks need to be delegated, when, and to whom including with what procedures in writing)
 - Share ideas, problems, and results (including by inviting managers from other departments to your department meetings)
 - Engage others throughout the organization when prudent
 - Move toward a more digital world (real time documentation, data gathering, reporting)
 - Increase and enhance water quality
 - Develop an enhanced flushing program targeting problem areas
 - Implement work plan efficiently concentrating on aged infrastructure and problem areas
 - Develop analytical tools for water usage and unaccounted volumes (complete AMI exchanges by Q2 of 2018)
 - Improve and expand on training opportunities toward an enhanced safe working environment
 
Tony
- Identify people in the department for succession planning and begin the process of preparing them by the end of 2017
 - Complete 30,000 meter exchanges by the end of the year (with entire project completed by Q2 of 2018)
 - Meet reliability goals by December 2017
 - Complete the 2017 right-of-way plan in 2017
 - Develop a training plan for dispatch center (by end of Q2) and begin implementation soon after
 - Develop and roll out the community solar program
 
Tracy
- Develop and roll out the community solar program (Tony and Sean) by 15 April 2017
 - Implement TWWI work plan by scheduling projects (by 31 January 2017) and making sure they are completed on time based on the schedule (Tim)
 - Implement prepay by 1 March 2017 (Blake)
 - Meet reliability goals by 31 December 2017 (Tony)
 - Establish a safety improvement plan by 30 June 2017 (Colleen)
 - Reduce cybersecurity risks by 1 July 2017 (Dane)
 - Complete succession plan by 30 June 2017 (Colleen)
 