Contract No.: Nlm/Otp/Isubatn/2017/18

Contract No.: Nlm/Otp/Isubatn/2017/18

NTABANKULU LOCAL MUNICIPALITY

CONTRACT NO.: NLM/OTP/ISUBATN/2017/18

NTABANKULU INTERNAL STREETS UPGRADE: BEHIND ABSA AND TOWN NORTH

Part C1: Pricing Data

Content / Pages
C2.1 / Pricing Instructions / 98-99
C2.2 / Bills of Quantities / 100-131

C2.1 Pricing Instructions

  1. For the purposes of this schedule of quantities, the following words shall have the meanings hereby assigned to them:

Unit: The unit of measurement for each item of works as defined in the specifications.

Quantity: The number of units of work for each item.

Rate: The payment per unit of measurement at which the tenderer tenders to do the work.

Amount: The product of the quantity and the rate tendered for an item.

Lump sum: An amount tendered for an item, the extent of which is described in the schedule of quantities, the specifications or elsewhere but the quantity of work of which is not measured in any units.

  1. This schedule of quantities forms an integral part of the contract documents.
  1. The quantities set out in the schedule of quantities are approximate quantities only. The quantities of workfinally accepted and certified for payment, and not the quantities given in the schedule of quantities, shall be used for determining payment to the contractor.

The validity of the contract shall in no way be affected by differences between the quantities in the schedule of quantities and the quantities finally certified for payment. Works shall be valued at the rates or lump sums tendered, subject only to the provisions for the general conditions of contract, paragraphs 11 and 12 of this preamble, and subclause 1209(a) of the standard specifications.

  1. Rates and lump sums shall be comprehensive in accordance with subclause 1209(b) of the standard specifications. Full compensation for completing and maintaining, during the maintenance period, all the work shown on the drawings and specified in the specifications, and for all the risks, obligations and responsibilities specified in the general conditions of contract, special conditions of contract and specifications shall be considered as provided for collectively in the items of payment given in the schedule of quantities, except in so far as the quantities given in the schedule of quantities are only approximate.
  1. The tenderer shall fill in a rate or a lump sum for each item where provision has been made for it, even where no quantities are given.

A tender may be rejected if the tenderer has not filled in a rate or a lump sum against each item and if the tenderer fails to furnish the rates or lump sums for such items within seven (7) days of having been notified in writing by the employer to do so.

The tenderer shall fill in a rate against all items where the words "rate only" appears in the amount column.

The provisions of subclause 1209(f) of the standard specifications shall apply to rate-only items.

Tenderers shall also note the provisions of paragraph 12 of this preamble.

The tenderer may not group a number of items together and tender one lump sum for such group of items.

The tenderer also may not indicate against any item that full compensation for such item has been included in another item.

The tendered lump sums and rate shall be valid irrespective of any change in the quantities during the execution of the contract.

  1. The works as executed will be measured for payment in accordance with the methods described in the contract documents under the various payment items, notwithstanding any custom to the contrary. Attention is directed to the provisions of clause 1220 of the standard specifications regarding the measurement of quantities for payment. Except where otherwise specified as in clause 1220, the nett measurement or mass of the finished work in place shall be taken for payment but excluding any volume or mass of work in excess of that ordered.
  1. The amount of work or the quantities of material stated in the schedule of quantities shall not be considered as restricting or extending the amount of work to be done or quantity of material to be supplied by the contractor.
  1. The stating of quantities of material or amount of work in the schedule of quantities shall not be regarded as authorization for the contractor to order material or to execute work. The contractor shall obtain the engineer's detailed instructions for all work before ordering any materials for or executing work or making arrangements in this regard.
  1. The short descriptions of the payment items given in the schedule of quantities are only for the purposes of identifying the items and providing specific details. Reference shall be made, inter alia, to the drawings, standard specifications, project specifications, general conditions of contract and special conditions of contract for more detailed information regarding the extent of the work entailed under each item.
  1. Reference shall be made to clause 48 of the general conditions of contract regarding provisional sums and prime cost sums.
  1. Subject to the conditions stated in paragraph 12 below, the rates and lump sums filled in by the tenderer inthe schedule of quantities shall be final and binding and may not be adjusted should there be any mistakes in the extensions thereof. Should there be any discrepancies between the correctly extended totalled schedule of quantities and the tender sum, the rates will be regarded as being correct, and the employershall have the right to make such adjustments to the tender sum as he may deem necessary in order toreconcile the total of the schedule of quantities with the tender sum. In such an event the contractor will be consulted but failing agreement between the parties, the decision of the employer shall be final and binding. Such adjustment of the tender sum shall take place only after acceptance of the tender, but prior to the signing of the contract. In their own interest tenderers should make double sure of the correctness of their tendered rates, the extensions and the tender sum.
  1. A tender may be rejected if the unit rates or lump sums for some of the items in the schedule of quantitiesare, in the opinion of the employer, unreasonable or out of proportion, and the tenderer fails, within a period of seven (7) days of having been notified in writing by the employer to adjust the unit rates or lump sums for such items, to make such adjustments.
  1. The units of measurement indicated in the schedule of quantities are metric units. The followingabbreviations are used in the schedule of quantities:

mm = millimetre h = hour

m = metre kg = kilogram

km = kilometre t = ton (1000 kg)

m² = square metre No. = number

m².pass = square metre-pass sum = lump sum

ha = hectare MN = meganewton

m³ = cubic metre MN.m = meganewton-metre

m³.km = cubic metre-kilometre P C sum = Prime Cost sum

l = litre Prov sum = Provisional sum

kl = kilolitre % = per cent

MPa = megapascal kW = kilowatt

  1. All rates and sums of money quoted in the schedule of quantities shall be in rands and whole cents.Fractions of a cent shall be discarded.
  1. The item numbers appearing in the schedule of quantities refer to the corresponding item numbers in thestandard specifications. Item numbers prefixed by the letter B refer to payment items described under part B of the project specifications; those prefixed by C refer to part C, etc for further parts of the project specifications.

Item numbers in schedule B of the schedule of quantities are in addition, preceded by the schedulenumber of each separate part of schedule B of the schedule of quantities, eg payment item 62.02 described in the standard specifications (clause 6210), when used in part 3 of the schedule B of the schedule of quantities, would be numbered 3/62.02, and if this payment item had been amended in part B of the project specifications, the payment item would be indicated as 3/B62.02.

NB: TENDERERS MUST COMPLETE THE SCHEDULE OF QUANTITIES IN BLACK INK

C2.2 Bills of Quantities

CONTENTS / PAGES
BILL OF QUANTITIES / 101- 131

1200 GENERAL REQUIREMENTS AND PROVISIONS

Item
No / Description / Unit / Quantity / Rate / Amount
R / c
1200 / 1200 GENERAL REQUIREMENTS AND PROVISIONS
B12.01 / Contract information signboard / No / 1.0
B12.02 / Additional Survey as requested by the Engineer:
(a) Additional survey as required by the Engineer / PC Sum / 1.0 / 60,000.00 / 60,000 / 00
(b) Handling costs, profits and all other charges in respect of Item 12.02 (a) / % / 60,000.00
B12.03 / Identification of location of existing services within the site
(a) Identification and/or confirmation of services by use of hand excavation less than 1.5m deep / m³ / 350.0 / 65.00 / 22,750 / 00
(b) Providing the Engineer with a detailed set of services' drawings and schedules after the investigation. / L/Sum / 1.00
B12.04 / Protection, removal, realignment and replacement of services
(a) Telkom services
(i) Underground ducts and cables / Prov Sum / 1.0 / 50,000.00 / 50,000 / 00
(ii) Handling costs, profits and all other charges in respect of Item 12.04 (a) (i) / % / 50,000.00
(b) Electrical services
(i) Underground ducts and cables / Prov Sum / 1.0 / 100,000.00 / 100,000 / 00
(ii) Handling costs, profits and all other charges in respect of Item 12.04 (b) (i) / % / 100,000.0
(c) Water pipes
(i) Relocation of exisitng water pipelines / Prov Sum / 1.0 / 150,000.00 / 150,000 / 00
(ii) Handling costs, profits and all other charges in respect of Item 12.04 (c) (i) / % / 150,000.0
(d) Sewer pipes
(i) Relocation of existing sewer pipes with diameter betweem 160mm - 350mm. / Prov Sum / 1.0 / 200,000.00 / 200,000 / 00
(ii) Handling costs, profits and all other charges in respect of Item 12.04 (d) (i) / % / 200,000.0
B12.05 / Reinstating trenches crossing roads :
a) Selected layers / m2 / 50.0
b) Subbase / m2 / 50.0
c) Base (incl. prime) / m2 / 50.0
d) Bituminous surfacing (including tack coat) / m2 / 50.0
Total Carried Forward To Summary

1300 CONTRACTOR'S ESTABLISHMENT ON SITE AND GENERAL OBLIGATIONS

Item
No / Description / Unit / Quantity / Rate / Amount
R / c
13 / 1300 CONTRACTOR'S ESTABLISHMENT ON SITE AND GENERAL OBLIGATIONS
B13.01 / Contractor's general obligations
(a) Fixed obligations / Sum / 1.0
(b) Value-related obligations / Sum / 1.0
(c) Time-related obligations / month / 7.0
(d) Environmental obligations / month / 7.0
(e) Monthly reporting costs / month / 7.0
Total Carried Forward To Summary

1400 HOUSING, OFFICES AND LABORA- TORY FOR THE ENGINEER'S SITE PERSONNEL

Item
No / Description / Unit / Quantity / Rate / Amount
R / c
14 / 1400 HOUSING, OFFICES AND LABORA- TORY FOR THE ENGINEER'S SITE PERSONNEL
14.01 / Office and laboratory accommodation
(a) Offices (interior floor space only) / m² / 24.0
(e) Ablution units / m² / 3.0
(f) Stores / m² / 30.0
(g) 1500mm wide roofed veranda over 100mm thick concrete floor slab around offices (all inclusive) / m² / 36.0
14.02 / Office and laboratory furniture
(a) Chairs / No / 10.0
(b) Draughtsman's stools / No / 2.0
(d) Desks, complete with drawers and locks / No / 2.0
(e) Drawing tables / No / 2.0
(f) Conference tables / No / 1.0
14.03 / Office and laboratory fittings, installations and equipment:
(a) Items measured by number:
(i) 220/250 volt power points / No / 2.0
(v) Single incandescent-light fittings complete with 100 watt globes / No / 2.0
(vi) Wash-hand basins complete with taps and drains / No / 1.0
(xi) Air-conditioning units with, 2,2kw minimum capacity, mounted and with own power connection / No / 2.0
(xv) Steel filling cabinets with drawers / No / 1.0
(b) Prime-cost items and items paid for in a lump sum;
(ix) Cellphone cost, including pro-rata rentals, for calls in connection with contract administration / PC Sum / 10,000 / 00
x) Handling costs and profit in respect of subitem B14.03 (b)(ix) above / % / 10,000.00
(c) Items measured by area:
(vi) Roller blinds, opaque type / m² / 16.0
viii) Notice boards as specified / m² / 10.0
14.04 / Car Ports:
Car ports, as specified, at offices and laboratory buildings / No / 2.0
14.07 / Rented, hotel and other accommodation:
(a) Provisional sum for providing rented housing, hotel or other accommodation as described in subsubclause 1403(c)(ii) / Prov Sum / 1.0
(b) Handling costs and profit in respect of subitem 14.07(a) / % / 50,000.00
Total Carried Forward

1400 HOUSING, OFFICES AND LABORA- TORY FOR THE ENGINEER'S SITE PERSONNEL

Item
No / Description / Unit / Quantity / Rate / Amount
R / c
Brought Forward
14.08 / Services
(a) Services at office and laboratories
(1) Fixed costs / L/Sum / 1.0
(2) Running costs / month / 8.0
14,10 / Provision of photostat facilities / month / 8.0
Total Carried Forward To Summary

1500 ACCOMODATION OF TRAFFIC

Item
No / Description / Unit / Quantity / Rate / Amount
R / c
15 / 1500 ACCOMODATION OF TRAFFIC
15.01 / Accommodating traffic and maintaining temporary deviations / km / 5.0
15.03 / Temporary traffic-control facilities
(a) Flagmen / man-day / 322.0
(b) Portable STOP and GO-RY signs / No / 2.0
(e) Road Signs, R- and TR- series (900 mm diameters) / No. / 5.0
(f) Road Signs, TW Series (1200 mm side) / No. / 5.0
(g) Roads signs,STW-, DTG-, TGS- and TG- SERIES (Engineering Grade background, sizes as spercified for 40km/hr) / m² / 10.0
(h) Delineators (DTH50J) (SIZE - 600 mm x 150mm including sand bags)
(i) Single / No / 10.0
(ii) Mounted back to back / No / 4.0
(i) Movable barricated/road sign combination ( 1600mm wide) / No / 2.0
(j) Two-way communiction devices / No / 2.0
15.06 / Watering of temporary deviations / kl / 20,000.0
15.10 / Accommodation of traffic where the road is constructed in half-widths / km / 3.8
15.15 / Provision of traffic safety equipment for useby the Engineer
(a) Safety Jackets / No / 4.0
(b) Amber Flashing lights with magnetic mounts / No / 2.0
Total Carried Forward To Summary

1700 CLEARING AND GRUBBING

Item
No / Description / Unit / Quantity / Rate / Amount
R / c
17 / 1700 CLEARING AND GRUBBING
B17.01 / Clearing and grubbing (Provisional) / ha / 2.5
B17.02 / Removal and grubbing of large trees and tree stumps / No / 10.0
B17.04 / Cleaning and grubbing at inlets and outlets of hydraulic structures / m³ / 25.0
B17.05 / Clearing out of hydraulic structures / m³ / 25.0
Total Carried Forward To Summary

1800 DAYWORKS

Item
No / Description / Unit / Quantity / Rate / Amount
R / c
SECTION B1800: DAYWORKS
B18.01 / Personnel during normal working hours
(a) Unskilled labour / h / 200.0
(b) Semi-skilled labour / h / 200.0
(c) Skilled labour / h / 200.0
(d) Ganger / h / 200.0
(e) Flagmen / h / 200.0
B18.02 / Equipment
(a) Excavators on tracks from 70 kW up to 100 kW and mass 25t / h / 80.0
(b) Tractor-loader-backhoe
(i) Rubber tyred up to 50 kW and mass 7t / h / 80.0
(c) Self-propelled compactors
(i) Vibrating roller up to 1,0 m wide and mass 1,5 t / h / 80.0
(ii) Vibrating roller more than 80 kW and mass 8 t / h / 80.0
(d) Tipper truck up to 10t capacity / h / 80.0
Water trucks up to 10 000 l / h / 80.0
Motor grader from 95 kW up to 120 kW and mass 16 t / h / 80.0
B18.03 / Materials
Procurement of materials / Prov Sum / 1.0
Contractor's handling costs, profit and all other charges in respect to subitem B18.03(a) / % / 150,000.0
B18.04 / Transport
LDV / km / 3,200.0
Flatbed truck / km / 1,000.0
Total Carried Forward To Summary

2100 DRAINS

Item
No / Description / Unit / Quantity / Rate / Amount
R / c
21 / 2100 DRAINS
21.01 / Excavation for open drains :
i) 0 m up to 1,5 m - material to spoil / m³ / 50.0
B21.02 / Clearing and shaping of existing open drains / m³ / 50.0
21.03 / Excavation for subsoil drainage systems
(a) Excavating soft material situated within the following depth ranges below the surface level:
(i) 0 m up to 1,5 m / m³ / 1,750.0
(b) Extra over subitem 21.03(a) for excavation in hard material, irrespective of depth / m³ / 50.0
21.04 / Impermeable backfilling to subsoil drainage systems
a) G6 material stabilised with 4% stabilising agent / m³ / 515.0
21.06 / Natural permeable material in subsoil drainage systems (crushed stone):
(b) Crushed stone obtained from commercial sources (19mm nom. size) / m³ / 515.0
21.08 / Pipes in subsoil drainage systems, normal duty complete with couplings
i) 110mm perforated or slotted / m / 800.0
ii) 110mm unperforated (carrier) / m / 200.0
(iii) 160 mm internal diameter perforated or slotted / m / 2,000.0
iv) 160 mm unperforated (carrier) / m / 800.0
21.07 / Natural permeable material in subsoil drainage systems (sand):
(b) Sand from commercial source - coarse river sand / m³ / 1,050.0
21,10 / Synthetic-fibre filter fabric
(i) Grade 2 needle punched non-woven / m / 3,800.0
Total Carried Forward To Summary

2200 PREFABRICATED CULVERTS

Item
No / Description / Unit / Quantity / Rate / Amount
R / c
22 / PREFABRICATED CULVERTS
B22.01 / Excavation
(a) Excavating soft material situated within the following depth ranges below the surface level:
(1) 0 m up to 1.5 m / m3 / 2,300.0
(2) Exceeding 1,5 m and up to 3,0 m / m3 / 450.0
(3) Exceeding 3,0 m and up to 4,5 m / m³ / 10.0
(b) Extra over subitem 22.01(a) for excavation in hard material, irrespective of depth / m3 / 175.0
B22.02 / Backfilling:
a) Using the excavated material / m3 / 210.0
(b) Using imported selected material / m3 / 630.0
22.03 / Concrete pipe culverts:
(c) On class C bedding
(4) 600mm dia. Class 100D / m / 1,040.0
B22.12 / Removing existing concrete
(a) Plain concrete / m³ / 5.0
(b) Reinforced concrete / m³ / 5.0
(c) Brick / m³ / 5.0
B22.17 / Manholes, catchpits, precast inlet and outlet structures complete
(a) Manholes
(i) As per Drwng No. STD 036 / No / 5.0
(b) Catch pits : Refer to Drwg STD 028
(i) Single splay / No / 5.0
(ii) Double splay / No / 11.0
(c) Outlet structure
(i) As per Drwg No. STD 016 / No / 5.0
B22.23 / Service ducts
(a) Ordinary pipes, 160mm PVC / m / 50.0
B22.29 / Breaking into existing drainage structures and building in pipes or culvers of diameter between 450mm - 750mm / No / 2.0
Total Carried Forward To Summary

2300 CONCRETE KERBING, CONCRETE CHANNELLING, CHUTES AND DOWNPIPES, AND CONCRETE LININGS FOR OPEN DRAINS

Item
No / Description / Unit / Quantity / Rate / Amount
R / c
23 / 2300 CONCRETE KERBING, CONCRETE CHANNELLING, CHUTES AND DOWNPIPES, AND CONCRETE LININGS FOR OPEN DRAINS
23.01 / Concrete kerbing
(a) Precast kerbing to SABS 927
(ii) Fig 4 / m / 2,600.0
vi) Fig 8c (mountable) / m / 2,600.0
xii) Fig 12 / m / 5,200.0
23.07 / Trimming of excavations for concrete-lined open drains
a) In soft material / m³ / 125.0
23.08 / Concrete lining for open drains, 100mm thick using 25Mpa Concrete
ii) 1000 mm wide toe drain / m3 / 85.0
b) Class U2 surface finish to cast insitu concrete
ii) 1000 mm wide toe drain / m2 / 165.0
23.09 / Formwork to cast insitu concrete lining for open drains (Class F2 surface finish)
b) to sides with formwork on both internal and external / m2 / 20.0
c) To ends of slabs / m2 / 10.0
23.12 / Steel reinforcement
c) Welded steel fabric (Ref 193 Mesh) / kg / 320.0
23/16.02 / Overhaul on material hauled in excess of 1,0 km (ordinary overhaul) / m3-km / 300.0
B23.14 / Cutting bituminous surfacing and pavement layers for concrete kerbing, channelling or concrete lined drains / m / 25.0
B23.16 / Demolition and removal of existing kerbs and/channels / m³ / 10.0
B23.17 / Extra over item 23.01 and 23.02 concrete kerbing and channelling on curves:
(a) on curves with radii equal to 5,0m but less than 20m / m / 100.0
B23.18 / Extra over item 23.02 for drop kerbs at pedestrian crossings and driveways / m / 100.0
Total Carried Forward To Summary

3300 MASS EARTHWORKS

Item
No / Description / Unit / Quantity / Rate / Amount
R / c
33 / 3300 MASS EARTHWORKS
B33.01 / Cut and borrow to fill including free-haul up to 1,0 km:
(a) Material in compacted layer thickness of 200mm and less, compacted to 93% of Mod AASHTO density
(i) Compacted to 93% of modified AASHTO density / m³ / 1,550.0
(e) Pioneer layer / m³ / 120.0
33.03 / Extra over item 33.01 for excavating and breaking down material in :
a) Intermediate excavation / m³ / 150.0
B33.04 / Cut to stockpile or spoil, including free-haul up to 1,0 km. Material obtained from:
(a) Soft excavation / m³ / 6,000.0
(b) Intermediate excavation / m³ / 4,000.0
33.07 / Removal of unsuitable material (including freehaul of 1,0 km)
b) In layer thicknesses exceeding 200 mm:
i) Stable material / m³ / 6,250.0
33.14 / Extra over item 33.01 for excavating material from the pavement and fills of existing roads :
a) Non-cemented material / m³ / 4,675.0
33/16.02 / Overhaul on material hauled in excess of 1.0 km (ordinary overhaul) / m3-km / 32,500.0
Total Carried Forward To Summary

3400 PAVEMENT LAYERS OF GRAVEL MATERIAL

Item
No / Description / Unit / Quantity / Rate / Amount
R / c
34 / PAVEMENT LAYERS OF GRAVEL MATERIAL
34.01 / Pavement layers constructed from gravel taken from cut or borrow, including free haul up to 1,0 km
(a) Gravel selected layer compacted to:
(1) 93% of modified AASHTO density- 200mm thick / m³ / 7,858.0
(c) Gravel subbase (unstabilized gravel) compacted to:
(1) 95% of modified AASHTO density - 150mm thick / m³ / 5,900.0
(d) Gravel subbase (chemically stabilized material) compacted to:
(2) 96% of modified AASHTO density (in thickness range 100mm - 125mm) / m³ / 650.0
(f) Gravel base (chemically stabilized material) compacted to:
(1) 97% of modified AASHTO density (in thickness range 100mm - 125mm) / m³ / 3,800.0
34/16.02 / Overhaul on material hauled in excess of 1,0 km (ordinary overhaul) / m3-km / 36,450.0
Total Carried Forward To Summary

3500 STABILIZATION

Item
No / Description / Unit / Quantity / Rate / Amount
R / c
35 / STABILIZATION
35.01 / Chemical stabilization extra over unstabilized compacted layers
(b) Sub-base
(2) 125mm thickness / m³ / 650.0
(c) Base
(2) 125mm thickness / m³ / 3,800.0
35.02 / Chemical stabilizing agent:
(a) Ordinary portland cement / t / 275.0
35.04 / Provision and application of water for curing / kl / 20,000.0
35.06 / Curing with bituminous membrane:
(a) MC 30 cut-back bitumen / l / 30,340.0
Total Carried Forward To Summary

5100 PITCHING, STONEWORK AND PROTECTION AGAINST EROSION