15-098R1 F3M Dorseybank52 Baltarugby G82P and Rugbypg 06 16 to 06 18

15-098R1 F3M Dorseybank52 Baltarugby G82P and Rugbypg 06 16 to 06 18

TEMPORARY OPERATING INSTRUCTION / No. / 15-098R1

O.O.

/ 15-05314 (F3M)
15-03724(BK52)
15-04938 (Balt-Rgby)
15-05655 (G82P)
15-05339/ 15-05846 (Rgby-PG) /

MISO No.

/ 1-07806842
1-08007201
1-07682236
1-08330422
1-07808269/ 1-08331278 /

File No.

/

240803

Name of Outage: / 115 kV Line F3M (Fort Francis –Running) and,
Dorsey 230 - 500 kV Bank 52 and,
230 kV Line Balta – Rugby and,
230 kV Line G82P (Glenboro – Peace Garden) and,
230 kV Line Rugby – Peace Garden
Effective Dates: / 2015-06-16from0700 to 2015-06-18 at 1830 CDT
(2015-06-16from 0700 to 2015-06-18 at 1830EST)
Standing Guide Reference: / MHEX – USA Special Study as per K. Long 2015-06-02
Description of Work: / F3M (IESO/MP) - Fiber work on double circuit lines.
Dorsey 230 - 500 kV Bank 52 (MHEB) – Replace Kiosk/Controls, Cap Bank Mtce
Balta-Rugby (GRE/OTP) - Moving line to allow for 230-115 kV transformer at Rugby
G82P (MHEB) – System Posturing for Rugby Terminal work.
Rugby – Peace Garden (GRE/OTP) – Rugby Bus Outage
TRANSFER LIMITS:
MH-USA South (MH Export)
SOL: / 1650 / Schedule Limit / 1425
Location / RM / CRSG / OM / Schedule Limit
TTC / Transfer (SOL) / Firm / Non-Firm
USA / 1900 / 250 / 1650 / 150 / 75 / 1425 / 0 / 1425
MH-USA North (MH Import)
IROL / 700 / SOL: / 465 / Schedule Limit / 415
Location / RM / CRSG / OM / Schedule Limit
TTC / Transfer (SOL) / Firm / Non-Firm
USA / 600 / 135 / 465 / 0 / 465 / 0 / 415 / 415
TLR Triggers / South TLR 1 / South TLR 3 / North TLR 1 / North TLR 3
1485 / 1500 / 432 / 442
MISO Webtool Postings /
MISO Webtool Postings / TTC / TRM / Coeff
MHEX_S (Export) / 1900 / 475 / 1.000
MHEX_N (Import) / 600 / 600 / 0.308

In addition to the TLAP table, the following Real Time (pre-contingent) transfer limits must also be

maintained.

D603M (Remaining 500 kV Bank):

TRANSFER
LIMITS:
D603M_S /
TTC / Transfer (SOL)
1188 / 1188
TLR Triggers / D603M_S TLR 1 / D603M_S TLR 3
1036 / 1046
Special Notes to MISO West RC / A) During this prior outage condition generation curtailment of the St. Joseph and St. Leon wind farms concurrent with TLR on MHEX_N may be required when Manitoba to USA flows are north to prevent post contingent overloads on G37C following a trip of B10T or D602F.
B) The SOL for MHEX_S and MHEX_ N is the same if the MISO RTCA and MISO Flowgate Monitoring Tool is unavailable prior to or during this outage.
Special Instructions to MHEB Operator: / A)TOI Extentions - This TOI may be extended until 23:59 by performing the following steps:
  1. Verify system conditions to confirm there are no additional tie line facilities outages, or new internal MH outages.
  2. Review RTCA to confirm there are no new contingencies.
  3. Contact MISO to confirm there are no new outages, if there are no new outages provide notice to MISO that MH is extending the TOI.
  4. Extend the outage in COLA.
  5. Update TLAP outage table.
  6. Provide notice to affected balancing authorities
B)When called upon by MISO for the supply of CRSG:
If Real Time Contingency Analysis (RTCA) indicates a post contingent overload condition on Y51L for the contingent loss of D14S - redispatch MH generation to maintain CRSG delivery as per:
  • Start Brandon Gas Generation and run up to 60 MW.
Brandon generation must be re-dispatched from HVDC generation at Dorsey
  • After 60 MW re-dispatch is complete, should RTCA continues to indicate a post contingent overload condition on Y51L due to the contingent loss of D14S,
Continue to re-dispatch generation from Brandon gas in 10 MW increments until post contingent overload on Y51L has been mitigated.
  • The mitigation must be completed within 30 minutes.
C) For MHEX_N:
  • The MHEX_N will at all times remain below 465 MW as measured at Dorsey, Letellier, and Glenboro Stations.
  • Manitoba Hydro will self-supply part of the CRSG as follows:
Self-Supply (CRSG - NonFirm) - MHEX_S MW + MHEX_N MW.
(415– 415) - MHEX_S MW + MHEX_N MW.
0 + MHEX_N MW.
D) Ambient Limits - For the duration of the Dorsey T52 outage, ambient temperature limits can be implemented allowing for an increase in the SCADA alarm level to a 30 deg C rating of 2983 A or 1188 MVA.
Prepared By: / J. Cameron / Date: / 20150521
Revised By: / J. Cameron / Date: / 2015 06 02

Copies to:

SOSS, System Control CentreMISO

NSSS, System Control CentreGSO, System Control Centre

GSSS, System Control Centre

15-098R1_F3M_DorseyBank52_BaltaRugby_G82P_and_RugbyPG_06_16_to_06_18.doc / Page 1 of 4