1. Communication Availability:

1. Communication Availability:

EQAG COMMUNICATION SECTION

MONTH & YEAR – May 2006

1. COMMUNICATION AVAILABILITY: -

Communication System Indices / May 2006 (%) / May 2005 (%) / Achieved for FY 2006 / Target for the FY 2007
Protection Channels / 99.95 / 99.96 % on average basis / 99.97 / 99.9
Data channels / 99.96 / 99.98 / 98.0
Voice system / 99.98 / 99.59 / 99.0

The method of calculating the Communication availability index is revised and divided into 3 parts as shown above from the month of October 2005.

Method of calculating Communication availability is changed to individual down time, aggregating the total down time then applying the following formula –

% availability =

Availability Figure / System / Channels affected
Protection / 99.95 % / The Salsette – Kalyan Fiber Optic link was out for 14 hrs between 18.00hrs on 31st May 06 to 10.00 hrs on 1st June 06. The carrier acceleration for Salsette – Kalyan straight 110 kv and Salsette – Kalwa – Kalyan 110 kv T line remained out because of new jointing bad patch cord at Kalwa.
Data / 99.96 % / The Salsette – Kalyan Fiber Optic link was out for 14 hrs between 18.00 hrs on 31st May 06 to 10.00 hrs on 1st June 06. The SMS data, ABT metering data from Kalyan and Ambernath remained out because of new jointing bad patch cord at Kalwa.
Voice / 99.98 % / The Salsette – Kalyan Fiber Optic link was out for 14 hrs between 18.00 hrs on 31st May 06 to 10.00 hrs on 1st June 06. The dialing to and fro Kalyan and Salsette remained out because of new jointing bad patch cord at Kalwa.
2. MAJOR INVESTIGATION & OCCURRENCES: -
Date / Division / Station / OCCURRENCES / INVESTIGATION
NIL
  1. COMMISSIONING / PROJECT ACTIVITIES : -

Date / Division / Description
1. Chembur Scada connectivity
04 May 06 / Scada connectivity for Chembur upto Dharavi is connected through CCR network.
2. New Telephone exchanges for the System
04, 05, 06 May 06 / Installation and IP audit for new exchanges at Bhira, Mulshi and Davdi.
10, 11, 12, 13 May 06 / Installation of new exchange at Saki.
17 May 06 / Installation of new exchange at BKC, Mahalaxmi.
3. Fibre Optic connectivity for Ambernath. & Bhivpuri
30 May 06 / Bhivpuri SMS data has been transferred on new Bhivpuri – Khopoli FOX 20 and existing Dharavi – Trombay links.
30 May 06 / Party line telephone (hot line) extended from LDD to Bhivpuri on new Bhivpuri – Khopoli FOX 20 links and existing Dharavi – Trombay links.
4. Fibre Optic connectivity for Kalwa
27 - 31 May 06 / The Fiber cable at Tower 77 on Salsette – Kalyan OPGW is rerouted through Kalwa C/R is completed. The 2 nos. FOX 20 equipment has been installed at Kalwa carrier room for establishing new links between Salsette – Kalwa and Kalwa – Kalyan for ABT metering data to Tata LDC and Line protection.
5. Distribution Automation System for Saki, Borivli and Central Mumbai Areas.
May 06 / No further progress.
  1. RETROFITTING JOBS: -

Date / Division / Description
27 May 06 / Kalwa / The FOX 20 panels earlier working between Trombay MW Central Station to LDC has been installed at Kalwa for establishing links between Salsette – Kalwa and Kalwa – Kalyan.
  1. BREAKDOWN MAINTENANCE ACTIVITIES : -

Date / Division / Description
24 May 06 / MSEB Kalwa / The modem of ABT metering at MSEB Kalwa end had hanged. On switching OFF/ON the 230 V supply to the modem, the modem started working. This matter needs to be taken up with Secure meters on priority.
26 May 06 / MSEB Borivli / The modem of ABT metering at MSEB Borivli end had also hanged. On switching OFF/ON the 230 V supply to the modem, the modem started working. This matter needs to be taken up with Secure meters on priority.
  1. PREVENTIVE MAINTAINANCE ACTIVITIES.

Date / Station / Link / Description
15.05.06 / Dharavi / PM completed
18.05.06 / Carnac and Bombay House / PM completed
19.05.06 / Dongarwadi for Bhira. / PM completed
20.05.06 / Tadgaon repeater station for Bhira. / PM completed
23.05.06 / Kolshet / PM completed
24.05.06 / Matheran repeater for Bhira, Khopoli & Bhivpuri. / PM completed
25.05.06 / Khopoli & Bhivpuri / PM completed
26.05.06 / Kalwa / PM completed
27.05.06 / Kalyan & Ambernath / PM completed
  1. PREVENTIVE MAINTAINANCE ACTIVITIES NOT COMPLETED

MW PM not carried out at Trombay Colony, RCF Chembur and Trombay.
FOP PM to be started.
PLCC PM to be started.
  1. Preventive Maintenance Completion Percentage

System / Percentage completion of PM for April 2006–March 2007.
April 05-March 06 / Till end of this month
Fibre Optic / 37.10 % / 0.00 %
Microwave / 25 % / 80.00 %
PLCC / 56.25 % / 0.00 %
Total / 38.30 % / 12.77 %

9. ADMINISTRATION AND MAN POWER DEVELOPMENT.

Date / Name / Description
NIL

10.COST OF REWORK FOR POOR QUALITY OF RECEIVED MATERIAL / EQUIPMENT.

Modems & adapter received from Secure after repairs were found to be defective & were unusable.
  1. K-HUB

Date / TOPIC
06 May 06 / A lecture on “Communication System for DAS on CDMA” was delivered by Mr. C Selvin to the audiences from IIT, TCE, ERDA and TPC at Dharavi.
06 May 06 / A lecture on “New IP based exchanges” being commissioned in TPC network with their dialing plan and features was delivered by H V Bahl to the TPC officers at Dharavi.