Product Descriptions Overview

Prince2 2009 Documentation

PRINCE2® PRODUCT DESCRIPTIONS

Release Status: FINAL

Author: John Aldridge, FMD Consultants Limited

Date:01 January 2016

Filename & Version:p2_product_descriptions_v01

Project ID:prince2_2009

Methodology: PRINCE2® 2009

FMD Consultants Limited assumes no responsibility for the usage of any information contained in this document and the way it is handled and disclaims all liability in respect of such information and its provision. Subject to this disclaimer, you may copy and utilise the material contained in the document.

This information is based on OGC PRINCE2® material. PRINCE2® is a registered trade mark of the Office of Government Commerce in the United Kingdom and other countries. All registered trademarks recognised & accepted.

Document Location

This document is stored in the following location:

Filename / p2_product_descriptions_v01
Location /

Revision History

This document has been through the following revisions:

Version No. Changed / Revision Date / Filename/Location stored: / Brief Summary of Changes
01 / 01/01/2016 / Released version

Authorisation

This document requires the following approvals:

AUTHORISATION / Name / Signature / Date
FMD Consultants Limited / John Aldridge / / 01/01/2016

Distribution

This document has been distributed to:

Name / Title / Version Issued / Date of Issue
n/a

Related Documents

Summary of filenames and locations of related documents:

Document Type / Filename/Location stored:

Contents

1Purpose

2Prince2® Process Model

3Prince2® Management Events

4Prince2® Management Products

5Prince2® Management Product templates

1Purpose

This purpose of this document is to provide an overview of PRINCE2® products, their typical usage and sequencing in a project, and to provide pointers to relevant product templates and product template descriptions.

2Prince2®Process Model

Prince2® Project Management Methodology consists of seven processes:

  • Start Up (SU)
  • Directing a Project (DP)
  • Initiating a Project (IP)
  • Managing Stage Boundary (MSB)
  • Controlling a Stage (CS)
  • Managing Product Delivery (MPD)
  • Closing a Project (CP)

These processes are graphically represented in the Prince2 Process Model, a summary of which is detailed below.

Prince2® Process Model summary[1]

Within each of these processes there are activities which create or update each of the PRINCE products, for example the lessons log is created in Starting up a Project, will be updated in Controlling a Stage and closed in Closing a Project.

3Prince2®Management Events

In total there are fifty-two products ranging (alphabetically) from acceptance record to work package. These products have been placed within a project plan to illustrate a typical sequence of management events. Note that this plan focuses on the typical sequence of activities from the Project Mandate through to project closure notification. The work required to produce products (deliverables) from the project is typically broken down into manageable stages and each of these stages completed before the next stage is authorised for execution. This plan details the production of products from only one stage (task ID 74, specialist products). In practice, on completing Report Stage End (task ID 105), the next stage would then be planned and authorised and the project plan would ‘loop back’ to Plan the Next Stage (task ID 54).

Please note that the final four activities (task ID 130 onwards):

  • Capture and examine risks
  • Escalate issues and risks
  • Take corrective action
  • Produce an exception plan

are ad-hoc activities and will be executed when required, typically when the project is not performing as forecast or within financial or time tolerances.

Task durations are for guidance only. The duration of each task is dependent on the complexity of the project, the level of quality management to be applied and the availability of relevant management and Project Office personnel. Each activity is shown as being dependent on the previous activity, however, in practice, these activities may overlap in some cases.

The resources detailed in the plan are as follows, the first resource listed against a task being responsible for that product’s production, update or closure:

co-Corporate/Programme

ex-Executive

su-Senior User

ss-Senior Supplier

pm-Project Manager

tm-Team Manager

pa-Project Assurance

ps-Project Support

The roles of this management team are described in greater detail in 4, PRINCE2® Management Products

The project plans are available for download in Microsoft Project 2007 format from


4Prince2® Management Products

Extracting the Prince2® Management Products from the project plan in 3above gives a clear picture where each product is created, updated, approved or closed. The table overleaf lists these products alphabetically, details the action against them, the PRINCE2® activity and PRINCE2® process in which this action takes place and the project plan ID where this action is carried out. In addition, this table gives the involvement of the management team for each management product in the form of:

p-Producer

r-Reviewer

a-Approver

The major responsibilities of the management team are:

Corporate/Programme Management – In general, this body will be responsible for the control of an organisation or a Programme. They sit outside the project but set the overall requirements and tolerance levels for the project. Any forecast breaches of project tolerance (time, cost or quality) should be reported to Corporate/Programme Management for guidance on their resolution or potentially premature closure of the project.

Executive – The executive is responsible for the Business Case for the duration of the project and is appointed by Corporate/Programme Management. He/she will usually be responsible for the Benefits Review Plan for the duration of the project and will either hand over the Benefits Review Plan to the Senior User on project closure. He/she should oversee the development of a viable business case, ensuring the project is aligned with corporate strategies, and securing appropriate funding for the project.

Senior User – Responsible for specifying the benefits upon which the Business Case is based. Ensure the desired outcome of the project is specified unambiguously. Ensure the project produces benefits which deliver the desired outcomes. Ensures the expected benefits are realised. Provide actual versus forecast benefits during benefits reviews.

Senior Supplier – May be within the organisation or an external organisation – responsible for confirming that the required products can be delivered within the expected costs and are viable.

Project Manager –Prepare the Business Case on behalf of the Executive. Carry out impact analysis of new or revised risks or issues which may impact the projects ability to meet requirements. Update the Business Case at the end of each Management Stage. Assess and report on performance at regular Project Board Meetings and project closure.

Team Manager – Overall control and co-ordination of teams responsible for producing products. Report any slippage or developmental problems during Project Stages.

Project Assurance – Assist in the development of the Business Case. Verify and monitor the Business Case against project progress and external events. Ensure the project fits with overall programme or corporate strategy. Monitor project finance on behalf of the customer. Ensure the value-for-money solution is constantly reassessed. Review the impact assessment of potential changes on the Business Case and Project Plan.

Project Support – The Business Case should be baselined therefore under configuration management. Project Support should notify the Project Manager of any proposed or actual changes to products which affect the Business Case.

Project ID: prince2_2009 / Doc Ref:p2_product_descriptions_v01
FMD Consultants Limited / Page 1 of 12 / Date of Issue: 01/01/2016

Product Descriptions Overview

Involvement
Document Name / Action / In Activity / In PRINCE Process / Template Plan ID / Responsible / corporate/programme / executive / senior user / senior supplier / project manager / team manager / project assurance / project support
acceptance record / obtain / Hand Over Products / cp / 118 / pm / 0 / a / a / a / P / 0 / r / 0
additional role descriptions / create / Select the Project Approach and assemble the Project Brief / su / 21 / pm / 0 / a / r / r / p / 0 / r / 0
update / Set up the Project Controls / ip / 41 / pm / 0 / a / a / a / p / 0 / r / 0
update / Create the Project Plan / ip / 48 / pm / 0 / a / a / a / p / 0 / r / 0
additional work estimates (premature closure) / create / Prepare Project Closure / cp / 113 / pm / 0 / a / a / a / p / 0 / r / 0
appoint executive / approve / Appoint the executive and the Project Manager / su / 4 / co / p / 0 / 0 / 0 / 0 / 0 / 0 / 0
appoint project manager / approve / Appoint the executive and the Project Manager / su / 6 / ex / a / p / 0 / 0 / 0 / 0 / 0 / 0
approval records / obtain / Execute a Work Package / mpd / 81 / tm / 0 / 0 / 0 / 0 / r / p / r / r
approve and appoint project management team / approve / Capture previous lessons / su / 14 / ex / a / p / 0 / 0 / 0 / 0 / 0 / 0
benefits review plan / create / Refine the Business Case / ip / 50 / pm / a / a / a / a / p / 0 / r / 0
update / Update the Business Case / msb / 102 / pm / r / a / a / a / p / 0 / r / 0
update / Hand Over Products / cp / 117 / pm / a / r / r / r / p / 0 / r / 0
checkpoint reports / create / Execute a Work Package / mpd / 78 / tm / 0 / 0 / 0 / 0 / r / p / 0 / 0
communication management strategy / create / Prepare the Communications Management Strategy / ip / 38 / pm / 0 / a / a / a / p / 0 / r / 0
configuration item records / create / Prepare the Configuration Management Strategy / ip / 32 / ps / 0 / 0 / 0 / 0 / a / 0 / r / p
update / Create the Project Plan / ip / 46 / ps / 0 / 0 / 0 / 0 / a / 0 / r / p
update / Plan the Next Stage / msb / 56 / pm / 0 / 0 / 0 / 0 / p / 0 / r / r
update / Authorise a Work Package / cs / 62 / ps / 0 / 0 / 0 / 0 / a / r / r / p
update / Execute a Work Package / mpd / 76 / ps / 0 / 0 / 0 / 0 / 0 / p / 0 / p
update / Receive Completed Work Package / cs / 86 / ps / 0 / 0 / 0 / 0 / a / r / r / p
update / Hand Over Products / cp / 116 / pm / 0 / 0 / 0 / 0 / a / 0 / r / p
update / Take corrective action / cs / 148 / pm / 0 / 0 / 0 / 0 / p / r / 0 / r
update / Produce an exception plan / cs / 154 / pm / 0 / 0 / 0 / 0 / r / 0 / r / p
configuration management strategy / create / Prepare the Configuration Management Strategy / ip / 31 / pm / 0 / a / a / a / p / 0 / r / 0
daily log / create / Appoint the executive and the Project Manager / su / 7 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Capture previous lessons / su / 11 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Prepare the Outline Business Case / su / 18 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Select the Project Approach and assemble the Project Brief / su / 23 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Plan the Initiation Stage / su / 26 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Capture and examine risks / cs / 132 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Take corrective action / cs / 149 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
close / Recommend Project Closure / cp / 126 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
detailed business case / create / Refine the Business Case / ip / 51 / pm / r / a / a / a / p / 0 / r / 0
update / Update the Business Case / msb / 101 / pm / r / a / a / a / p / 0 / r / 0
draft project closure notification / prepare / Recommend Project Closure / cp / 128 / pm / 0 / a / a / a / p / 0 / r / 0
end project report / create / Evaluate the Project / cp / 120 / pm / 0 / a / a / a / p / 0 / r / 0
end stage report (current stage) / create / Report Stage End / msb / 106 / pm / 0 / a / a / a / p / 0 / r / 0
exception plan / create / Produce an exception plan / cs / 153 / pm / 0 / a / a / a / p / 0 / r / 0
exception report / create / Escalate issues and risks / cs / 138 / pm / 0 / a / r / r / p / 0 / r / 0
executive role description / create / Appoint the executive and the Project Manager / su / 3 / co / p / 0 / 0 / 0 / 0 / 0 / 0 / 0
follow-on actions recommendation (project) / create / Hand Over Products / cp / 115 / pm / 0 / a / a / a / p / 0 / r / 0
follow-on actions recommendation (stage) / create / Report Stage End / msb / 108 / pm / 0 / a / a / a / p / 0 / r / 0
highlight report / create / Report Highlights / cs / 95 / pm / 0 / 0 / 0 / 0 / p / 0 / r / 0
issue / raise / Execute a Work Package / mpd / 79 / tm / 0 / 0 / 0 / 0 / r / p / 0 / 0
issue register / create / Prepare the Configuration Management Strategy / ip / 33 / ps / 0 / 0 / 0 / 0 / a / 0 / r / p
update / Plan the Next Stage / msb / 58 / pm / 0 / 0 / 0 / 0 / p / 0 / r / 0
update / Authorise a Work Package / cs / 65 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Update the Project Plan / msb1 / 99 / pm / 0 / 0 / 0 / 0 / p / 0 / r / 0
update / Update the Business Case / msb1 / 104 / pm / 0 / 0 / 0 / 0 / p / 0 / r / 0
update / Capture and examine risks / cs / 134 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Escalate issues and risks / cs / 140 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Take corrective action / cs / 144 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Produce an exception plan / cs / 156 / pm / 0 / 0 / 0 / 0 / p / 0 / r / 0
close / Review the Stage Status / cs / 90 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
close / Recommend Project Closure / cp / 123 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
issue register (premature closure) / update / Prepare Project Closure / cp / 110 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
issue report / create / Review the Stage Status / cs / 93 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
create / Capture and examine risks / cs / 133 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
create / Escalate issues and risks / cs / 139 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
create / Take corrective action / cs / 146 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
lessons log / create / Capture previous lessons / su / 9 / pm / 0 / r / 0 / 0 / p / 0 / 0 / 0
update / Review the Stage Status / cs / 92 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
close / Recommend Project Closure / cp / 127 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
lessons report / create / Report Stage End / msb / 107 / pm / 0 / a / a / a / p / 0 / r / 0
create / Evaluate the Project / cp / 121 / pm / 0 / a / a / a / p / 0 / r / 0
Outline business case / create / Prepare the Outline Business Case / su / 16 / ex / a / p / r / r / r / r / 0
product descriptions / create / Create the Project Plan / ip / 45 / pm / 0 / a / a / a / p / 0 / r / 0
project approach / create / Select the Project Approach and assemble the Project Brief / su / 20 / pm / 0 / a / r / r / p / 0 / r / 0
project brief / create / Select the Project Approach and assemble the Project Brief / su / 22 / pm / 0 / a / r / r / p / 0 / r / 0
project controls / create / Set up the Project Controls / ip / 40 / pm / 0 / a / a / a / p / 0 / r / 0
project initiation document / create / Assemble the Project Initiation Document / ip / 53 / pm / 0 / a / a / a / p / 0 / r / 0
update / Produce an exception plan / cs / 152 / pm / r / a / a / a / p / 0 / r / 0
project management team role descriptions / create / Capture previous lessons / su / 12 / pm / 0 / a / 0 / 0 / p / 0 / 0 / 0
project management team structure / create / Capture previous lessons / su / 13 / pm / 0 / a / 0 / 0 / p / 0 / 0 / 0
update / Set up the Project Controls / ip / 42 / pm / 0 / a / a / a / p / 0 / 0 / 0
update / Create the Project Plan / ip / 47 / pm / 0 / a / a / a / p / 0 / r / 0
project manager role description / create / Appoint the executive and the Project Manager / su / 5 / ex / a / p / 0 / 0 / 0 / 0 / 0 / 0
project mandate / create / Appoint the executive and the Project Manager / su / 2 / co / p / 0 / 0 / 0 / 0 / 0 / 0 / 0
project plan / create / Create the Project Plan / ip / 44 / pm / 0 / a / a / a / p / 0 / r / 0
update / Update the Project Plan / msb / 97 / pm / 0 / a / a / a / p / 0 / r / 0
update / Prepare Project Closure / cp / 111 / pm / 0 / 0 / 0 / 0 / p / 0 / r / 0
project product descriptions / create / Prepare the Outline Business Case / su / 17 / pm / 0 / a / a / a / p / 0 / r / 0
project status account / create / Prepare Project Closure / cp / 112 / ps / 0 / 0 / 0 / 0 / r / 0 / r / p
quality management strategy / create / Prepare the Quality Management Strategy / ip / 35 / pm / 0 / a / a / a / p / 0 / r / 0
quality register / create / Prepare the Quality Management Strategy / ip / 36 / ps / 0 / 0 / 0 / 0 / a / 0 / r / p
update / Plan the Next Stage / msb / 59 / ps / 0 / 0 / 0 / 0 / r / 0 / r / p
update / Authorise a Work Package / cs / 63 / ps / 0 / 0 / 0 / 0 / r / r / r / p
update / Accept a Work Package / mpd / 71 / ps / 0 / 0 / 0 / 0 / r / r / 0 / p
update / Execute a Work Package / mpd / 75 / ps / 0 / 0 / 0 / 0 / r / r / 0 / p
update / Produce an exception plan / cs / 157 / pm / 0 / 0 / 0 / 0 / r / 0 / r / p
close / Recommend Project Closure / cp / 125 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
risk / raise / Accept a Work Package / mpd / 70 / tm / 0 / 0 / 0 / 0 / r / p / 0 / 0
raise / Execute a Work Package / mpd / 80 / tm / 0 / 0 / 0 / 0 / r / p / 0 / 0
risk management strategy / create / Prepare the Risk Management Strategy / ip / 28 / pm / 0 / a / a / a / p / 0 / r / 0
risk register / create / Prepare the Risk Management Strategy / ip / 29 / ps / 0 / 0 / 0 / 0 / a / 0 / r / p
update / Plan the Next Stage / msb / 57 / pm / 0 / 0 / 0 / 0 / p / 0 / r / 0
update / Authorise a Work Package / cs / 64 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Update the Project Plan / msb1 / 98 / pm / 0 / 0 / 0 / 0 / p / 0 / r / 0
update / Update the Business Case / msb1 / 103 / pm / 0 / 0 / 0 / 0 / p / 0 / r / 0
update / Capture and examine risks / cs / 135 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Escalate issues and risks / cs / 141 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Take corrective action / cs / 145 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
update / Produce an exception plan / cs / 155 / pm / 0 / 0 / 0 / 0 / p / 0 / r / 0
update / Review the Stage Status / cs / 89 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
close / Recommend Project Closure / cp / 124 / pm / 0 / 0 / 0 / 0 / p / 0 / 0 / 0
specialist products / create / Execute a Work Package / mpd / 74 / tm / 0 / a / a / a / r / p / r / 0
stage plan / create / Plan the Next Stage / msb / 55 / pm / 0 / a / a / a / p / 0 / r / 0
update / Authorise a Work Package / cs / 67 / pm / 0 / 0 / 0 / 0 / p / r / r / 0
update / Receive Completed Work Package / cs / 87 / pm / 0 / 0 / 0 / 0 / p / 0 / r / 0
update / Review the Stage Status / cs / 91 / pm / 0 / 0 / 0 / 0 / p / 0 / r / 0
update / Take corrective action / cs / 147 / pm / 0 / 0 / 0 / 0 / p / r / 0 / r
stage plan (initiation) / create / Plan the Initiation Stage / su / 25 / pm / 0 / a / a / a / p / 0 / r / 0
team plan / create / Authorise a Work Package / cs / 66 / tm / 0 / 0 / 0 / a / a / p / r / 0
update / Accept a Work Package / mpd / 69 / tm / 0 / 0 / 0 / a / a / p / r / 0
update / Execute a Work Package / mpd / 77 / tm / 0 / 0 / 0 / 0 / 0 / p / r / 0
update / Deliver a Work Package / mpd / 84 / tm / 0 / 0 / 0 / 0 / r / p / r / 0
work package / create / Plan the Next Stage / cs / 60 / pm / 0 / 0 / 0 / 0 / p / a / r / 0
approve / Accept a Work Package / mpd / 72 / pm / 0 / 0 / 0 / 0 / p / a / r / 0
update / Deliver a Work Package / mpd / 83 / tm / 0 / 0 / 0 / 0 / a / p / r / 0
Project ID: prince2_2009 / Doc Ref:p2_product_descriptions_v01
FMD Consultants Limited / Page 1 of 12 / Date of Issue: 01/01/2016

Product Descriptions Overview

5Prince2® Management Product templates

These products are available from :

Prince2 Management Product / Template
acceptance record / 
approval records / [2]
benefits review plan / 
business case / 
business case responsibilities / 
checkpoint reports / 
communication management strategy / 
configuration item records / 
configuration management strategy / 
daily log / 
end project report / 
end stage report (current stage) / 
exception report / 
executive role description / [3]
highlight report / 
issue register / 
issue report / 
lessons log / 
lessons report / 
product descriptions / 
product status account / 
project approach / [4]
project brief / 
project controls ??? / 
project initiation document / 
project initiation plan / 
project management team role descriptions / 
project management team structure / 
project manager role description / 
project mandate / [2]
project plan / 
project product descriptions / 
project status account / 
quality management strategy / 
quality register / 
risk management strategy / 
risk register / 
roles and responsibilities / 
work package / [2]
Additional Management Products
post project review plan / 
product checklist / 
request for change / 

----- end of document -----

Project ID: prince2_2009 / Doc Ref:p2_product_descriptions_v01
FMD Consultants Limited / Page 1 of 12 / Date of Issue: 01/01/2016

[1]A PDF version of the full Prince2® Process Model can be obtained from the downloads tab of the ILX website,

[2]Company specific format and standards

[3]Incorporated in Roles & Responsibilities

[4]Incorporated in Project Brief

[2]

[2]