Plan Id: 597Plan Description: Job Services Australia Program Risk Plan 2012-13Version: 4

DEEWR Risk Management Plan

Access: Open

Plan ID / 597
Plan Description / Job Services Australia Program Risk Plan 2012-13
Plan Type / Program
Current Status / Submitted for Approval
Next Review Date / 30/04/2013
Plan Owner / LAKER, Linda (LL0063)
Plan Approver / DRAYTON, Moya (MD2889)
Date Last Updated / 07/12/2012
Organisation Unit / 50030089

RISK MANAGEMENT PLAN PROFILE

Risk Rating Summary / -
Number of Risks / 10
Risk Rating / Current - Operational / Current - Departmental / Target - Operational / Target - Departmental
Low / 3 / 3 / 10 / 10
Medium / 6 / 6 / - / -
High / 1 / 1 / - / -
Extreme / - / - / - / -
Treatment Summary / -
Number of Treatments / 38
Treatment Status / Ongoing / Proposed / Completed
- / 38 / 0 / 0

CONTEXT

Objectives / Purpose, budget, timeframes, and impact on staff etc. Refer to program guidelines, business plans or other documentation.
- / Job Services Australia will help to boost employment participation and the productive capacity of the Australian workforce, address skills shortage areas and better meet the needs of employers through:
tailored assistance for job seekers;
early assistance to the most disadvantaged job seekers;
better meeting the skills needs of employers;
enhancing opportunities for work experience, including Work for the Dole and Green Corps;
an effective compliance system; and
streamlining programs and processes to reduce the burden of administration and red tape, which will cut the costs for JSA providers.
Environment / Internal and external environment including legal, regulatory, policy requirements such as FMA Act, relevant standards etc.
- / Legal and regulatory requirements which must be complied with in the implementation and delivery of Job Services Australia.
2012-15 Employment Services Contractand Funding Deed
Social Security Act 1991
Financial Management and Accountability Act 1997 and DEEWR Chief Executive Instructions
Commonwealth Procurement Guidelines
Job Seeker Compliance Framework
Contract Management Framework and the Employment Services Charter Of Contract Management (employment services)
Privacy Act 1988
Freedom Of Information Act 1989
Departmental probity requirements
Commonwealth Fraud Control guidelines
Additional legal and regulatory requirements will be considered on a project by project basis. These may include enabling program legislation and Electronic Transaction Act.
Stakeholders / Internal and external stakeholders.
- / Federal Ministers – Minister Ellis, Minister Shorten, Minister Collins.
DEEWR National office staff – Employment Cluster.
DEEWR state office staff – Account and Contract Managers.
Job Services Australia Providers.
Job Seekers.
Department of Human Services.
Peak bodies i.e. NESA, Jobs Australia, ACOSS.
Risk History / Details of major risk exposure during the past three years, explanation of how the risks occurred and any corrective action taken.
- / No major risks incidents have occurred since the implementation of the Job Services Australia model on 1 July 2009.
Related Plans / Plan ID / Plan Description / Relationship
597 / Job Services Australia Program Risk Plan 2012-13 / Other
597 / Job Services Australia Program Risk Plan 2012-13 / Other
597 / Job Services Australia Program Risk Plan 2012-13 / Parent

RISK SUMMARY

Risk ID / Risk Description / Risk Category / Current Operational Rating / Current Departmental Rating / No. of Treatments / No. of Events
5467 / Providers obtain unfair gains through:
claim of payments to which they are not entitled;
manipulation of records in relation to the provider’s performance of the Employment Services Deed; and
Unauthorised access to confidential information / Fraud / High / Medium / 7 / -
5468 / The financial stability of JSA providers in times of economic change is jeopardised through:
poor financial practices or business models;
lack of internal adaptive change management processes; and
low caseload flows. / Strategic / Medium / Medium / 3 / -
5471 / The public image of JSA funded programs is adversely affected by:
ineffective engagement and management of stakeholders by policy and program areas;
miscommunications to Providers and other stakeholders; and
lack of shared commitment to a positive image of JSA. / Stakeholder/Relationship / Medium / Medium / 2 / -
13594 / Inconsistent management of Deed leads to failure to achieve program objectives. / Implementation/Service Delivery / Medium / Medium / 3 / -
13595 / Data and Intelligence is not used efficiently and effectively to identify non-compliant provider behaviour. / Implementation/Service Delivery / Medium / Medium / 6 / -
13596 / Reduction in department resourcing and skills base jeopardises the effectiveness of JSA program. / Resource Management / Low / Medium / 3 / -
13597 / ESS functionality and capability does not meet the specified program and or business policy need including supporting providers in their business. / Planning/Processes / Low / Low / 8 / -
13598 / Failure to align and deliver policy and program agendas across agencies (particularly DHS) inhibit the delivery of desired objectives. / Implementation/Service Delivery / Medium / High / 2 / -
13601 / Inability to rapidly change JSA administration to meet changing political, economic or policy environment. / Planning/Policy / Medium / Low / 3 / -
13602 / Mismatch of job seeker expectations about entitlements and obligations leads to reputational damage. / Reputational / Low / Low / 1 / -

TREATMENT SUMMARY

Treatment ID / Treatment Description / Treatment Owner / Mitigation/ Contingency / Treatment Status / Next Review Date / No. of Related Risks / No. of Monitoring Notes
10249 / Program level risk assessment are:
Maintained; and
Reviewed by all relevant parties. / Redacted / Mitigation / Ongoing / 18/01/2013 / 1 / 3
10256 / Effective communication strategies facilitate:
productive consultation and liaison with key stakeholders and leading industry bodies;
the discussion and management of emerging issues with all stakeholders;
ongoing dialogue between National Office, State Office and program areas to develop, implement and maintain program assurance and contract management activities;
reporting the results of assurance activities; and
promulgating positive outcomes and lessons learned. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 3
10261 / Identify, initiate and manage strategic partnerships outside the department to improve service delivery and achieve required outcomes. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 3
10270 / Enforce the Deed requirement that providers submit financial statements to the department for testing financial viability. / Redacted / Mitigation / Ongoing / 18/01/2013 / 1 / 3
10271 / Ensure guidelines and operational policy documents are clear (i.e. not ambiguous) and are easily accessible to providers. / Redacted / Mitigation / Ongoing / 18/01/2013 / 1 / 3
10278 / Contract management is based on a robust framework of risk assessments with a focus on capacity building. / Redacted / Mitigation / Ongoing / 18/01/2013 / 1 / 3
10289 / Effective coordination between National Office, State Office Network and policy areas in the reporting, implementation and management of compliance. / Redacted / Mitigation / Ongoing / 18/01/2013 / 1 / 3
10290 / Contractual requirement for providers to take all reasonable steps to prevent fraud upon the Commonwealth, including the implementation of a fraud control plan. / Redacted / Mitigation / Ongoing / 18/01/2013 / 1 / 3
10322 / Ensure sufficient and appropriate resourcing through:
capability development in staff members;
targeted training and staff development; and
ongoing review of resource allocation to achieve work deliverables. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 3
13997 / Monitoring through site visits, desktop monitoring or other processes the minimum required sample of claims and payments of fees or the use of:
Employment Pathway Fund;
Job Placements and Outcome Fees;
Work Experience; and
Other programs, e.g. NEIS, Connecting People with Jobs. / Redacted / Mitigation / Ongoing / 18/01/2013 / 1 / 3
23358 / Approved Deed management strategy developed, implemented, resourced and monitored/reviewed for its effectiveness in mitigating inconsistent advice. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23359 / Departmental policy, guidelines, advices and training materials are:
Accessible to relevant stakeholders; and
Reviewed and updated regularly. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23360 / Provider contracts and funding management processes clearly articulate obligations. Quality assurance processes include:
advice and clearance through departmental legal areas when required;
regular and random program assurance and contract activities review, compliance assessments, site visits and data; and
appropriate escalation to National Office through established processes e.g. Question Manager and AM Teleconference. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23388 / Contract Management staff apply legislative and contractual requirements and public accountability standards. / Redacted / Mitigation / Ongoing / 18/01/2013 / 1 / 2
23389 / Analysis by Contract Managers against identified reports to assess organisations that meet criteria identified by JSAG. Desktop monitoring and follow up action where appropriate to be documented. / Redacted / Mitigation / Ongoing / 17/01/2013 / 1 / 1
23390 / Data analysis aligns with the priorities in the department’s program assurance strategy. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23391 / Establish data mining/production protocols to ensure consistency across National and State Offices. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23392 / Program monitoring procedures established/enforced to assist in early detection of service delivery anomalies. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23393 / Risk assessment undertaken against possible areas for data interrogation for the identification of non-compliant provider behaviour for the effective rationing of limited resources. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23394 / EPF and Linkages team monitoring of EPF expenditure and identification of anomalies. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23395 / Human intelligence (i.e. tip off line, CSL line) to inform data interrogation for non-compliant provider behaviour / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23396 / Regular review of work priorities and identification of areas of duplication and over staffing. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23405 / Recruit appropriately skilled/experienced staff. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23418 / Implement and manage protocols to reallocate business, in the event provider/s exits the market due to financial stress. / Redacted / Mitigation / Ongoing / 17/01/2013 / 1 / 1
23419 / Systems development tasks to be developed and prioritised, and reviewed (including through Employment Systems Board) in line with DEEWR/provider/other/ stakeholder needs. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23420 / Feedback on systems use and issues by staff and providers is forwarded to ESG. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23421 / IT systems support the reporting and management requirements for each program / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23422 / DEEWR and DHS IT systems support program delivery, as appropriate. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23423 / Develop workarounds and offline contingency plans and procedures ensuring all staff (DEEWR/provider) are aware of these and have appropriate access. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23424 / Regular, scheduled and on demand communications are costed and developed into IT solutions. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23425 / Program areas ensure clear and timely identification of needs to fit in with IT business and funding schedules. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23426 / Strong relationship between program areas and ESG to ensure that policy requirements are reflected in IT system. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23427 / Undertake regular and continual monitoring of service delivery and management by providers, DHS and departmental staff, escalating when necessary. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23428 / Implementation/use of governance arrangements to identify inconsistencies and manage solutions. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23429 / Provide accurate and timely advice to Ministers and Government requests. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23430 / Provide ongoing advice and feedback to Ministers on current and emerging issues, escalating when necessary through appropriate internal governance mechanisms (i.e. Employment Steering Committee). / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23431 / Managing JSA budget processes guided by the requirements of the Financial Management and Accountability Act 1997 (FMA) and Charter of Budget Honesty Act 1998. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
23432 / National Office and State Network identify, initiate and manage strategic partnerships outside the department to:
improve positive messaging about JSA
clearly articulate service expectations to job seekers. / Redacted / Mitigation / Ongoing / 29/03/2013 / 1 / 1
Risk ID: / 5467
Risk Description: / Providers obtain unfair gains through:
claim of payments to which they are not entitled;
manipulation of records in relation to the provider’s performance of the Employment Services Deed; and
unauthorised access to confidential information.
Risk Category: / Fraud
- / Current Risk Rating
Operational / Current Risk Rating
Departmental / Target Risk Rating
Operational / Target Risk Rating
Departmental
Likelihood / Likely / Unlikely / Rare / Rare
Consequence / Moderate / Moderate / Minor / Minor
Risk Rating / High / Medium / Low / Low
Justification for accepting the risk / -
Treatment ID / Treatment Description / Treatment Owner / Treatment Status / Mitigation/Contingency / Next Review Date
10249 / Program level risk assessment are:
maintained; and
reviewed by all relevant parties / Redacted / Ongoing / Mitigation / 18/01/2013
10271 / Ensure guidelines and operational policy documents are clear (i.e. not ambiguous) and are easily accessible to providers. / Redacted / Ongoing / Mitigation / 18/01/2013
10289 / Effective coordination between National Office, State Office Network and policy areas in the reporting, implementation and management of compliance. / Redacted / Ongoing / Mitigation / 18/01/2013
10290 / Contractual requirement for providers to take all reasonable steps to prevent fraud upon the Commonwealth, including the implementation of a fraud control plan. / Redacted / Ongoing / Mitigation / 18/01/2013
13997 / Monitoring through site visits, desktop monitoring or other processes the minimum required sample of claims and payments of fees or the use of:
Employment Pathway Fund;
Job Placements and Outcome Fees;
Work Experience; and
Other programs, e.g. NEIS, Connecting People with Jobs. / Redacted / Ongoing / Mitigation / 18/01/2013
23388 / Contract Management staff apply legislative and contractual requirements and public accountability standards. / Redacted / Ongoing / Mitigation / 18/01/2013
23389 / Analysis by Contract Managers against identified reports to assess organisations that meet criteria identified by JSAG. Desktop monitoring and follow up action where appropriate to be documented. / Redacted / Ongoing / Mitigation / 17/01/2013
Risk ID: / 5468
Risk Description: / The financial stability of JSA providers in times of economic change is jeopardised through:
Poor financial practices or business models;
Lack of internal adaptive change management processes; and
Low caseload flows.
Risk Category: / Strategic
- / Current Risk Rating Operational / Current Risk Rating
Departmental / Target Risk Rating
Operational / Target Risk Rating
Departmental
Likelihood / Unlikely / Unlikely / Rare / Rare
Consequence / Moderate / Moderate / Minor / Minor
Risk Rating / Medium / Medium / Low / Low
Justification for accepting the risk / -
Treatment ID / Treatment Description / Treatment Owner / Treatment Status / Mitigation/Contingency / Next Review Date
10270 / Enforce the Deed requirement that providers submit financial statements to the department for testing financial viability. / Redaction / Ongoing / Mitigation / 18/01/2013
10278 / Contract management is based on a robust framework or risk assessments with a focus on capacity building. / Redaction / Ongoing / Mitigation / 18/01/2013
23418 / Implement and manage protocols to reallocate business, in the event provider/s exits the market due to financial stress. / Redaction / Ongoing / Mitigation / 17/01/2013
Risk ID: / 5471
Risk Description: / The public image of JSA funded programs is adversely affected by:
Ineffective engagement and management of stakeholders by policy and program areas;
Miscommunications to Providers and other stakeholders; and
Lack of shared commitment to a positive image of JSA.
Risk Category: / Stakeholder/Relationship
- / Current Risk Rating Operational / Current Risk Rating
Departmental / Target Risk Rating
Operational / Target Risk Rating
Departmental
Likelihood / Unlikely / Unlikely / Rare / Rare
Consequence / Moderate / Moderate / Minor / Minor
Risk Rating / Medium / Medium / Low / Low
Justification for accepting the risk / -
Treatment ID / Treatment Description / Treatment Owner / Treatment Status / Mitigation/Contingency / Next Review Date
10256 / Effective communication strategies facilitate:
Productive consultation and liaison with key stakeholders and leading industry bodies;
The discussion and management of emerging issues with all stakeholders;
Ongoing dialogue between National Office, State Office and program areas to develop, implement and maintain program assurance and contract management activities;
Reporting the results of assurance activities; and
Promulgating positive outcomes and lessons learned. / Redacted / Ongoing / Mitigation / 29/03/2013
10261 / Identify, initiate and manage strategic partnerships outside the department to improve service delivery and achieve required outcomes. / Redacted / Ongoing / Mitigation / 29/03/2013
Risk ID: / 13594
Risk Description: / Inconsistent management of Deed leads to failure to achieve program objectives.
Risk Category: / Implementation/Service Delivery
- / Current Risk Rating Operational / Current Risk Rating
Departmental / Target Risk Rating
Operational / Target Risk Rating
Departmental
Likelihood / Likely / Likely / Unlikely / Unlikely
Consequence / Minor / Minor / Minor / Minor
Risk Rating / Medium / Medium / Low / Low
Justification for accepting the risk / -
Treatment ID / Treatment Description / Treatment Owner / Treatment Status / Mitigation/Contingency / Next Review Date
23358 / Approved Deed management strategy developed, implemented, resourced and monitored/reviewed for its effectiveness in mitigating inconsistent advice. / Redacted / Ongoing / Mitigation / 29/03/2013
23359 / Departmental policy, guidelines, advices and training materials are:
Accessible to relevant stakeholders; and
Reviewed and updated regularly. / Redacted / Ongoing / Mitigation / 29/03/2013
23360 / Provider contracts and funding management processes clearly articulate obligations. Quality assurance processes include:
Advice and clearance through departmental legal areas when required;
Regular and random program assurance and contract activities review, compliance assessments, site visits and data; and
Appropriate escalation to National Office through established processes e.g. Question Manager and AM Teleconference. / Redacted / Ongoing / Mitigation / 29/03/2013
Risk ID: / 13595
Risk Description: / Data and Intelligence is not used efficiently and effectively to identify non-compliant provider behaviour
Risk Category: / Implementation / Service Delivery
- / Current Risk Rating Operational / Current Risk Rating
Departmental / Target Risk Rating
Operational / Target Risk Rating
Departmental
Likelihood / Likely / Likely / Unlikely / Unlikely
Consequence / Minor / Minor / Minimal / Minimal
Risk Rating / Medium / Medium / Low / Low
Justification for accepting the risk / -
Treatment ID / Treatment Description / Treatment Owner / Treatment Status / Mitigation/Contingency / Next Review Date
23390 / Data analysis aligns with the priorities in the department’s program assurance strategy. / Redacted / Ongoing / Mitigation / 29/03/2013
23391 / Establish data mining/production protocols to ensure consistency across National and State Offices. / Redacted / Ongoing / Mitigation / 29/03/2013
23392 / Program monitoring procedures established/enforced to assist in early detection of service delivery anomalies. / Redacted / Ongoing / Mitigation / 29/03/2013
23393 / Risk assessment undertaken against possible areas for data interrogation for the identification of non-compliant provider behaviour for the effective rationing of limited resources. / Redacted / Ongoing / Mitigation / 29/03/2013