Phone: 908-204-3001; Fax: 908-204-3015; Website:
Resolution #050179
Application for NJ Department of Transportation
2006 Local Bikeway Program
Martinsville Road
(Valley Road to Mountain View Boulevard)
WHEREAS, the Township Committee of the Township of Bernards authorizes submission of project applications for a bikeway on Martinsville Road, Valley Road to Mountain View Boulevard ($533,135), and;
WHEREAS, the grant requests (minimum of $200,000, maximum of $500,000) will come from federal funds; and
NOW THEREFORE BE IT FURTHER RESOLVED, that the Township Committee of the Township of Bernards authorizes the Township Engineer to submit project proposals and project cost estimates for the above bikeway/sidewalk projects.
Agenda and Date Voted:4/12/05
TREASURER’S CERTIFICATIONI, John M Bolcato CPA, Treasurer of the Township of Bernards, hereby certify that adequate funds will be made available for the above referenced purchase in an amount approved by the Township Committee in the 2006 Capital Improvement Fund budget. Monies will be available in the Capital Improvement Fund pending Township Committee approval of the 2006 budget.
Date: 4/5/05 /
John M Bolcato CPA, Treasurer
Explanatory:
The NJDOT is encouraging every municipality to submit project applications for the 2006 Local Bikeway Program with only project proposals and project cost estimates.
Peter A. Messina, P.E., P.P.
Township Engineer/Planner
March 29, 2005
Proposal for Sidewalk/Bikeway on Martinsville Road
(Valley Road to Mountain View Blvd)
Bernards Township is proposing a sidewalk/bikeway as Phase I to interconnect Pleasant Valley Park & Mountain Road Athletic Facility. Phase I is approximately 6,100 linear feet and traverse through a commercial area. The Township anticipates the total cost for Phase I to be $533,135 of which the Township is willing to match up to 10% of the grant. The scope of work includes:
- DEP Permits where required
- Extensive Maintenance & Protection of Traffic
- Excavation & Fill as required
- Retaining Wall to minimize wetlands encroachment
- 4’ wide concrete sidewalk – 6,100 L.F.
- Relocation of guide rails
- Crosswalks and Walk/Don’t Walk signals at existing traffic controls
- Minor landscaping & topsoiling
Project: / Martinsville Road Sidewalk/Bikeway Valley Road to Mountainview Corporate Center
File: / F:/PROGRAMS/EXCEL/ESTIMATE'04/Martinsville Road Sidewalk-Bikeway Valley to Mountainview Corp
Date: / 05-Apr-05
SUMMARY OF COSTS
1.00 / MOBILIZATION / $10,000.00
2.00 / SITE PREPARATION / $25,000.00
3.00 / EARTHWORK / $58,500.00
4.00 / DRAINAGE / $4,940.00 / PROJECT DESCRIPTION: CONSTRUCT NEW 4'
5.00 / SANITARY SEWERS / $0.00 / WIDE CONCRETE SIDEWALK/BIKEWAY FROM
6.00 / PAVEMENT / $88,200.00 / VALLEY ROAD TO MOUNTAINVIEW CORPORATE
7.00 / CURBING / $0.00 / CENTER. DEP PERMITS , A NEW WALK/DON'T
8.00 / TRAFFIC CONTROL / $40,000.00 / WALK SIGNS, RETAINING WALL WILL ALL BE REQUIRED
9.00 / LANDSCAPE / $192,500.00
10.00 / UTILITIES / $0.00
11.00 / UNCLASSIFIED ITEM / $0.00 / PROJECT LENGTH: 6,100'
12.00 / CONTINGENCY / $62,871.00
13.00 / ENGINEERING / $51,122.70
14.00 / BONDING/LEGAL / $0.00
TOTAL= / $533,133.70
AVG. / QUANTITY / TOTAL
ITEM / DESCRIPTION / UNIT / UNIT PRICE / THIS EST. / THIS EST.
1.00 / MOBILIZATION
1.01 / mobilization / L.S. / $10,000.00 / 1.00 / $10,000.00
1.02 / $0.00 / $0.00
1.03 / $0.00 / $0.00
Subtotal= / $10,000.00
2.00 / SITE PREPARATION
2.01 / clear. and grub. / L.S. / $25,000.00 / 1.00 / $25,000.00
2.02 / clear. and grub. / LS. / $0.00 / $0.00
2.03 / demolition / L.S. / $0.00 / $0.00
2.04 / tree removal 6.1"-12"dia. / Each / $300.00 / $0.00
2.05 / tree removal 12.1"-18"dia. / Each / $400.00 / $0.00
2.06 / tree removal 18.1"-24"dia. / Each / $500.00 / $0.00
2.07 / tree removal 24.1"dia.-up / Each / $600.00 / $0.00
2.08 / tree removal various sizes / Each / $300.00 / $0.00
Subtotal= / $25,000.00
3.00 / EARTHWORK
3.01 / unclassified excavation / C.Y. / $15.00 / 1500.00 / $22,500.00
3.02 / rock excavation / C.Y. / $50.00 / $0.00
3.03 / ditch/grass excavation / C.Y. / $0.00 / $0.00
3.04 / embankment excavation / C.Y. / $0.00 / $0.00
3.05 / milling 0-2" thick / S.Y. / $1.75 / $0.00
3.06 / milling 2" thick / S.Y. / $2.25 / $0.00
3.07 / milling 6 1/2" thick / S.Y. / $3.00 / $0.00
3.08 / native fill / C.Y. / $3.00 / $0.00
3.09 / select fill mix I-4 / C.Y. / $12.00 / 3000.00 / $36,000.00
Subtotal= / $58,500.00
4.00 / DRAINAGE
4.01 / RCP 15" CLIII / L.F. / $40.00 / $0.00
4.02 / RCP 15" CLV / L.F. / $33.00 / $0.00
4.03 / RCP 18" CLIII / L.F. / $35.00 / $0.00
4.04 / RCP 18" CLV / L.F. / $36.00 / $0.00
4.05 / RCP 24" CLIII / L.F. / $55.00 / 8.00 / $440.00
4.06 / RCP 24" CLV / L.F. / $40.00 / $0.00
4.07 / RCP 30" CLIII / L.F. / $43.00 / $0.00
4.08 / RCP 30" CLV / L.F. / $46.00 / $0.00
4.09 / RCP 42" CLIII / L.F. / $48.00 / $0.00
4.10 / RCP 42" CLV / L.F. / $50.00 / $0.00
4.11 / RCP 48" CLIII / L.F. / $52.00 / $0.00
4.12 / RCP 48" CLV / L.F. / $56.00 / $0.00
4.13 / 18" F.E.S. / Ea. / $800.00 / $0.00
4.14 / 24" F.E.S. / Ea. / $900.00 / $0.00
4.15 / 30" F.E.S. / Ea. / $1,050.00 / $0.00
4.16 / 36" F.E.S. / Ea. / $1,200.00 / $0.00
4.17 / rip-rap / S.Y. / $20.00 / $0.00
4.18 / Type F Underdrains / L.F. / $20.00 / $0.00
4.19 / 38"x60" HERCP (24' WIDE) / L.F. / $150.00 / $0.00
4.20 / Type "A" Inlet / Ea. / $1,500.00 / $0.00
4.21 / Type "B" Inlet / Ea. / $2,000.00 / $0.00
4.22 / New Headwall / CY / $450.00 / 10.00 / $4,500.00
4.23 / Replace inlet grate / Ea. / $250.00 / $0.00
Subtotal= / $4,940.00
5.00 / SAN SEWERS
5.01 / cut 0-8' 8" / L.F. / $25.00 / $0.00
5.02 / cut >8' 8" / L.F. / $35.00 / $0.00
5.03 / house conn. 4" / L.F. / $15.00 / $0.00
5.04 / tee or wye 8"x4" / Ea. / $250.00 / $0.00
5.05 / manholes / Ea. / $1,250.00 / $0.00
5.06 / replace C.O. caps / Ea. / $50.00 / $0.00
Subtotal= / $0.00
6.00 / PAVEMENT
6.01 / FABC top mix I-5, 1 1/2" Tk / Tons / $35.00 / $0.00
6.02 / Stab. base mix I-2, 4" Tk. / Tons / $35.00 / $0.00
6.03 / D.G.A. 3" thick / Tons / $15.00 / $0.00
6.04 / 2 1/2" Roadstone / Tons / $15.00 / $0.00
6.05 / 3" bit. asphalt sdwlk, 4" dga / SY / $36.00 / $0.00
6.06 / Conc. sidewalks 4in. thick / SY / $36.00 / 2450.00 / $88,200.00
6.07 / Conc. apron 6"TK. / SY / $40.00 / $0.00
6.08 / driveway repair, 2" FABC / SY / $12.00 / $0.00
6.09 / stab. base I-2, repair areas, 5" / SY / $0.00 / $0.00
6.10 / Asphalt Overlay 4' wide 2" thick / SY / $10.00 / $0.00
6.11 / Remove & Replace 4" Conc. / SY / $35.00 / $0.00
6.11 / Remove & Replace 6" Conc. Apron / SY / $40.00 / $0.00
Subtotal= / $88,200.00
7.00 / CURBING
7.01 / conc. curb / L.F. / $15.00 / $0.00
7.02 / gran. block curb / L.F. / $20.00 / $0.00
7.03 / rolled asphalt curb / L.F. / $3.00 / $0.00
7.04 / New Granite Curb / L.F. / $20.00 / $0.00
7.05 / Remove & Replace Conc. Curb / L.F. / $25.00 / $0.00
7.06 / Remove & Replace Granite Curb / L.F. / $25.00 / $0.00
Subtotal= / $0.00
8.00 / TRAFFIC CONTROL
8.01 / street signs / Ea. / $150.00 / $0.00
8.02 / traffic strip. (thermo) / L.F. / $1.50 / $0.00
8.03 / arrow/only / Ea / $150.00 / $0.00
8.04 / maint. and prot. of traffic / L.S. / $25,000.00 / 1.00 / $25,000.00
8.05 / stop bars (thermo) / S.F. / $2.25 / $0.00
8.06 / beam guide rail / L.F. / $22.00 / $0.00
8.07 / brakeway end terminal / Ea. / $875.00 / $0.00
8.08 / Lowering of Junction boxes / Ea. / $2,000.00 / 3.00 / $6,000.00
8.07 / Relocate Guiderail / LF / $7.50 / 1200.00 / $9,000.00
Subtotal= / $40,000.00
9.00 / LANDSCAPE
9.01 / topsoil, seed, mulch / S.Y. / $4.00 / 5000.00 / $20,000.00
9.02 / pines 6' high / Ea. / $200.00 / $0.00
9.03 / norway spruce 6' high / Ea. / $200.00 / $0.00
9.04 / norway spruce 8' high / Ea. / $250.00 / $0.00
9.05 / blue spruce 6' high / Ea. / $200.00 / $0.00
9.06 / relocate trees and shrubs / Ea. / $300.00 / $0.00
9.07 / plant shrubs / Ea. / $50.00 / $0.00
9.08 / Landscaping / LS / $15,000.00 / 1.00 / $15,000.00
9.09 / Keystone Wall / SF / $25.00 / 6300.00 / $157,500.00
Subtotal= / $192,500.00
10.00 / UTILITIES
10.01 / electrical conduit / L.F. / $3.00 / $0.00
10.02 / electric lamps / EA. / $1,000.00 / $0.00
10.03 / panel board / EA. / $2,000.00 / $0.00
10.04 / 2" water line / L.F. / $8.00 / $0.00
10.05 / 2" water line main tap / EA. / $2,000.00 / $0.00
Subtotal= / $0.00
11.00 / UNCLASSIFIED ITEMS
11.01 / erosion control / L.S. / $0.00 / $0.00
11.02 / silt fence / L.F. / $3.00 / $0.00
11.03 / inlet filter / EA. / $30.00 / $0.00
11.04 / DEP Permit / L.S. / $25,000.00 / $0.00
11.05 / Lighting (Walk/Don't Walk) / LS / $10,000.00 / $0.00
Subtotal= / $0.00
12.00 / CONTINGENCY
12.01 / contingency / L.S. / $62,871.00 / 1.00 / $62,871.00
Subtotal= / $62,871.00
13.00 / ENGINEERING
13.01 / design / L.S. / $28,070.00 / 1.00 / $28,070.00
13.02 / inspection / L.S. / $23,052.70 / 1.00 / $23,052.70
13.03 / $0.00 / $0.00
13.04 / $0.00 / $0.00
13.05 / $0.00 / $0.00
Subtotal= / $51,122.70
14.00 / BONDING/LEGAL
14.01 / bonding/legal / L.S. / $20,957.00 / $0.00
14.02 / $0.00 / $0.00
14.03 / $0.00 / $0.00
Subtotal= / $0.00