Natural Gas Transmission

Cogeneration / Power Plant Interconnection

Information Sheet and Service Guide

Completed Gas Transmission Interconnection Applications should be sent to:

Mike O’Brien: 415-973-5652

Fax number: 415-973-6112

Email address:

Or mail to:Or deliver to:

Contract Development SectionContract Development Section

Mail Code B16AMail Code B16A

P.O. Box 7700077 Beale Street

San Francisco, CA 94177San Francisco, CA 94105

Gas System Operations - Transmission System Planning

Cogeneration / Power Plant Interconnection Information Sheet

Application Date: / Natural Gas Service Start Date:
Applicant Name:
Project Name:
Project Location:
(County, City, Street Number - Attach Project Vicinity Map)
A. / Existing host thermal load gas service data:
1. / Customer Name:
2. / Customer Meter Number(s):
3. / Winter Season Load (Nov 1 - Mar 31)
Curtailable / Non-curtailable
Total Peak Demand (Mmbtu/h):
Total Average Demand (MMbtu/h):
Days / Hours of Operation: / /
4. / Summer Season Load (April 1- Oct 31)
Curtailable / Non-curtailable
Total Peak Demand (Mmbtu/h):
Total Average Demand (MMbtu/h):
Days / Hours of Operation: / /
5. / Name plate rating of all existing gas fired equipment:
Device / Function / Rating (MMbtu/h)
6. / What equipment will remain after the cogen plant is operational and how will it be used?
7. / What existing equipment will operate coincident with the cogen plant gas turbine ?
8. / What existing equipment will operate coincident with the cogen plant auxiliary boilers?
B. / Proposed gas service data for cogeneration / power plant:
1. / Service Requirements for all proposed gas fired equipment:
Device / Function / Service Pressure (psig) / Rating (MMbtu/h)
2. / When will the auxiliary boiler(s) and/or duct burner(s) operate and at what load?
3. / Winter Season Load Profile (Nov 1 - Mar 31)
(attach hourly gas load / electric generation profiles) / MMbtu/h / Time (hours)
Total Plant Peak Demand:
Total Plant Off-Peak Demand (MMbtu/h):
Days per week / Hours per day of operation: / /
4. / Summer Season Load Profile (April 1- Oct 31)
(attach hourly gas load / electric generation profiles) / MMbtu/h / Time (hours)
Total Plant Peak Demand:
Total Plant Off-Peak Demand (MMbtu/h):
Days per week / Hours per day of operation: / /
5. / Other service requirements PG&E should be aware of, such as absolute minimum pressure requirements, right-of-way issues, CEC requirements and schedule, project schedule, etc.…
6. / Expected total gas load for first year of gas service (Mmbtu): ______
(Type Name)
(Signature)
(Title) / (Date)