Form 9.1 Installation checklist: Demand/timed dosed pumps and siphons
Client name: Reference #:
Permit(s) #:
Completed by: Time: Date:
System type: ð Pump ð Siphon
1. Control type:
ð Piggyback ð Control panel ð Siphon counter
a. Panel ð NA ð Yes ð No
Manufacturer:
Model:
ð NEMA 4X Panel rating
Elapsed time meter ð NA ð Yes ð No
Cycle counter ð NA ð Yes ð No
b. Timer
Manufacturer:
Model:
c. Telemetry ð NA ð Yes ð No
Manufacturer:
Model:
2. Pump ð NA ð Yes ð No
a. Pump manufacturer:
Model:
b. Type of pump: ð Multi-stage ð Single-stage
ð Sewage ð Effluent ð Grinder
c. Pump specifications:
i. Design flow rate: gpm
ii. Design pressure (TDH): ft
iii. Horsepower: hp
d. Pump installed under access ð Yes ð No
e. Pump intake elevated: Height inches ð Yes ð No
f. Pump removal
ð Pull chain or rope installed ð Pump rails installed
ð Other:
g. Pump vault flow rating: gpm
3. Siphon ð NA ð Yes ð No
a. Siphon manufacturer:
Model:
b. Siphon capacity: gpm
c. Siphon installed under access ð Yes ð No
d. Siphon removable ð Yes ð No
e. Siphon cycle counter installed ð NA ð Yes ð No
4. Pump discharge assembly
a. Quick disconnect ð Installed
Type of disconnect:
Accessible from surface
b. Isolation valve ð Installed ð NA
Type of valve:
c. Anti-siphon/air release device ð Installed ð NA
ð Air release hole between check valve and pump discharge
ð Reversed check valve at high point in assembly
ð Spit tube
d. Drainback allowed ð Yes ð No
e. Inline filter ð Installed ð NA
Manufacturer:
Model:
f. Pressure gauge / port ð Installed ð NA
g. Sampling port ð Installed ð NA
5. Supply lines and discharge pipes
a. Air/vacuum release ð Installed ð NA
b. Thrust blocks ð Installed ð NA
c. Siphon discharge diameter greater than ð Yes ð No
or equal to trap diameter
Grade on siphon discharge pipe ð Level ð Sloping
6. Water level sensors ð NA
a. Type of water level sensor: ð Floats ð Pressure transducer
ð Ohm probe ð Other:
b. Sensor attachment
ð Tethered to float tree
ð Tethered to bracket on riser ð Other:
c. Sensor settings:
Sensor number* / Function / Set at** / SecuredInches / Datum
1 / ð Yes ð No
2 / ð Yes ð No
3 / ð Yes ð No
4 / ð Yes ð No
5 / ð Yes ð No
*Designate starting from bottom of tank.
**Measurements are taken from a fixed point (Datum) near the surface or bottom of float tree.
d. ð Pump will be submerged at OFF elevation
7. Wiring ð NA
a. Electrical service
ð Single-phase 120V ð Single-phase 240V ð 3-phase 240/120V
ð 3-phase 208/120V
b. Wire gauge: ð Adequate for distance
c. ð Wire contained within conduit and junction boxes
Conduit sealed ð Within panel ð Within dosing tank riser
Sealant used:
d. ð Float wires color-coded:
Sensor number* / Function / Color1
2
3
4
5
e. Connections completed by
ð Electrician ð Installer
ð Homeowner ð Other: