Second Wind Generation Workshop
August 22, 2008 (9:00 am to 4:00 pm)
ERCOT Met Center, 7620 Metro Center Drive
Austin, Texas 78744
Preliminary agenda
- Overview of wind generation technologies (45 minutes) : Rob Sims
- Physical design / capability of 3 specific wind generators representing a range of technologies:
· Rob Sims – AES
· John Franklin – EON
· Mike Barrios -- FPL
(20 minutes per presentation)
- Describe the turbine
- Physical characteristics
- Rating
- Method of starting
- Method of controlling power output
- Method of stopping
- Reactive devices as part of the turbine
- Physical description
- How used operationally
- Describe the wind ranch
- Site selection criteria
- Cabling connecting to collector substation
- Electrical characteristics
- Operational issues
- Substation
- Substation / switching diagram
- Step up transformer(s)
- Reactive devices
- Control system
- Location of control rooms / facilities
- SCADA
- Turbine power control
- Reactive control
- Switch / breaker control
- Transmission interconnection issues
- Special Protection Schemes (SPSs)
- Remedial Action Plans (RAPs)
- Describe current Voltage Ride Through capability
- What are current low voltage relay settings
- What design changes would be required and what would it cost to comply with FERC 661A nine cycle zero volt standard
- Typical operating day – interaction with QSE / ERCOT (20 minutes per presentation) : same 3 wind presenters
- Describe - data / communication flow / physical activities for (including discussion of current capability to meet applicable draft response time requirements and cost or time to comply):
- submitting COP / resource plan
- responding to curtailment order
- release from curtailment order
- voltage control
- deploying reactive assets
- changing control settings for reactive
- switch / breaker operation
- Identify operating problems or issues
- Operation of SPSs or RAPs
- Communications
- Response to frequency changes
- Transient response characteristics
- lunch
- ERCOT voltage control requirements (15 minutes) : ERCOT
- Transmission Owner voltage management practices (25 minutes) : Oncor
- ERCOT Operational Proposals (40 minutes) – ERCOT
- Utilizing High Frequency Relaying to protect against sudden increases in wind output
- Special Protection System (SPS) Operation
- Weather data input requirements for the wind forecast
- Ramp Rate discussion
- Explore the possibility of wind generation providing governor-like response
- Explore the possibility of a ramp rate instruction
- Next steps (60 minutes)
- Identify training needs
- For wind generators and QSEs
- For ERCOT staff
- Identify procedural changes to be made
- Data collection
- Operating procedures
- Equipment design
· $free
· See http://www.ercot.com/calendar/2008/08/20080822-WIND for more info, or contact Walter Reid, John Dumas, or Mark Garrett.
· Presentations will be posted to the calendar page prior to the meeting.
· Conference call lines (40) will be available.
· Rev 8/13. Topics subject to slight change.