FHWA – Indiana PSE Checklist
ContractNo.: / DESNo.:Route: / County:
INDOTDistrict: / Construction Cost at Stage 3:
LettingDate: / CompletionDate:
StateAdministered FHWAOversight
Location:location as shown in SPMS
Description:work type as shown in SPMS
Notes:
See PSE Checklist Narrative for instructions oncompletingform.
Items in bold text beloware critical. Only Yes orNA answerscanbe given in order to for PSE to be approved.
Item / Yes / No / NASection 1: DESIGN QUALITY, Plans Reviewer S3 Review
- Is Title Information accurate and complete?
- Is the designspeed greater than or equal to the posted speed?
- Is the designspeed appropriate for the facility?
- Are typical sections included?
- Has the pavement designbeen approved and does it match the typical
- If there are 3 lanessloped insame direction, does the outsidelane
- Is drainage addressed andappear to drain away from the road?
- If required, is the medianwidth adequate? If no, has a design exception
- Do the foreslopes and backslopes meetstandards?
- Do the vertical and horizontal alignments complement each other?
- Are all obstructions outsideof the horizontal sight distance impact area?
- Are right of way limits defined?
- Is the proposed workwithin the ROW?
- Is the Level 1checklist submittedalongwith design exception approval if applicable?
- Is safety hardware used appropriately? (guardrail?)
- Is lane alignment thru intersection appropriate?
- Is accesscontrol appropriate within the vicinity of interchanges and
If not,has documentation been approved by FHWA?
- Do signs andplacement comply with the IMUTCD?
- Do signs convey the intended message? Are they placed in accordance
- Are appropriate pavement markings called for?
- Has the workzone traffic controlplan ortransportationmanagementplan,
- Are lanewidths appropriate for MOT phases? If not, has a designexception
- Does the MOT account for drainage?
Item / Yes / No / NA
- Is the posted speed duringconstruction less than or equal to the
- Does the MOT address bike and pedestrian traffic if applicable?
- Will emergency response teams be able to get through the construction
- Based on theMOT, is the project constructible?
- Are there provisions to maintain access to businessesand residences
- Are provisions made for protecting motorists from drop-offs?
- Do sidewalks and trailscomply with the ADA?
- Is the final design estimatecomplete and reasonable?
- If non-participating items are included inthe project, are they listedseparately with an asterisk inthe estimate?
- Are proprietary items included in the contract documents?
Reviewed By(full name):
Date (mo.day.yr):
Phone /Email:
INDOT Comments for Section 1:
Section 2: Project Manager Review
- Is the construction phase in the TIP/STIP?
If Yes, list TIP/STIP reference and Date:
- Is the projectrequired to be on Federal-aid system? If Yes, is it on the
- Has right ofwaybeen certified? If Yes, list type and date of Right-of-way certificate:
- If right of way certificate isalevel 2 or 3 exception, has FHWA
- If ROW is notclear prior to letting, are appropriate restrictions included in
- Has the utility certificate orwaiver beencompleted? If Yes, list type and date of certificate:
- If utility relocations are required and not completed prior to construction
- Has aNEPAdocument been completed? If Yes, list type and date of initial and subsequentNEPA approval.
Has the Environmental Consultation Form been approved?
- Have all waterway permitsbeenreceived? If Yes, list required permits:
- Is the projectcommitments database current andcommitments incorporated in the final design?
- (a) Has the railroad coordination certification been completed?
Item / Yes / No / NA
43. (b) If the project requires use oforadjustment to railroad facilities,has a railroad agreement been signed? List date of agreement:
(c) Does the proposal includeliability insurance requirements?
- Has coordination with FAA been completed for project located within 2 miles of an airport?
- For an Interstate interchange, is an IJ required? If so, was final approval
- If the project is:
•a bridge and the total cost exceeds $40 M
has a valueengineeringstudybeen completed?
- If the total project cost is between $100 M and $500 M, has an Initial
- If the total Project cost is $500 M or more:
Was aCost EstimateReviewcompleted? List date of review:
- If applicable, has an FHWA approval letter been included for use of experimentalfeatures?
- If there are guarantees orwarranties and the project is on the NHS,has
- If there are any incentive / disincentive clauses, havethey been reviewed
- If State furnished material (other thansignal controllers), borrow or disposal
- If non-participating items were added after S3 review, are they listed separately with an asterisk inthe estimate?
- Are proprietary items included in the contract documents?
- Has a realistic construction completiondate been set? Contract Completion Date:
- Are previous review comments incorporated into the Final Tracings plans?
Reviewed By (full name):
Date (mo.day.yr):
Phone / Email:
INDOT Comments for Section 2:
Item / Yes / No / NA
Section 3: Contracts Administration Review
- If procurement is byother than competitive bidding, has a cost
- Doesthe proposal contain:
•US Department of LaborWage RateGeneral Decision Number
•Title VI Assurances
- Was aDBEgoal established for the contract?
- If less than a3 week advertisement period is requested, is the request
- Have priorcomments, including phase I PSE been addressed?
- Final construction cost estimate submitted?
Reviewed By (full name):
SubmittalDate (mo.day.yr):
Phone / Email:
INDOT Comments for Section 3:
INDOT Review & Approval:
Name:Date:
Phone/Email:
INDOT hereby submits Phase 1 PS&E to FHWA for review and comments.
INDOT hereby submits Phase 2 PS&E to FHWA, requesting approval.
FHWA ReviewComments (if Full Oversight):
Comments included on attached comment sheet
No comments
FHWA Signature (required for Full-Oversight Project):
Reviewed and approved By:______Date: ______
PSE has been approved and is readyfor advertisement with the following conditions:
No conditions