The AmeriCorps Retention Project Calendar 2012-2013
Due Date or Activity Date / Report/Activity / Period Covered (if applicable)August 1, 2012 OR
August 31, 2012 / Member Start Date / Member participates in site-specific orientation
September 2012 / ORCC Program Orientation / Required for all ORCC AmeriCorps Members
September 30, 2012 / Member Development Plan due to ORCC / Members and supervisors will work together to outline a professional development plan for the service year
October 2012 / AmeriCorps Launch Event Portland State University / Participate in skill-building workshops. Take an oath of service
October 2012 / Make a Difference Day of Service / Mandatory Member participation in local service project. Report of service activities due to ORCC
October 30, 2012 / Winter Service Plan form due to ORCC / Members and supervisors will work together to outline a plan for holiday leave time
December 2012 / In-Service Training / Members come together for continuing training
January 14, 2013 / Mid-Term Member Performance Evaluation / Site supervisor and Member complete, review together, and send to ORCC
January 21, 2013 / Martin Luther King Jr. Day of Service / Mandatory Member participation in local service project. Report of service activities due to ORCC
February 2013 / Mid-Year Progress Report Due / Site supervisor and Member complete, review together, and send to ORCC
Spring 2013 / Site Visits / ORCC will conduct site visit with host sites
April 24-26, 2013 / Continuums of Service Conference / Host sites are encouraged to submit proposals to disseminate project information at the conference
June 17, 2013 / End of Term Member Performance Evaluation / Site supervisor and Member complete, review together, and send to ORCC
June 2013 / In-Service Training / Members come together for Life After AmeriCorps and continuing training
June 2013 / Graduation
Location/exact dates TBD / Required for all AmeriCorps Members
June 2013 / Final (Cumulative) Progress Report Due / Site supervisor and Member complete, review together, and send to ORCC
Timeline TBA / Assessments (Mentee Participant Survey, Mentor Civic Engagement Survey, Retention Project Coordinator Civic Engagement Survey) / Required for all host sites
June 30/July 31, 2013 / Last Day of Service
Activities in bold are required