Form I.2: The structure and contents of the project's environmental protection plan, not subject to the provisions in Appendix 5.1 of Circular No. 27/2015 / TT-BTNMT dated 29/05/ 2015 of the Minister of Natural Resources and Environment:

SOCIALIST REPUBLIC OF VIETNAM

Independence - Freedom - Happiness

------

…………..(Location and date) ......

To: The Management Board of Industrial Parks of Hung Yen province.

The environmental protection plan for registration with the following contents:

I. General information

1.1. Name of project, establishment (referred to as project): ...

1.2. Name of Project Owner: ...

1.3. Address: ...

1.4. Legal representative: ...

1.5. Means of communication with the project owner: (telephone number, fax, E-mail ...).

II. Basic information on production and business activities

2.1. Location of the project implementation: ......

......

......

2.3. Type of production, business, service; product and quantity:

......

......

2.4. Area of production, business, service establishment (m2): ......

......

2.5. Demand for raw materials and materials used in production process: ......

......

......

......

2.6. Fuel used in production process (oil, coal, firewood, gas, electricity ...)

......

......

......

III. Environmental protection plan during construction phase

Impact Factor / Status / Mitigation Measures / Status
Yes / No / Yes / No
Exhaust emissions from means of transport, construction machines / Usetested construction equipment, machines
Use less polluting fuel
Regular maintenance of equipment and facilities
Other measures:
Dust / Isolate, spray water to reduce dust
Other measures:
Daily-life waste / Collect, self-treat before discharged into the environment (indicating the source of wastewater receipt)
Collect, rent functional units to handle
Pour directly into the drainage system
Other measures:
Construction waste / Collect, self-treat before discharging into the environment (indicating the source of wastewater receipt)
Pour directly into the drainage system
Other measures:
Building solid waste / Collect for recycling or reuse
Dispose of waste at designated local sites (specify the location)
Rent functional units to handle
Other measures:
Domestic solid waste / Dispose of waste at designated local sites (specify the location)
Rent functional units to handle
Other measures:
Hazardous waste / Rent functional units to handle
Other measures:
Noise / Periodic maintenance of equipment
Arrange appropriate construction time
Other measures
Vibration / Periodic maintenance of equipment
Arrange appropriate construction time
Other measures
Run-off rain water / Having water drainage systems, pits for collecting and filtering rainwater before being released into the environment.
Other measures

IV. Environmental protection plan in the operation phase

Impact Factor / Status / Mitigation Measures / Status
Yes / No / Yes / No
Dust and exhaust emissions / Install dust and exhaust emissionstreatment systems with chimney
Install ventilation fan with air filter at the end of the pipe
Other measures
Domestic wastewater / Collection and reuse
Preliminary treatment by septic tank before discharged into the common drainage system
Other measures
Production wastewater / Collect and reuse
Waste water is treated locally and discharged into the concentrated wastewater treatment system
Wastewater treatment meets regulatory standards and releasedinto the environment (indicating the source of receipt and standards attained after treatment).
Other measures
Waste water from the cooling system / Collect and reuse
Heat - relieve and discharge into the environment
Other measures
Solid waste / Collect for recycling or reuse
Self-handle
Rent functional units to handle
Other measures
Hazardous waste / Rent functional units to handle
Other measures
Smell / Install ventilation fan
Other measures
Noise / Periodic maintenance of equipment
Install soundproof to reduce noise
Other measures
Heat surplus / Install ventilation fan
Other measures
Run-off rain water / Having water drainage systems, pits for collecting and filtering rainwater before being released into the environment.
Other measures

V. Commitment

5.1. We / I pledge to strictly comply with the environmental protection regulations of the Law on Environmental Protection in 2014, comply with regulations, standards and technical regulations on environment and take full responsibility if occurring violation of regulations on environmental protection.

5.2. We pledge to implement the above mentioned environmental protection plans.

5.3. We / I ensure the integrity of the information and contentsprovided in this environmental protection plan.

PROJECTOWNER

(Signature, full name, title, seal (if any))

Requirements: Environmental protection plan is signed by the project owner at the bottom of each page