P Eng Suraj Singh April 11, 2006 Page 1 of
Civil Engineering
Buildings Practice
Construction Method Statements
General Activities
P Eng Suraj Singh
Contents index
For navigation please click these pasted hyperlinks
Construction Method Statements for various activities within civil engineering for plants worksSite Preparation & Earth Work / PROTECTIONOF EXISTING SERVICES / RE-ROUTING OF 33KV CABLES
Concrete PipeCulverts
CONCRETING TO WALLS OF
CENTRAL CONTROL BUILDING / LABORATORY / CONCRETE PIPE CULVERTS / CULVERTCROSSINGS TO AVENUE E AND MAIN HIGHWAY.
PLACING CONCRETE ON SERVICE
WATER TANK 58-TK-205 FOUNDATIONS / CONCRETE REPAIR
Top / CONSTRUCTION OF PIPE RACK BASES
EXCAVATION IN Operating Authority CONTROLLED AREAS / CONSTRUCTION OF MAIN SUBSTATION / REMOVAL OF HAZARDOUS MATERIALS
CONSTRUCTION OF FLOOR SLAB
CENTRAL CONTROL BUILDING / MORTAR FOR BLOCKWORK / CONTROL OF CAMP SEWAGE SYSTEM
STRUCTURAL STEEL-PIPERACKS / COMPRESSORS’ STRUCTURES
RCC COLUMN PLATE INSERTS / EXCAVATION FOR
132KV CABLE INTERCONNECTION
ROAD CROSSING FOR 132 KV ROUTE / NIGHT SHIFT WORKING - EARTHWORKS / GROUTING TO PIPE RACK FOUNDATION BASES
CEMENTITIOUS GROUTING TO FOUNDATION BASES / ETYLENE COMPRESSOR
MASSIVE FOUNDATION (CONCRETE POUR / PROPANE COMPRESSOR
MASSIVE FOUNDATION (CONCRETE POUR)
PROPANE COMPRESSOR
MASSIVE FOUNDATION (CONCRETE POUR) / PROPANE COMPRESSOR
MASSIVE FOUNDATION (CONCRETE POUR / PROPANE COMPRESSOR
MASSIVE FOUNDATION (CONCRETE POUR
PROPANE COMPRESSOR
MASSIVE FOUNDATION (CONCRETE POUR / SEAWATER BASIN
(WATER TIGHTNESS BS 8007 : 1987) / SEAWATER BASIN
(WATER TIGHTNESS BS 8007 : 1987 )
SEAWATER BASIN
(WATER TIGHTNESS BS 8007 : 1987 ) / ADMINISTRATION BUILDING
STAIR LANDINGEXTENSION AT GRID 4 J / ADMINISTRATION BUILDING
STAIR LANDING EXTENSION AT GRID 4 J
ADMINISTRATION BUILDING
STAIR LANDING EXTENSION AT GRID 4 J / FENCING
Top
/ ADMINISTRATION BUILDINGCERAPlant Operating Authority TILES FLOORING SYSTEM
ADMINISTRATION BUILDING
CERAPlant Operating Authority TILES FLOORING SYSTEM / ADMINISTRATION BUILDING
PLASTERING AND RENDERING / ADMINISTRATION BUILDING
ROOFING SYSTEM
ROOFING SYSTEM / BUILDINGS
ROOFING SYSTEM / CRACKED GAS COMPRESSOR TABLE TOP CONCRETE POUR
WATER TIGHTNESS TESTS FOR THE COLLECTION SUMPS ACCORDING TO BS 8007 : 1987 SECTION 9 / WATER TIGHTNESS TESTS FOR THE COLLECTION SUMPS ACCORDING TO BS 8007 : 1987 SECTION 9 / ADMINISTRATION BUILDING
MARBLE FLOORING
ETHYLENE GAS COMPRESSOR
TABLE TOP POUR
/PROPANE GAS COMPRESSOR
TABLE TOP POUR
/ EXPANSION JOINTS IN DITCHESEXPANSION JOINTS IN DITCHES
Top
/ CONCRETE COATINGUSING MASTER SEAL 550 / DEWATERING FOR THE 84” GRE PAIR LINE PARALLEL TO
CORNICHE ROAD EAST WEST
CERAPlant Operating Authority WALL TILES FIXING / BEDDING AND GRAVEL FILLING BENEATH 60 “ DIA PIPE COOLING WATER PIPE / EXTERNAL CONCRETE PROTECTION ADMINISTRATION BUILDING
ABOVE GROUND CONCRETE PROTECTION
USING MASTERSEAL 300 H / ABOVE GROUND CONCRETE PROTECTION
USING MASTERSEAL 300 H / HAND EXCAVATION TO INSTALL
TELEPHONE DUCTS BETWEEN BOX NO.20 TO TELECOM CENTRE
BACKFILLING OF THE WEST SIDE OF THE QUENCH TOWER FOUNDATION – (RIB) / EXCAVATION -
COOLING WATER OUTFALL CHAMBER / DRILLING OF HOLES ON
PIPE RACK & STRUCTURES ON SITE
SITE OFFICE ESTABLISHMENT / Welding of Earthing Lugs on
East West Piperack (SR0099A &B) / FILLING AROUND ALL THE PIPES WITHIN THE Plant AREA
PRECASTING MAN HOLES
CATCH BASIN AND
VALVE CHAMBERS / TERMINATIONDETAIL TO PROTECTIVE MEMBRANE AROUND RCC COLUMNS SUPPORTING THE STRUCTURAL STEEL
COLUMNS FOR PIPE RACKS
CASE (1) WITH ALUMINIUM BEAD
CASE (2) WITH REBATE
CASE (3) GRAVEL FILL
CASE (4) PAVING / TERMINATION DETAIL TO PROTECTIVE MEMBRANE AROUND RCC COLUMNS SUPPORTING THE STRUCTURAL STEEL
COLUMNS FOR PIPE RACKS
CASE (1) WITH ALUMINIUM BEAD
CASE (2) WITH REBATE
CASE (3) GRAVEL FILL
CASE (4) PAVING
Top
/ ROAD CROSSING FOR LAYING 2 PIPES 1 FOR 20” RAW ETHANE & 1 FOR 6” PROPANEFIRST STREET Operating Authority ENTRY / ROAD CROSSING FOR LAYING 2 PIPES1 FOR 20” RAW ETHANE1 FOR 6” PROPANEFIRST STREET Operating Authority ENTRYDIRECTIONAL BORINGFOR LAYING SLEEVES FOR2 PIPES1 # 20” RAW ETHANE1 # 6” PROPANEOperating Authority Plant REFINERY ENTRY / 2 #s ROAD CROSSINGSFOR LAYING1 FOR 14” DESALINATED WATER1 FOR 8”POTABLE WATER1 FOR 20” RAW ETHANE
1 FOR 8” NATURAL GAS
1 FOR 6” PROPANE
AVENUE ‘C’AT FIRE STATION / 2 #s ROAD CROSSINGSFOR LAYING1 FOR 14” DESALINATED WATER1 FOR 8”POTABLE WATER1 FOR 20” RAW ETHANE
1 FOR 8” NATURAL GAS
1 FOR 6” PROPANE
AVENUE ‘C’AT FIRE STATION
ADMINISTRATION BUILDING
GRC
PANEL FIXING / PAINTING ADMINISTRATION BUILDING / PAINTING ADMINISTRATION BUILDING
Top
ROAD CROSSING FOR LAYING 2 PIPES1 FOR 20” RAW ETHANE1 FOR 6”PROPANEAVENUE ‘C’ / EARTHWORKS SURVEY SYSTEM / ROAD CROSSING FOR LAYING84”G R E PAIR SEAWATERCOOLING LINESATAVENUE ‘D’ / CORNICHEJUNCTIONROAD CROSSING FOR LAYING84”G R E PAIR SEAWATERCOOLING LINESATAVENUE ‘D’ / CORNICHEJUNCTION / TENNIS COURTS SURFACING
Top
/ PRECASTING LIGHTING POLES FOUNDATIONSLIGHTING POLES FOUNDATIONS / SEA WATER SURGE BASIN
CONCRETE PROTECTION
MASTER SEAL 550 / CONCRETE COATING OF STRUCTURES USING MASTERSEAL 550
ABOVE GROUND CONCRETE PROTECTION
SEAWATER SURGE BASIN / SEA WATER SURGE BASIN JOINT SEAL / PAINTING
SUB STATIONS
PAINTING
SUB STATIONS / ELECTRICAL & INSTRUMENTATION TRENCHES / ELECTRICAL & INSTRUMENTATION TRENCHES
PULL PITS
ROAD CROSSING TO MAKE GOODWEARING COURSE OVER COMPLETED
1# FOR 14” DESALINATED WATER1# FOR 8”POTABLE WATERAVENUE ‘C’ / PULL PITS
ROAD CROSSING TO MAKE GOODWEARING COURSE OVER COMPLETED
132 KV ELECTRIC CABLEAVENUE ‘C’ / PULL PITS
ROAD CROSSINGTO MAKE GOOD (temporarily)WEARING COURSE OVER COMPLETED
132 KV ELECTRIC CABLEAVENUE ‘C’
DRINKING WATER CONNECTION
Top
/ PROTECTION TO TRANSFORMER FOUNDATION SIDES IN SUB STATIONSWITH ALUMINIUM BEAD TERMINATION FOR BELOW GROUND AND MASTERSEAL 300H FOR ABOVE GROUND IN GRAVEL FILL AREA / TIMBER DOORS FIXING
ADMINISTRATION BUILDING
GROUTING TO STEEL TANKS BEARINGS ON RING BEAMS / GROUTING TO STEEL TANKS BEARINGS ON RING BEAMS / EXCAVATION FOR CCB UNDERGROUND WATER TANK
EXCAVATION FOR CCB UNDERGROUND WATER TANK / SOAKAWAY CHAMBERS / EPOXY FLOORING
BUILDINGS
EPOXY FLOORING
BUILDINGS / EPOXY FLOORING
BUILDINGS / VINYL WALL COVERING
BUILDINGS
DRY WALL LININGS
BUILDINGS / RUBBER FLOORING
(BUILDINGS) / RUBBER FLOORING
(BUILDINGS)
RUBBER FLOORING
(BUILDINGS) / RUBBER FLOORING
(BUILDINGS) / RUBBER FLOORING
(BUILDINGS)
SUSPENDED CEILINGS
ALL BUILDINGS / PIT 21 WATER CONNECTION
Top
/ CEMENT BASED NON SHRINK GROUTING TO FOUNDATION BASESUSING MASTERFLOW 928 T
REPAIR OF CONCRETE FLOOR SCREEDS
Top
/ REPAIR OF CONCRETE FLOOR SCREEDS / EPOXY GROUTING TOVIBRATING INSTALLATION BASES
USING MASTERFLOW 648 CP
GENERAL FOUNDATIONS
KERBS & INTERLOCKING BLOCKS PAVING AROUND BUILDINGS / ERECTION OF STEEL STRUCTURES (FOR HIGHER LEVELS) / VINYL FLOORING
BUILDINGS
CONCRETE PAVING / CENTRAL CONTROL BUILDING
CERAPlant Operating Authority TILES FLOORING SYSTEM / CONCRETE PLACEMENT
PRECAST RCC COVERS
CABLE & INSTRUMENTATION TRENCHES / BLACK TOP REPAIR
IST STREET BETWEEN
AVENUE C & B / REPAIR OF
SINGLE LEAF SWING GATES
REPAIR TO
FLOOR SCREED LEVELS / RESIN INJECTION TO LEAKING JOINT
SEA WATER SURGE BASIN / RESIN INJECTION TO LEAKING JOINT
SEA WATER SURGE BASIN
RESIN INJECTION TO LEAKING JOINT
SEA WATER SURGE BASIN / FIRE WATER LINE EXCAVATION AROUND CONSUMER RECEIPT STATION / ROAD CROSSINGFOR LAYING1 FOR 20” RAW ETHANE
1 FOR 6” PROPANE
FIRST STREET
ROAD CROSSINGFOR LAYING1 FOR 20” RAW ETHANE
1 FOR 6” PROPANE
FIRST STREET / 2 #s ROAD CROSSINGSFOR LAYING1 FOR 20” RAW ETHANE
1 FOR 8” NATURAL GAS
1 FOR 6” PROPANE
1 FOR 14”DESALINATED WATER
1FOR 8” POTABLE WATER
AVENUE -D / TREATMENT TO MOVED EXPANSION JOINTS
SEA WATER SURGE BASIN
Top
TESTING OF FRESH CONCRETE ON SITETop
/ ROAD CROSSINGTO INSTALL CULVERT FOR1# 14” DESALINATED WATERCORNICHE ROAD / ROAD CAT GUP GATE NOTH / ROAD CROSSINGTO INSTALL CULVERTFOR1 # 14” DESALINATED WATER
AVENUE ‘C’ ROAD GUP GATE EASTMAIN ENTRANCE
ROAD CROSSINGTO INSTALL CULVERTFOR1 # 14” DESALINATED WATER
AVENUE ‘C’ ROAD GUP GATE EASTMAIN ENTRANCE / ROAD CROSSINGTO INSTALL CULVERTFOR1 # 14” DESALINATED WATER
AVENUE ‘C’ ROAD GUP GATE EASTMAIN ENTRANCE / REPLACEMENT OF MISALIGNED ANCHOR BOLTS
IN
FOUNDATION 55-VV-906
USING RENDEROC LAX TRA
REPLACEMENT OF MISALIGNED ANCHOR BOLTS
IN
FOUNDATION 55-VV-906
USING RENDEROC LAX TRA / BUILDINGS
SCREEDS FOR VINYL AND EPOXY
FLOOR FINISHES / BUILDINGS
SCREEDS FORVINYL AND EPOXY
FLOOR FINISHES
BUILDINGS
SCREEDS FOR VINYL AND EPOXY
FLOOR FINISHES / DIRECTIONAL BORING AT 3# LOCATIONS FOR 14”DESALINATED WATER PIPE CORNICHE ROAD
NORTH OF Operating Authority / DIRECTIONAL BORING AT 3# LOCATIONS FOR 14”DESALINATED WATER PIPE CORNICHE ROAD
NORTH OF Operating Authority
DIRECTIONAL BORING AT 3# LOCATIONS FOR 14”DESALINATED WATER PIPE CORNICHE ROAD
NORTH OF GUP / DIRECTIONAL BORING AT 3# LOCATIONS FOR 14”DESALINATED WATER PIPE CORNICHE ROAD
NORTH OF GUP / EPOXY SKIRTING IN
CENTRAL CONTROL BUILDING
& SUB STATIONS ON DRY LINING
EPOXY SKIRTING
ON DRY LINING / EPOXY SKIRTING
ON DRY LINING / ROAD SURFACE
REINSTATEMENT
OVER BOX CULVERT CROSSINGS
Top
/ REPAIR TO LIFTCLADDING PANEL
ADMINISTRATION BUILDING / FIXING SHEETING PANELS
WALL & ROOF CLADDING
FIXING SHEETING PANELS
WALL & ROOF CLADDING / ROAD CROSSINGAT FIRE STATION- FIRST STREETFOR LAYING2 # 100 mm SLEEVES
FOR TELEPHONE CABLES / SEA WATER SURGE BASINCLOSING THE STRUCTURAL GAPON THE ROOF, WALL & BASE SLAB
HDPE PIPESBUTT FUSION / ROAD CROSSINGSTO CONSTRUCT BOX CULVERTS OFH 2 & 3CORNICHE ROADETHYLENE EXPORT / ROAD CROSSINGSTO INSTALL CULVERTS OFH 4 & 5CORNICHE ROAD ETHYLENE EXPORT
MDPE DRINKING WATER LINE – NY LINES / ROOF & SIDE CLADDING –Plant AREA / FOUNDATIONS ALONG FENCE BELOW
‘FERTIL OVER HEAD CONVEYOR’
FOR PIPE RACK LEADING TO SEA
REINSTATEMENT TO
‘DAMAGE CAUSED
FLARE PIPE RACK
COLUMN MEMBER 01537’
AT GRID 19A / REINSTATEMENT TO
‘DAMAGE CAUSED
FLARE PIPE RACK
COLUMN MEMBER 01537’
AT GRID 19A / Maintenance Warehouse
Overcoating
To Epoxy Painted Surface
With
Mastertop Top Coat 44P
Access to Corridors & Walkway
Roads
Bituminous Concrete Surfacing / Roads
Bituminous Concrete Surfacing / Excavation for 200 pair Telecom Route
(Direct Buried)
parallel to Avenue D & 3rd street
Hand Excavation for 200 pair Telecom Route
(Direct Buried)
parallel to Avenue C / 200 pair Telecom Road Crossing
at Avenue D / 3rd Street Intersectionalong E 676976 / Manual Excavation
200 pair Telecom Road Crossing
@ Access road to GASCO camp
@ C / L, co-ordinate N 2666305 / avenue C
Manual Excavation
200 pair Telecom Road Crossing
@ Access road to Operating Authority camp
@ C / L, co-ordinate N 2666940 / avenue C / REMOVAL OF CONTAMINATED SOIL / BLINDING CONCRETE
REINFORCEMENT RECEIVAL & FABRICATION / REINFORCEMENT PLACEMENT / FORMWORK ERECTION
CONCRETE TO PAVED AREAS / EXCAVATION & BACKFILL TO STRUCTURES / TELEPHONE CABLE TO SITE OFFICE
ELECTRIC CABLE FROM RLIP SUBSTATION TO Civil Contractor CAMP / WATER SUPPLY TO Civil Contractor CAMP / ADMINISTRATION BUILDING SUBSTRUCTURE
WASTE MANAGEMENT / SEA WATER BASIN / EXCAVATION FOR
ETHANE & PROPANE
GAS PIPELINE INTERCONNECTION
GENERAL
/Top
#1
Site Preparation & Earth Work
Top
Index
Scope - Reference documents – Definitions – Responsibilities – Safety – Method – Equipment - Attachment
Scope
The purpose of this method statement is to define the sequence of activities for the site preparation works related to the Company Petrochemical project. The extent of these activities are defined upon the attached site plan (Not included with this statement). Refer to indicative google photos.
Reference documents
Specifications for:
Site preparation,Excavation & backfill for underground installations,Fill, Grading and Paving,Testing Laboratory,Geotechnical Investigation
Definitions
GE Geotechnical Engineer
PSM Project Site Manager
SE Site Engineer
SOSafety Officer
QM/QEQuaity Manager/Quality Engineer
IS Infrastructure Superintendent
ST Survey Team
PPE Personal Protective Equipment
Responsibilities
It is an overall responsibility of the PSM to ensure that the site preparation activities are conducted according to the project specifications. PSM shall arrange all required resources.
The IS shall ensure that the site preparation activities are conducted according to this method statement as well complying with all specifications.
The GE shall ensure that the activities are conducted according to the project specifications and this method statement.
Safety
Prior to the commencement of any activities, the workforce shall receive a toolbox talk on the project site as well as on general safety requirements. SO shall ensure that the persons being inducted on site are well aware of the safety procedure to be implemented on site for the activity concerned.All persons upon the site shall wear PPE issued to them. Where possible hazards may arise from excavation activities, the necessary safety measures shall be taken to prevent accident or injury at all times. This may include provision of signage, barriers, watchman and lighting.Where work upon existing services is required, the necessary authority, permits and safety equipment shall be attained prior to the activity commencing. Scanning of existing services shall be conducted by suitable methods.
Method
The survey team shall locate and mark all services that are present upon the site (This includes above ground services as well as buried services). These services, (Electric, telephone, gas, oil, chemical, water etc), shall be clearly marked using stakes and warning tapes, reflected upon a site drawing and the issues raised with the client.
The survey team shall also mark upon the site plan all obstructions, structures and developments. Any obstruction encountered during excavation activities shall be plotted and recorded.
Where hazardous material is encountered, it shall be identified and isolatedin compliance with the safety procedures under SO supervision. The client shall be informed & hazardous material be collected and removed to a licensed tipping place. The details of the material and tipping arrangements shall be documented for review by the client as appropriate. Refer to Method statement Removal of hazardous materials.
Existing structures, fences and developments shall be demolished in a safe manner as site-stripping activities proceed. The necessary permits, approvals and permission shall be obtained from the concerned authorities prior to the commencement of the activity. The method of removal of these existing elements shall usually be conducted by dozer or breaker. Where necessary otherwise, discussions on site shall be made concerning alternate methods of removal when the full extent of these structures are exposed.
The removal of the topsoil shall include all vegetation and rubbish material from the work site.
Prior to the start of topsoil removal, the surveyor shall peg out the haul roads to be used by the construction equipment to execute all the site preparation activities. These roads shall be constructed by leveling of the existing terrain. Grade pegs shall be set to an agreed grid to indicate existing grade and reduced grade. Dependant upon the quality of the existing soil where the roads is to be built, suitable compactable fill may be imported or re-located from other parts of the site. The material shall be approved by the GE & QM/QE jointly.
These roads shall be maintained as the work proceeds.
Where required, water shall be spayed for dust control.
For general removal of the topsoil activities using appropriate equipment, the areas concerned shall be excavated and graded to levels that ensure adequate surface water drainage. The GE/QM/QE shall monitor the activity to ensure that the topsoil material is removed. Sampling and testing of the resultant material shall be conducted for specification compliance & proper compaction.
Upon completion of the topsoil removal activities where appropriate, the exposed surface shall be scarified, moistened and compacted to achieve the required density criteria. The areas shall be divided into manageable sections that be defined upon sketches. The GE shall monitor and test all sections. The results of the tests shall be recorded upon the relevant QC format. The number of tests conducted shall reflect the specification requirement.
In excavation areas, the GE shall review the material to be excavated to ascertain its suitability for re-use as fill material. This excavated material shall be transported to areas that require filling. The material shall be deposited onto the areas to receive filling, leveled, moisture conditioned and compacted. If necessary, stockpiling may be required.
The excavated areas shall be divided into manageable sections, which be defined upon sketches. The excavated areas shall be monitored by the GE to ensure that any unsuitable material does not appear. Where unsuitable material appears, it shall be removed. The excavated formation surface shall be treated by scarification, moistened and compacted according to the specification criteria. All areas shall be tested and the results recorded.
Where areas are to receive fill, the material that has been excavated shall be transported to the fill area, tipped, leveled, moisture conditioned and compacted. The material shall be spread and leveled in 200mm layers. The areas to be filled shall be divided into manageable sections that be defined upon a sketch. The fill layer shall be moistened and compacted to achieve the required specification criteria. No further fill activity shall be conducted upon an area that has not been approved and released by the GE. Attention shall be observed at edges and slopes, to ensure that compaction criteria are achieved. Additional layers of fill material shall be placed similarly as described above until the desired elevation has been achieved.
Production procedure.
Verification exercise for fill activity had been conducted to establish the economical and effective method for the fill activity.
Import and place fill to controlled areas of approximately 25m wide by 100 - 150m long.
Spread and level the imported fill.
Add water to the fill layer by passing the water tanker over the fill layer. The water tanker should pass over the layer twice.
A time gap of approximately two hours is allowed for the water to soak into the fill material.
The layer is now mixed with the grader until a uniform blend of moist material is achieved.
Additional water is added by passing the water tanker over the layer in a uniform sequence. A time period of approximately one-hour is allowed for this water to soak into the fill layer.
The fill layer is mixed again with the grader leaving the fill level to the correct grade.
Vibrating rollers shall now compact the fill layer in a logical sequence that compacts the fill layer uniformly.
Testing of the layer shall be conducted according to specification requirements.
Equipment
Dozers & Graders, Vibrating drum rollers, Dumper trucks, Excavators & Loaders, Water tankers
Attachment
None.Refer to indicative google photos as incuded as a facility. Assume there was nothing prior to construction & whole site was filled for preparationworks.