Regional Micro-Hydropower Capacity Development and Investment for Rural Electricity Access in Africa

UNDP Project Document

Governments of Mali, Togo, Benin, Cameroon, Congo-Brazzaville, Gabon, Central African Republic, Burundi, Rwanda and DRC

United Nations Development Programme

African Microhydro Initiative: Regional Micro/Mini-Hydropower Capacity Development and Investment for Rural Electricity Access in Sub-Saharan Africa

80

Regional Micro-Hydropower Capacity Development and Investment for Rural Electricity Access in Africa

TABLE OF CONTENTS

Section I: Elaboration of the Narrative 6

PART I: Situation Analysis 6

1.1. Context and Global Significance 6

1.2. Threats, Root Causes and Barriers Analysis 7

1.3. Institutional, Sectoral and Policy Context 13

1.4. Stakeholder Analysis 31

1.5. Baseline Analysis 31

Baseline Analysis 31

PART II: Strategy 38

2.1. Project Rationale and Policy Conformity 38

2.2. Project Goal, Objective, Outcome and Outputs/Activities 49

2.3. Load Curve Estimation, Peak Load Analysis and Productive – End Use Capacities 54

2.4. Investment Project Cost Estimation 55

2.5. Micro-hydro Financial and Economic Analysis 57

2.6. Project Indicators, Risks and Assumptions 66

2.7. Expected Global, National and Local Benefits 70

2.8. Country Ownership: Country Eligibility and Country Drivenness 73

2.9. Sustainability 75

2.10. Replicability 86

PART III: Management Arrangements 87

3.1. Implementation Modalities 87

PART IV: Monitoring and Evaluation Plan and Budget 91

4.1 Monitoring and Reporting 91

4.2 Independent Evaluation 96

4.3 Audit Clause 96

Section II: STRATEGIC RESULTS FRAMEWORK AND GEF INCREMENT 101

Part I : Incremental Cost Analysis 101

PART II : Logical Framework Analysis 101

SECTION III: Total Budget and Workplan 102

Section IV: Additional Information 107

PART I: Legal Context and Pre-requisites 107

List of Tables

Table 1: Electrification Rate in DRC 23

Table 2: Linking barrier removal and project design 52

Table 3: Levelized Cost of Micro-hydro Investments and Derivation of the cost of Electricity 58

Table 4: Levelized Cost of Diesel Gensets Investments and Derivation of the cost of Electricity 59

Table 5: Electricity Tariff evolution in Gabon 62

Table 6: Rwanda electricity tariff 1990-1997 64

Table 7: Evolution of Rwanda electricity tariff 1997-2005 64

Table 8 Environmental Risk Classification for West-Africa (Benin, Mali and Togo) 66

Table 9: Environmental Risk Classification for Central Africa 67

Table 10: Environmental Risk Classification for East-Central Africa 67

Table 11: Countries eligibility references 73

Table 12: Determination of weighted average KWh tariff for financial break-even in Benin 79

Table 13: UNDP-GEF baseline Diesel Scenario tariffs settlements for comparison with Prior/on-going Private Sector lead Diesel Operation in the decentralized rural electrification sector in Mali. 80

Table 14: UNDP-GEF Microhydro Scenario tariffs settlements before government contribution for comparison with Prior/on-going Private Sector lead Diesel Operation in the decentralized rural electrification sector in Cluster 3. 81

Table 15: UNDP-GEF Estimated Diesel Scenario tariffs settlements before government contribution for comparison with proposed Microhydro Tariff settlements in table 12. 82

Table 16: Break-even tariffs for equivalent Diesel generation scenario in Cluster 2 85

Table 17: Tentative financing plans of sub-regional projects (in million USD) 90

Table 18: Indicative Monitoring and Evaluation Work plan and corresponding Budget 98

Table 19: Financing plan by outcome/component (in million of USD) (excludes PDF B). 102

Table 20: Financing plan by level of intervention (national, sub-regional, regional) (in million of USD, excludes PDF B) 102

Table 21: Sources of co-financing 103

Table 22: Overall Project Financing Plan 103

Table 23: Project Financing Plan/West AFRICA 104

Table 24: Project financing Plan/Central AFRICA 104

Table 25: Project Financing Plan/East-Central AFRICA 105

Table 26: Overall cost and Financing Plan 106

List of figures

Figure 1: Proposed Ownership and Management for Micro-hydro Mini-Grid Systems 53

Figure 2: Proposed Execution Arrangements for Micro-hydro Mini-Grid Systems at National Level 54

Figure 3: Illustration of economic effect of Micro-hydro Activities in West African Countries 65

Figure 4: Opportunities for Load Curve improvement/displacement and revenue increase 83

Figure 5: Opportunities for Load Curve improvement/displacement and revenue increase 84

Figure 6: Load Profile Magoulumba-RCA 86

Figure 7: Proposed Execution Arrangements for Micro-hydro Mini-Grid Systems at National Level 89

LIST OF ACRONYMS AND ABBREVIATIONS

ABERME Benin Agency for Rural Electrification and Energy Management

AEC African Economic Community

AFD Agence Française de Développement

AfDB African Development Bank

AMADER Malian Agency for the Development of Domestic Energy and Rural Electrification

ARSE Autorité de Régulation du Secteur de l’Électricité au Togo/Electricity Sector Regulatory Agency

CAS Country Assistance Strategy

CAR/RCA Central African Republic/République Centre Africaine

CBO Community-Based Organization

CEDP Competitiveness and Enterprise Development Project

CEMAC Communauté Economique et Monétaire de l’Afrique Centrale

CFR Country Framework Report

CLIE Comité Local d’Initiative de l’Energie

COMESA Common Market for Eastern and Southern Africa

DE Direction de l’Energie

DGE General Electricity Directorate

DGHER Direction Générale de l’Hydraulique et de l’Electrification Rurale

DRC Democratic Republic of Congo

DSM Demand Side Management

Electrogz Public National Electricity company

ELGZ Electrogaz

ENDA Environmental Development Action in the Third World

ENERCA Energie Electrique de Centre Afrique

ESCO Energy Services Company

EU European Union

FMR Financial Monitoring Report

GEF Global Environment Facility

GHG Greenhouse Gas

GOR Government of Rwanda

GWh Gigawatt Hours

HFO Heavy Fuel Oil

IBRD International Bank for Reconstruction and Development

ICB International Competitive Bidding

ICT Information, Communications & Telecommunications

IDA International Development Association

IEPF Institut de l’Energie et de l’Environnement de la Francophonie

IRR Internal Rate of Return

JV Joint Venture

KIST Kigali Institute o f Science and Technology

kV Kilo Volt

kW Kilowatt

kWh Kilowatt Hour

LI Lahmeyer Intemational GmbH

LPG Liquid Petroleum Gas

LV Low Voltage

MFI Micro-Finance Institution

MinaLoc Ministry o f Local Government

MinInfra Ministry o f Infrastructure

MiniTerre Ministry of Lands, Environmental Protection, Water, and Natural Resources

MV Medium Voltage

MW Megawatt

NDF Nordic Development Fund

NEPAD New Partnership for Africa’s Development

NGO Non-Governmental Organization

OD Operational Directive

OP Operational Procedure

OPEC Organization of Petroleum Exporting Countries

PCU Project Coordination Unit

PPA Power Purchase Agreement

PPIAF Public Private Infrastructure Advisory Facility

PRSC Poverty Reduction Support Credit

PRSP Poverty Reduction Strategy Paper

PV Photovoltaic

RE Renewable Energy

RPM Regional Project Management

RURA Rwandan Utility Regulatory Authority

SBD Standard Bidding Documents

SHS Solar Home System

SIDA Swedish International Development Agency

SIL Specific Investment Loan

Sinelac National Electricity company o f the Great Lakes

SME Small and Medium-size Enterprise

SNEL National Electricity company of DRC)

SSM Supply Side Management

TA Technical Assistance

TOR Terms of Reference

UER Urgent Electricity Rehabilitation

UNDP United Nations Development Programme

UNEP United Nations Environment Programme

UNIDO United Nations Industrial Development Organisation

UPEGAZ Unit of Promotion and Exploitation of Gas of the Lake Kivu

UEMOA Union Economique Monétaire Ouest Africaine

VAT Value-Added Tax

Exchange rate: 1 US $ = 525 FCFA (May 2004)

Section I: Elaboration of the Narrative

PART I: Situation Analysis

1.1. Context and Global Significance

1.  In April 2004, GEF approved a PDF intended to assist 10 Sub-Saharan African countries in the preparation of a first regional micro/mini hydropower Capacity Development and Investment in rural electricity access in Sub-Saharan Africa. With co-financing from IEPF and the collaboration of the African Development Bank, an international project preparation Steering Committee composed of UNDP/UNDP-GEF, AfDB, UNEP, UNIDO, UN-ECA, the World Bank together with E&Co Inc. and two African NGOs (ENDA and KITE) was established to launch project preparation through the 10 participating UNDP-Field Offices. Additional key players were the national directorates of Energy, which had been collaborating on the project concept in recent years with UNDP-GEF and IEPF under the aegis of “Francophonie”.

2.  By way of a letter dated July 28th 2004 signed by the Burundian Minister of Communal Development followed up by a similar request dated July 29th 2004, which was signed by the Minister of Energy and Mineral resources, Burundi and UNDP-Bujumbura made a convincing case for the country’s participation in the first round of African Micro-hydro projects under UNDP-GEF. Principally, the need to assist Burundi on the same priority issues as in Rwanda, DRC and RCA was evident given the close geographical proximity with the above countries and the country’s documented sizable water resources in sharp contrast with the close to zero rural electrification rate.

3.  In September 21-22, 2004, the above African countries along with Burundi gathered in Douala (Cameroon) to: (i) review progress made towards the preparation of the First African Regional Micro-hydro Project, including; (a) technical feasibility studies; (b) financial/economic feasibility with Micro-hydro systems maintenance arrangements at the national and regional levels; (c) review of the project’s legal and institutional due diligence; (d) analysis of the provisional environmental impact assessments; (ii) discuss co-financing arrangements to ensure timely submission of the project to GEF Council (original target submission date was May 2005); and (iii) inform the participating countries of the eligibility criteria guiding the selection of the micro/mini-hydro sites to be equipped through the intended project activities. An important illustration of the level of commitment and ownership of the project by these countries was the pulling of national resources worth over US$0.5 million under the institutional umbrella of UNDP to support the feasibility phase, cover the expenses for knowledge sharing events and cross-fertilization of national experiences.

4.  As suggested by the participating countries’ electricity sector assessments/reviews, the beginning of any sensible attempt to provide productive rural electricity access through micro/mini-hydropower in ways that attract private sector financing is two fold: (i) mobilize and strengthen national capacity to manage and make the required adjustments to the sector’s regulatory/legislative framework (particularly, after many years of political isolation and donor absence in the post conflict countries) and (ii) take measures to significantly clarify the operational responsibilities of national utilities and improve the operational capacities of the national rural electrification agencies. Rural electrification rates in all participating countries are strikingly low and the prospect for improvement looks bleak given the focus of local energy institutions on urban electricity supply capacity increases. At the projected growth rate for rural electricity demand, and unless the use of a micro/mini-hydropower scheme has been successfully piloted, it will be extremely difficult to secure adequate private financing to meet rural electricity demand in the near future through micro/mini-hydropower systems. The most appealing option to governments in Sub-Saharan Africa could remain diesel-fired generators with even more reliance on fuel-oil instead of breaking the grip of the dependence on conventional fuels.

5.  All ten countries were visited by the Technical Feasibility team composed of five experts with complementary expertise and their findings with the technical recommendations laid a solid foundation for additional field missions by the other thematic teams (ESW –Economic Sector Work for each country, Financial Analysis of Power Utilities in connection with rural electrification issues, Legal/institutional review of the on-going reforms, Participatory approaches and Social Analysis, Environmental Impact Assessments, Micro-hydro Systems maintenance planning etc.). Overall, the above investigations were executed with an eye to strengthening the synergies and avoiding duplication given that the gaps in one country’s analysis could be offset by insights from sector analysis from a surrounding country. The regional approach of this project was found useful in establishing a minimum level of national ownership on renewable energy policies and rural electrification access with a consensus on the roles and responsibilities of the various players. When such a dialogue is initiated and the funding is within reach as it is the case with the AfDB’s co-financing commitment, some cooperation can be expected particularly with the catalytic support of UNDP-GEF and the momentum that can be created by regional synergies. The micro-hydro power project will also reduce the overall project costs among participating countries through economies of scale in addition to its policy leveraging impact. The remarkable level of cooperation of the host National Directorates of Energy allowed the field visits of several sites which had been identified through prior donor funded activity and/or during the review and discussions that took place within the PDF-B exercise. The positive reaction from the targeted rural beneficiaries helped enrich the socioeconomic and environmental data collected to put in focus the development of the project under GEF SP-3 principally.

6.  A sub-regional execution arrangement was agreed upon to allow for effective coordination, while maximizing managerial flexibility and efficiency. Given the political and social synergies as well as geographic proximity, the participating countries were grouped into three separate sub-regional projects:

·  West Africa: Benin, Mali and Togo;

·  Central Africa: Cameroon, Congo Brazzaville, CAR and Gabon;

·  East-Central Africa: Burundi, Democratic Republic of Congo (DRC) and Rwanda.

1.2. Threats, Root Causes and Barriers Analysis

1.2.1 Barriers and Constraints to Micro-hydro power Development in participating countries

7.  While the lifecycle costs of the electricity produced by small hydro power plants can be comparable to the price of non-subsidized electricity from the grid and lower than electricity costs of a diesel generator, different market barriers have so far prevented the broader adoption of small hydro power plants for rural electrification. During the preparatory phase of this project, an analysis of the barriers to the adoption of micro/mini-hydropower[1] in West, Central, East-Central African countries was conducted at the regional level. The outcome of the investigation served as a basis for the design of the current project. The common threads that were identified throughout the region can be summarized as follows:

Policy Barriers

·  Lack of an enabling policy, legal and regulatory framework for the development and operation of small hydro power projects by the private sector, touching issues such as land and water use rights, tariff setting, required certificates and licenses, conflict solving procedures, possible incentives and competitiveness with other, eventually subsidized energy sources (such as diesel or grid electricity) etc.

·  Weak institutional framework and capacity, at all levels (sub-regional, national and local) to support the rural electrification on the basis of the available renewable energy sources. For instance, only very few or none of the recently established Rural Electrification Agencies in Sub-Saharan Africa appear to have the development of renewable energy solutions as a component of their principal mandate; and there are no electrification agencies or institutions that are currently considering – without GEF intervention – a focus on micro-hydropower for rural areas.