4 Laning of NH-17 from km. 283+300 to km 358+080 (Section 1) and Mangalore – Kerala Border (Km 375+300 to Km 376+700 (i.e. Nantoor Circle to Mahaveer Circle) and km 3+700 to km 17+200 (i.e. Mahaveer Circle to Kerala Border) (Section 2) in the state of Karnataka” – (Package No. NHDP – III / BOT / KNT/04)
Physical Progress Status as on 26.10.2016
Sl.No / Description / Unit / Total / Completed up to September2016 / During the month up to 26.10.2016 / Total Completed as on 26.10.2016 / Balance / Remarks
1 / BC / Km / 90.08 / 81.955 / 0.00 / 81.955 / 8.125 / In progress.
2 / DBM / Km / 90.08 / 81.955 / 0.00 / 81.955 / 8.125 / In progress.
3 / WMM / Km / 90.08 / 82.31 / 0.00 / 82.31 / 7.77 / In progress.
4 / GSB / Km / 90.08 / 82.12 / 0.00 / 82.12 / 7.96 / In progress.
5 / SG / Km / 90.08 / 82.30 / 0.00 / 82.30 / 7.78 / In progress.
6 / EMB / Km / 90.08 / 80.94 / 0.00 / 80.94 / 9.14 / In progress.
7 / CG / Km / 90.08 / 81.14 / 0.00 / 81.14 / 8.94 / In progress.
8 / Major Bridges / Nos / 9 / 9 / 9 / Nil
9 / Minor Bridges / Nos / 10 / 9 / 0 / 9 / 1 / Yet to be start. (Falling in Padubidri existing alignment).
10 / Flyovers / Nos / 3 / 0 / 1 / 1 / 2 / In progress.
11 / ROB / Nos / 1 / 1 / 1 / Nil
12 / VUP / Nos / 3 / 2 / 0 / 2 / 1 / 1 No. yet to be start.
13 / PUP / Nos / 5 / 2 / 0 / 2 / 3 / 2 no. Yet to be start & 1 no. in progress.
14 / CUP / Nos / 2 / 2 / 2 / Nil
15 / RE Wall / Sqm / 57749.562 / 23043.61 / 0 / 23043.61 / 36156.792 / In progress.
16 / Subway / Nos / 1 / 0 / 0 / 0 / 1 / Yet to be start.
17 / Rest Area / Nos / 1 / 0 / 0 / 0 / 1 / Land to be handed over by NHAI.
18 / Toll Plaza / Nos / 3 / 0 / 2 / 2 / 1 / 1 In progress.
19 / Box Culvert / Nos / 126 / 114 / 0 / 114 / 7 / In progress (4 nos not constructed at site)
20 / Pipe Culvert / Nos / 106 / 87 / 0 / 87 / 13 / In progress (6 nos not constructed at site)
21 / BusBays / Nos / 50 / 30 / 0 / 30 / 20 / In progress.
22 / Truck Lay Bays / Nos / 5 / 1 / 1 / 2 / 3 / In progress.
23 / Major Junctions / Nos / 24 / 12 / 0 / 12 / 12 / In progress.
24 / Minor Junctions / Nos / 316 / 249 / 25 / 274 / 42 / Yet to be start.
25 / Over Pass / Nos / 1 / 1 / 0 / 1 / Nil

Cumulative Physical Monthly Progress up to 26thOctober 2016: Pie Chart

Physical Progress achieved upto 26thOctober 2016.

Balance