ISO New England Operating Procedure OP-5 - Resource Maintenance and Outage Scheduling,

Appendix B

Appendix B -

Outage Request Form

Table of Contents

Form 1 - Appendix B - Outage Request Form 2

OP-5 Appendix B Revision History 3

Form 1 - Appendix B - Outage Request Form

Capacity Resource ID (only required for Import Capacity Resources):

For generator/DARD/ATRR: Asset ID: Asset Name:

For DRR: DRR ID: DRR Name:

Seasonal Claimed Capability /

Regulation capability /

Nominated Consumption Limit:

Seasonal DR Audit value:

Amount of physical reduction /

Amount of Regulation reduction /

Inability to interrupt:

Blackstart capable during outage (Yes/No) :

FCM exempt (Yes/No):

Preferred outage start date/time:

Projected outage end datetTime:

Outage/reduction reason:

Work to be accomplished:
Flexibility of the requested outage dates/times:

EMAIL TO: and

Note: Use Outage-Request Template to submit this form.

OP-5 Appendix B Revision History

Document History (This Document History documents action taken on the equivalent NEPOOL Procedure prior to the RTO Operations Date as well revisions made to the ISO New England Procedure subsequent to the RTO Operations Date.)

Rev. No. / Date / Reason /
Rev 1 / 02/01/05 / Updated to conform to RTO terminology
Rev 2 / 06/24/05 / Renamed to Appendix B since former Appendix A has been terminated
Rev 3 / 10/01/06 / Updated for ASM Phase 2
Rev 4 / 12/11/09 / Updated for FCM
Rev 5 / 12/01/10 / Biennial review by procedure owner;
Reformatted entire document, changed font, minor editorial and format changes, added uncontrolled disclaimer to 1st page footer and “Hard Copy is Uncontrolled” to each page footer,
Updated for ISO outage application software
Rev 6 / 11/29/12 / Biennial review by procedure owner, resulted in no document content changes required, only make administrative updates;
Added cover page with Table of Contents;
1st page Footer, deleted disclaimer 2nd paragraph;
Rev 7 / 10/29/14 / Biennial review by procedure owner;
Updated OP-5 Title in Headers;
Modified to add data entry for ATRR regulation capability and reduction;
Rev 8 / 09/09/16 / Biennial review by procedure owner;
Added required corporate document identity to all Footers;
Added comment to require generators to add reason for outage/reduction;
Rev 9 / 06/01/18 / Biennial review by procedure owner;
Updated OP-5 title in headers;
Globally made editorial changes to be consistent with current conditions, practices and management expectations;
Updated for PRD;

Hard Copy Is Uncontrolled

Revision 9, Effective Date: June 1, 2018 Page 3 of 3