Page 1
AGENDA
Meeting
Review of Draft Remediation Plan (RP) for Adaya Site
20-24 February 2012, Room F8 17, Vienna, Austria
Monday, 20 February 2012
1.
/Welcome
a)Introductionsb)Agreement of agenda /
IAEA
All
All2.
/IAEA Safety Standards on Remediation
a)Legal and regulatory framework, remediation criteria, and general contents of a remediation planb)Discussion / Zhi-Wen Fan, IAEA
All
3.
/Site Description
a)Presentation of site (includes description, photos, and any videos of site and surrounding areas)-Remediation Plan of Adaya Nuclear Site
b)Discussion / MoST Representative
Hadi Jassim
All
Afternoon Session
4.
/Regulatory Review
a)Regulatory Review (including draft legal and regulatory framework for remediation activities, remediation criteria and licensing process)b)Discussion / (Lead Facilitator-R. Stenton)
MoEN Representative
Shaker HamedRayiss
All
5.
/Project Management and Planning
a)Licensing Plan (including schedule of remediation activities) and Cost estimate
b)Discussion
/ (Lead Facilitator-D. Killey)All
Tuesday, 21 February 2012
6.
/ Characterisation Activitiesa)Historical Assessment; Characterisation Plan/Report
- Characterization Plan of Adaya Nuclear Site
b)TTU Survey at Adaya Site /
(Lead Facilitator-D.Killey)
MoST RepresentativeHadi Jassim
Ron Chesser and Brenda Rogers, TTU
Afternoon Session
7.
/ Characterisation Activitiesc)Recommendations for surface characterisation of Adaya Burial Site – (13:00)
d)Comments on the Characterisation Activities by Regulatory Body
e)Discussion
/(Lead Facilitator-R.Stenson)
Didier Dubot, CEA
MoENRepresentative
AllWednesday, 22 February 2012
8.
/Strategy, Technology and Techniques
a)Remedial Options
b)Remediation Actions: TechnologyTechniques
c)Discussion
d)TTU In-vitro Bioassay Studies(10:00am) /(Lead Facilitator- R. Stenson)
AllBrenda Rodgers
Afternoon Session
9.
/ Specific Assessmentsa)Safety Assessment
b)Environmental Assessment (including Hydrology and Erosion Protection and impacts)
c)Dose Assessment and Radiation Protection
d)Discussion /
(Lead Facilitator-D.Killey)
All
Thursday, 23 February 2012
10.
/Waste Management Activities
a)Waste Management (Including storage and transport of waste for final disposal)b)Discussion /
(Lead Facilitator-R.Stenson)
All11.
/ Remediation Management Activitiesc)Remediation Management (Including quality assurance, training, record management)
d)Discussion /
Lead Facilitator- D. Killey)
AllAfternoon Session
12.
/ Maintenance, Monitoring and Surveillance Programmes and Institutional Controla)Maintenance, Monitoring and Surveillance
b)Institutional Controls
c)Discussion /
(Lead Facilitator-R.Stenson)
All
13.
/ Emergency Planning and Physical Protectiond)Emergency Plan
e)Physical Protection Plan
f)Discussion /
(Lead Facilitator-D.Killey)
All
Friday, 24 February 2012
14.
/ Final survey plana)Survey Plan for post-remediation activities
b)Discussion /
(Lead Facilitator-D.Killey)
All
15.
/Prepare Action Plan on issues identified during week
/All
16.
/Summary, next steps, and closing discussion
/IAEA
Normal Working Times
- Morning session: 09:00 – 12:00
- Lunch: 12:00 – 13:00
- Afternoon session: 13:00 – 17:00
Read-ahead material provided by MoST Representatives
- Remediation Plan
- Characterisation Plan/Report
- Safety Assessment