Layered Process Check
Instructions
1. Operator: Perform audit daily for 1 week and document any findings and corrections made below. / 4. Production Manager: Perform the Layer 3 audit once during the month.2. Supervisor: Perform the Layer 2 audit once per week / 5. Production Manager: See the QA manager for any nonconformances listed.
3. Supervisor: Document any findings and corrections made below. / 6. QA Manager: Issue CAR’s to the Production Manager as required based on the 3 audits performed.
Audit Items
= Satisfactory
NS = Not Satisfactory
N/A – Not Applicable / Unit Of Measure
(Deg F, Deg C, Sec., Min., PSI, Lbs., etc.) /
Initials
Shift
Date
/ Layer 1 – Daily by Operator (Initials) / Weekly Audit By SupervisorSunday
/ Monday / Tuesday / Wednesday / Thursday / Friday / SaturdayDate
1 2 3 / 1 2 3 / 1 2 3 / 1 2 3 / 1 2 3 / 1 2 3 / 1 2 3- Process Parameter #1(Pressure, Load, Time, Temp, etc.)
Actual
- Process Parameter #2 (Pressure, Load, Time, Temp, etc.)
Actual
- Process Parameter #3(Pressure, Load, Time, Temp, etc.)
Actual
- Process Parameter #4(Pressure, Load, Time, Temp, etc.)
Actual
- Process Parameter #5(Pressure, Load, Time, Temp, etc.)
Actual
- Is measuring equipment in Calibration?
- Is part dimensionally correct, and check sheet complete? (1Pc)
- Are safety rules followed?
- Are all parts contained and labeled correctly?
- Is the area clean and orderly?
- Is scrap placed in RED marked bins/containers?
Weekly Audit Performed By:
/ Monthly Audit Performed By: / Date:Item #
/ Finding for any NS items / Immediate Action/Correction TakenUse the back of this sheet if more space is needed
Item #
/ Finding for any NS items / Immediate Action TakenForm: F-822101-1Rev: 5/5/04