CIVL 493 CONSTRUCTION MANAGEMENT
REVIEW QUESTIONSDate: 21/04/2015
- An owner choses a delivery method in response to the amount and type of risk that he or she sees in a project. True or False
- A delivery method is a type of contracting method. True or False.
- Which of the following reasons will not cause a contract change?
- A change in owner requirements
- Unforeseen conditions
- Designer omissions or errors
- Poor job-site productivity
- None of the above
- Which type of contractual agreement could be used when the quantities of work are difficult to determine in advance yet still provide price competition?
- Single fixed price
- Unit price
- Cost plus a fixed fee
- Cost plus a percent fee
- None of the above
- To ensure maximum competitive advantage and the best subcontractor price for an owner, a construction manager should seek twelve or more bidders per work package. True or False
- A bid breakdown submitted by the bidder can be useful in guiding contractor progress payments. True or False
- A bidder who submits the low bid using an alternate not equal to the original specifications but now acceptable to the owner should win the contract. True or False
- Bid alternates priced by the contractor and accepted by the owner lead to an increase in the contract sum. True or False
- A project that is builtsignificantly under budget is good and indicates a competent designer. True or False.
- An estimate prepared by the design firm at the end of design development guarantees the project completion cost to the owner. True or False.
- As a project moves on time, the accuracy of an estimate improves and cost and time to complete it lessen. True or False
- Which of the following will not increase the cost of a project?
- Increased square footage
- Increased inflation
- Increased availability of labor
- Increased demand (faster schedule) for the finished project
- Increased quality expectations
- As the square footage of a project increases, what happens to the cost per square foot?
- It decreases at a decreasing rate
- It decreases at an increasing rate
- It increases at a decreasing rate
- It increases at an increasing rate
- It stays the same
- Which of the following is not a reason for construction cost variation among different geographic locations?
- Local union bargaining agreements
- Physical project size
- Rail/roadway/harbour capability
- Local construction activity
- None of the above
- A private sector owner has more flexibility in designer and builder selection and choice of delivery method than does a public owner. True or false.
- Which project participant is responsible for establishing the project objectives?
- The owner
- The architect
- The engineer
- The constructor
- All of the above
- Which of the following should be considered in establishing organizational structure for the management of a construction project?
- How work functions will be compartmentalized
- The number of resources to be committed to the project
- Whether decisions should be made in a centralized or decentralized manner
- The degree of need for interdisciplinary work
- All of the above
- Contract changes are likely to occur on a single fixed price contract than on a cost plus a fee contract. True or False.
- Which of the following is not a local condition necessary to investigate before the beginning of a project?
- Subsurface site conditions
- Site access
- Availability of skilled labor
- Codes and regulations
- Project drawings and specifications
- Good work package definition is critical to successful price and schedule control. True or False.
CIVL493 REVIEW QUESTIONS / 1