High Value Contracts (More than One Crore) (As on. 16.12.2013)

S. No. / NIT No. / Name of work / Accepted Value
(Rs. In Crs) / Name of Contractor / Date of Acceptance / Original date of completion / Progress
(Financial)
1. / 62 of
2009-10 / Supply & stacking of 20190 cum 65mm gauge hard stone machine crushed ballast on cess in the section of RKB-JSM under ADEN/JSM. / 1.06
Enh- 1.42 / M/s Bhaniyana Const., Jaisalmer. / 14.09.09 / 13.05.10 Ext.
30.11.10 / 98%
2 / 105 of 2009-10 / RCC jacketing & replacement of bed block of Br. 42 at km 16/14-15 & Box bridge No. 145-A at km 135/8-12, Replacement of cracked ballast retainer of bridge No. 48 at of RCC Box Br. No. 126 A at km 108/13-14 on RKB-JSM section under ADEN/JSM. / 1.73 / Satish Malpani Jodhpur / 07.01.10 / 06.11.10 30.8.13 31.10.13 / 64%
3. / 126 of 2009-10 / Up gradation of manned L-Xing C-Class to Spl. Class & Up gradation of manned L-Xing C-Class to A-Class & provision of duty hut at L-Xing & gang rest shelter, store godown etc in the section of RKB-JSM under ADEN/JSM. / 1.01 / Shri K.S. Mehra,
Jodhpur / 09.02.10 / 08.12.10 / 82%
4. / 94 of 2009-10 / Execution of various P.Way works mainly provision of over runs/deed ends, laying of fan shaped turnouts in connection with Std.-III interlocking work in FL(ex)- MTD (ex) section, laying/ linking of additional loop line at Jalsu & other misc. connected works under ADEN/DNA. / 1.28 / M/s Jai Bharat Rail Nirman, Nagaur / 22.01.10 / 21.12.10
30.06.13
30.09.13 / 70%
5. / 37 of
2008-09 / Welding of rail joints 10,000 No’s with SKV process in the various section of Jodhpur Division. / 2.45 / M/s India Thermit Corp. Ltd. Kanpur / 28.11.08 / 04.12.09
Ext
30.06.13 / 69%
6. / 134 of 2010.11 / Replacement of 29 No. existing quarters (Type-I) by providing 29 No. Type II Quarters 20 No. at MMY & 9 No. at OSN on age cum condition basis on RKB-JSM section under ADEN/JSM.(Including Electric work) / 1.52/1.89 / M/S Kera Ram Poosa Ram, Jodhpur. / 27.10.10 / 26.06.11 31.07.13 / 86%
7. / 131 of
2009-10 / Welding of Rail Joints 7654 Nos with SKV process in the section of ADEN/JSM. / 1.93 / The ITC Ltd. Kanpur / 17.9.10 / 16.05.11
31.12.13 / 53%
8. / 101 of 2010.11 / Prov. of R.C.C. BOX Br. (Ltd Ht. Sub way) 9 No. LC No. C-82,Km 176/5-6,c-85 at Km181/5-6,C-97 at Km 206/8-9, C-32 at Km 48/4-5, C-110 at Km 251/5-6, C-35 at Km 53/0-1, C-36 at Km 54/8-9, C-105 at Km 237/9-238/0, C-33 at Km 49/6-7 on RKB-JSM section under ADEN/ JSM.. / 5.13 / Jagtaji Cemcon Parmar Sonipat (Haryana). / 17.09.10 / 16.09.10
Ext
15.03.13 / 72%
9. / 360 of 2008-09 / Supplying and loading into ballast hoppers machine crushed railway track ballast of 1,00,000 cum at Pokran Mega ballast depot under ADEN/Special/JU in Jodhpur division of NWR. / 3.80/ 4.08 / M/S Bhaniyana Constructions. Pokran / 11.08.10 / 10.11.11
Ext
10.10.12 / 97%
10. / 100 of
2010.11 / Provision of R.C.C. BOX BRIDGE.( Limited Height Sub way) at L-xing No-C-36 at KM 709/3-4,C-29 at KM 698/2-3, C-221 at KM 651/9-10, C-11 at KM 674/6-7, C-49 at KM 726/2-3, C-47 at KM 724/12-13, C-5 at KM 663/3-4, C-2 at KM 698/2-3, on HWT-MJ & C-161 at KM 612/3-4, C-134 at KM 570/5-6, on MTD-JU section under ADEN/Line /Jodhpur. / 5.72 / OM Prakash Goyal & Co. Neemuch (M.P.) / 28.09.10 / 27.09.11
Ext
31.01.12 / Work completed final bill received. Variation under vetting
11 / 105 of
2010.11 / Provision of R.C.C.BOXBRIDGE ( Limited Height Sub way) at L-xing No-C-27 at KM 44/4-5, at L-xing No-C-26 at KM 40/9-41/0, at L-xing No-C-11 at KM 18/2-3, at L-Xing N….. on DNA–RTGH section & at L-xing No-C-80 at KM 497/5-6, C-92 at KM 513/1-2 between MTD-DNA under ADEN/DNA. / 5.50 / Marwar Metals Pvt. Ltd., Jaipur / 11.10.10 / 10.10.11
Ext
31.03.13 / 73%
Work Physically comp. Final bill & variation received. under vetting.
12 / 118 of 2010-11 / Provision of 40 Type II quarters on BGKT colony on replacement basis at Jodhpur under ADEN/HQ/JU. / 1.86 / M/S Stand.Const.Co
Jodhpur. / 24.09.10 / 23.07.11
Ext
30.9.12 / 70%
Work terminated on 27.8.13, Final bill/variation awaited.
13 / 102 of 2010.11 / Const of RUB in replacement of LC No. C-14, Bet. MKSR-BAWA, LC No.C-17 Bet. MKSR-BAWA, LC No.C-37 Km 50/15-16, LC No……. be bet BIPR-MBNL, LC No……. bet RNV-MSQ, LC No.124 bet MSQ-JARI, LC No.148 bet RXN-JNZ, LC No.155 Km 209/6-7 bet JNZ-BLDI on SMR-BLDI section under ADEN/SMR. / 6.21 / Jagtaji Cemcon Parmar Sonipat (Haryana). / 17.09.10 / 16.09.11
Ext
30.09.13 / 80% final Bill awaited.
14 / 82 of 2010.11 / Provision of Gate Gumties, road surface, check rail & Allied work in connection with manning of unmanned. Level crossings in the section of ADEN/SMR. / 1.04 / Shri Kera Ram s/o Poosa Ram, Jodhpur. / 14.09.10 / 13.03.11
Ext
31.12.12 / 98% Final Bill Reeived. Variation under process.
15 / 108 of 2010.11 / Replacement of old low level Plinth arch type 67 type I, Quarters by standard type II Quarters in the section of ADEN/MTD. / 3.49 / Kera Ram S/o Poosa Ram, Jodhpur. / 22.12.10 / 21.10.11
30.08.13 30.04.14 / 66%
16 / 140 of 2009-10 / Improvement to leaky roof & Replacement of old damaged wooden doors in various colony in the section of ADEN/HQ/JU / 1.82 / M/S Kera Ram Poosa Ram & Co. Jodhpur. / 6.5.10 / 05.03.11
Ext
30.11.12 / 95% Final Bill awaited
17 / 198 of 2010-11 / Construction of Gate Lodge (Type II Quarter) in connection with Manning of 17 Nos……(LC No.107, 121, 123, 125, 129, 131, 136, 141, 142, 144, 147, 149, 152, 160, 162, 163, 168) on SMR-BLDI Section under ADEN/SMR. / 1.90 / Bhinmal Contractors,
Property & Land Devel. Pvt. Ltd.
Mumbai / 3.3.11 / 02.03.12 Ext
31.05.12 / 17% Closed on Admn Ground. Variation & F/Bill receicved.
18 / 219 of 2010-11 / Provision of integrated coach care complex at BME station on SMR-BME section under ADEN/BME. / 1.27 / M/S Om Bldrs,
Jodhpur. / 20.4.11 / 19.12.11
31.08.13
31.12.13 / 79%
19 / 60 of
2012-13 / Provision of PF shelter 15 Bay at PF No. 4 & 5 at Jodhpur station and 8 bay PF No. 1 at RKB under ADEN HQ JU / 1.85 / Dhanshree Const. Nehru Nagar Jaipur. / 24.08.12 / 23.04.13
27.10.13 30.12.13 / 22% Work in Progress
20 / 50 of
2012-13 / Provision of washable apron at Merta Road under ADEN MTD / 1.49 / OM Builders Jodhpur / 07.08.12 / 06.12.12
05.10.13
31.01.14 / Nil
21 / 56 of
2012-13 / Provision of washable apron line no.6 at JODHPUR under ADEN LINE JU / 1.48 / Durga Cosnt. Jodhpur / 16.07.12 / 15.03.13
31.10.13 / 55%
22 / 63 of
2012-13 / Provision of PF shelter 12 Bay at PF No. 1 12 Bay at PF 2 & 3 at Jodhpur station with kota stone flooring under ADEN HQ JU / 1.90 / Dhanshree Const. Nehru Nagar Jaipur. / 28.09.12 / 27.05.13
27.10.13 30.12.13 / 18 %
Work in progress.
23 / 78 of 2012-13 / Ancillary Work in C/W TBR at 45.0 km ……. ON RKB-JSM SEC under ADEN/JSM. / 1.21 / Girdhari Ram S/O Sajan Ram JU / 16.11.12 / 15.07.13
31.12.13 / 43%
Work in progress.
24 / 116 of 2012 / Extension and improvement of washable apron at Line no. 3 & 4 in JU yard. / 2.10 / Girdhari Ram S/O Sajan Ram JU / 13.12.12 / 13.10.13 / 51% . Work in progress
25 / 89 of 2012 / Supply of Ballast at POK DEPOT under ADEN JSM / 6.27/6.77 / M/S Bhaniyana Constructions. Pokran / 20.11.12 / 19.02.14 / 98%
Work in progress
26 / 156 of 2012-13 / Provision of LHS in lieu of LC NO. C-143 &C-153 ….under ADEN/SMR. / 1.15 / Osian Maa Builders. JU / 28.12.12 / 27.06.13 / 29%
Work in progress
27 / 231 of 2012 / Ancillary work in C/W TBR of 90 Km in LN-SMR-BME section bet K. 668/ TO 758 under DEN/W. / 1.13 / Oswal Const. Co. Kota / 01.05.13 / 31.12.13 / 13%
Work in progress
28 / 178 of 2012 / Provision of RCC Box bridge at LC NO. C-78 , C-97 & C/137 in SMR-BLDI ….under ADEN/SMR. / 2.25 / Osian Maa Builders. JU / 16.03.13 / 15.11.13 / 21%
Work in progress
29 / 169 of 2012 / Provision of Bridge at Breaches site at KM. 854.420, & 855 & 856 ……..IN Barmer – Munabao section / 1.51 / Osian Maa Builders. JU / 28.03.13 / 27.09.13 / PG deposited
Work in progress.
30 / 21 of 2013-14 / Supplying ballast in stacks and loading in to ballast hoppers machine crushed Railway track ballast 60,000 cum of 65mm gauge at Samdari Megha ballast Depot under ADEN/SMR. / 3.03 / M/S Kera Ram Poosa Ram & Co.,Jodhpur. / 01.08.13 / 30.04.14 / 11%
Work in progress.
31 / 76 of 2013-14 / Provision of RCC Box Bridges (Limited height sub way) 4 nos. at Level crossing No.C-4,C-16,C-35 & C-28 on LN-MJ section under ADEN/Line/Jodhpur. / 3.39 / Osian Maa Builders. JU / 05.08.13 / 04.07.14 / PG deposited
32 / 96 of 2013-14 / Provision of RCC Box Bridges (Limited height sub way) 4 nos. at Level crossing No.C/207, C/209, C/210, C/211 / on LN-BGKT section under ADEN/Line/Jodhpur. / 4.22 / Osian Maa Builders. JU / 05.09.13 / 4.4.14 / PG yet not deposited
33 / 77 of 2013-14 / Provision of RCC Box Bridges (Limited height sub way) 4 nos. at Level crossing No. C/215, C/216, C/217, C/218 on LN-BGKT section under ADEN/Line/Jodhpur. / 3.82 / Osian Maa Builders. JU / 02.08.13 / 01.03.14 / 06%
Work in progress.
34 / 125 of 2013-14 / Zone Contract (Masonary & Painting ) Zone- 1 Residentail building in N.P. Colony, DS Colony,……..Under the section of ADEN/HQ/JUM / 1.21 / Rama Kishan Prajapat, Cont. Jodhpur. / 18.10.2013 / 30.06.14 / PG Deposited work in progress.
35 / 79 of 2013-14 / Provision of RCC Box Bridges (Limited height sub way) 5 nos. at Level crossing No. C-104, C-115, C-117, C-118 & C-121 on RDRA-JSM section under ADEN/JSM. / 4.11 / Jagtaji Cemcon Parmar Sonipat (Haryana). / 12.11.13 / 11.06.14 / PG has yet not been deposited.
36 / 78 of 2013-14 / Provision of RCC Box Bridges (Limited height sub way) 4 nos. at Level crossing No. C-87, C-94, C-95 & C-98 on RDRA-JSM section under ADEN/JSM. / 3.28 / Jagtaji Cemcon Parmar Sonipat (Haryana). / 12.11.13 / 11.06.14 / PG has yet not beendeposited.
37 / 95 of 2013-14 / Provision of R.C.C. BOX BRIDGE (Limited Height Sub way) 04 Nos at L-xing number C-79, C-80, C-83 & C-84, on RKB-JSM section under ADEN/JSM. / 3.31 / Jagtaji Cemcon Parmar Sonipat (Haryana). / 12.11.13 / 11.06.14 / PG Deposited Agreement under execution
38 / 162 of 2013-14 / Provision of rail level concreted platform measuring 700 x 15 met. of Nawa City for salt loading under ADEN/DNA. / 1.82 / Marwar Metals Pvt. Ltd., Jaipur / 13.11.13 / 12.08.14 / PG has yet not deposited.