J-295 GEORGIA GWINNETT COLLEGE

August 3, 2017

BID FORM

BIDDER INFORMATION:

(Name) (Contact Name)

(Street Address) (City, State, Zip)

( )

(Phone Number) (Email)

BID PACKAGE NO. & DESCRIPTION: 7D – Sprayed Insulation

ADDENDUM ACKNOWLEDGEMENT: None

1. BASE BID: Bidder has examined the bid documents, existing conditions, and acknowledges receipt of all attachments indicated in the Invitation to Bid. Bidder is fully informed as to the nature of the work and conditions relating to its performance. Bid includes all labor, materials, equipment, tools, taxes, permits and all other items necessary for the proper and complete execution of the work. Bid shall be valid for 60 days. Bidder agrees to execute Winter’s standard Subcontract Agreement and to meet Winter’s standard insurance requirements.

The base bid for the referenced scope of work is:

Dollars $( )

Break Out Price for Submittal Package (includes complete submittal package, including submittals, samples, product data, shop drawings, calculations as required for this scope of work).

Dollars $( )

**The amount for the Submittal Package is included in the base bid.

Note: It is Winter’s intent to award this scope of work in early September. Winter intends to begin mobilization activities early August pending Land Disturbance Permit.

2. UNIT PRICES: The Contract Sum will be increased or decreased per quantities of added or omitted Work based on unit prices accepted by the Owner.

A. Inclusions: Unit prices shall include all costs including, without limitation, costs for material, labor, fabrication, delivery, unloading, handling, protection, storage, tools, equipment, supervision, taxes, insurance, overhead, and profit.

B. Duration: All unit prices shall be held good and unchanged for the duration of the contract unless specified or agreed.

C. Provide unit prices for the following items:

N/A

3. SCHEDULE: Bidder understands that mobilization is scheduled to begin August 1, 2017 with material completion of the project 11 months. Bidder has included the necessary personnel to complete this work in the allotted time.

Indicate duration for the following items:

A. Provide submittals/product data/samples Days

4. VE/ALTERNATES: Alternates are Not Accepted as part of the base bid. If Trade Contractor would like to propose an alternate or VE option, please list below.

A. Alternate 1: ADD/DEDUCT $ ______

B. Alternate 2: ADD/DEDUCT $______

C. Alternate 3: ADD/DEDUCT $______

5. General Scope Requirements

1.  Subcontractor agrees to comply with photo badging system for all workers.

2.  Just in time deliveries are required.

3.  There is no on-site parking. An off-site parking area will be provided. Cost associated with shuttle transportation from off-site parking to the jobsite will be at the responsibility of the Subcontractor.

4.  The campus and jobsite are 100% tobacco and smoke-free.

5.  Subcontractor employees are not permitted to enter campus buildings or dining halls. Workers are confined within the limits of the construction fence.

6.  Subcontractor employees shall not fraternize or socialize with campus employees and students.

7.  Walking through the campus from off-site parking area to the jobsite will not be permitted.

8.  Compliance with all requirements under Georgia Peach Program

9.  Compliance with all requirements under Commission Plan

10.  Compliance with BIM Coordination Execution Plan

6. Trade Specific Scope Requirements

1.  Sprayed Insulation