Story Board – 3 Telford Way

This EPC was completed as part of attendance of the Stroma NDEA Level 3 course on 6th November 2008.

Date / Action / Photo / Further information
5/11 / Informed on course that we would be conducting a survey of the property the following day. Location of property and condition provided.
6/11 / Arrived at site. Conducted external risk assessment of building and site. Conducted external survey of building.
North elevation showing:
1)  Traffic hazards,
2)  Entrance door,
3)  Roller shutter door,
4)  Ground floor and first floor windows /
East elevation showing:
1)  Bank to east of building which presents a slip hazard /
West elevation showing:
1)  External component of ‘split system’ comfort cooling units.
2)  Brick elements of brick and block construction
3)  Insulated metal clad wall construction
4)  Windows /
View of west elevation showing
1)  Vents from mechanical extraction vents
2)  Details of brick construction /
Conducted internal walkthrough and risk assessment. Provided with drawings. /
Conducted survey of main warehouse. Zone z0/01. /
Electric meter in z0/01 /
Gas meter in z0/01 /
1 of 3 250w Metal halide floodlights in Zone z0/01
Dextra Avalon AVAH 250L Aluminium E40 250W HQI – T
http://www.dextralighting.co. uk/pdf/exterior/avalon.pdf /
Photo showing detail of exterior wall construction – from interior
Insulated brick and block below 2.5 m and insulated metal cladding above /
Roof above z0/01 showing roof lights in line with roof /
z0/01 showing ground floor and first floor /
z0/01 roof and wall cladding detail /
Conducted survey of z0/02
Photo showing
1)  Un-fanned electric resistance heater,
2)  Window
3)  Luminaries each containing 4x18w T8 standard ballast fluorescent lights /
Detail of suspended ceiling and block and beam floor above z0/02 /
Domestic style boiler in z0/04 /
Manual of boiler: Ideal Mini C28 - 28kW combi non condensing wall mounted gas boiler – sedbuk.com states seasonal efficiency as 78.3% /
Detail of 70W T8 standard ballast fluorescent light typical of remainder of building except z0/01 and z0/02 /
z0/05 showing typical radiator /
z0/06 showing twin 70w T8 standard ballast fluorescent lights /
z1/01 view of first floor showing
1)  70w T8 standard ballast fluorescent lights
2)  Windows
3)  Internal component of split system /
6/11 / Returned to course base and started to prepare zone plans from site notes
24/11 / Completed zone plans
24-25 /11 / Entered data into iSBEM
11-18th Mar 2009 / Completed storyboard, risk assessment form and printed EPC plus all supporting documents