Business Practice Manual for

Market Operations

Version 25

Last Revised: April 9, 2012

CAISO Business Practice Manual BPM for Market Operations

Approval History

Approval Date: March 23, 2009

Effective Date: March 31, 2009

BPM Owner: Nancy Traweek

BPM Owner’s Title: Director of System Operations

Revision History

Version / Date / Description /
1 / 3-23-2009 / Version Release
2 / 10-14-2009 / PRR # 39 – Changes were made to Appendix C Section C.4.1 to reflect new expected energy types arising from implementation of new exceptional dispatch codes.
3 / 11-02-2009 / PRR # 78 – New Expected Energy Calculation Schedule effective with Payment Acceleration. Changes were made to Appendix C Section C.6 due to implementation of payment acceleration initiative.
4 / 12-31-2009 / PRR # 86 – Changes to Market Operations BPM arising out of implementation of Standard Capacity Product. Changes were made to Section 6.6.3 due to implementation of Standard Capacity Product initiative.
4 / 12-31-2009 / PRR # 100 - Market Operations BPM changes due to Simplified ramping rules implementation. Changes were made to Section 6.6.2 and Section 7.6.3.2 of the BPM.
4 / 12-31-2009 / PRR # 104 - Revisions to ensure consistency with RMR contract and tariff requirements. Changes were made to Section 6.5.1 and Section 6.5.2 of BPM.
5 / 4-1-2010 / PRR # 171 - Market Operations BPM changes related to AS in HASP. The following sections were updated :2.3.2, 2.3.2.1
, 2.3.2.2, 2.3.2.3, 4.3.2, 4.5, 7.2.2, 7.2.3.2, 7.3.3, 7.3.4, 7.5, 7.5.4, 7.5.5, 7.5.5.2, 7.6.2. The following new sections were added: 7.6.2.1, 7.9.4.1
5 / 4-1-2010 / PRR # 189 - Five-Day Price Correction Time Horizon. Changes were made to section 8.1.6.2 of the BPM.
5 / 4-1-2010 / PRR # 201 - Proposed parameter changes for April 1, 2010 Energy Bid Cap increase to $750. Changes were made to sections 2.2.2 and 6.6.5 of the BPM.
6 / 4-15-2010 / PRR # 170 - Market Operations BPM changes related to RTM forbidden operating region (FOR) implementation.
7 / 5-12-2010 / PRR # 132 - Market Operations BPM Updates related to PIRP
7 / 5-12-2010 / PRR # 202 - Update hyperlink to market data
8 / 6-1-2010 / PRR # 213 - Price Corrections Make Whole Payments. A new appendix E was added.
9 / 6-15-2010 / PRR # 215 - Details related to the Forbidden Operating Region (FOR) implementation. Changes were made to sections 7.8.2.4, 7.10.4 and 7.10.4.1.
10 / 7-26-2010 / PRR # 276 - Detail related to Eligible Intermittent Resources (EIRs). Changes were made to Appendix A sections 13, 13.2, 13.2.2, 13.3, 13.3.1, 13.3.2, 13.3.3, 13.3.5, 13.5, 13.7; New section 13.4 was added.
11 / 08-09-2010 / PRR # 167 - Market Operations BPM changes related to PDR. Changes were made to sections 2.1.2, 2.4.4, 2.4.5, 2.5.2.1, 2.5.2.3, 4.1.1, 4.2.1, 4.6, 4.6.3, 6.5.1, 7.4, 7.8.1.2
12 / 09-14-2010 / PRR 281 – Wheeling out and wheeling through transactions. Changes were made to section 2.5.2.2
13 / 10-01-2010 / PRR 296 – LDF adjustment due to weather. Changes were made to section 3.1.4
13 / 10-01-2010 / PRR 297 – Post five-day price correction process. Changes were made to section 8.
13 / 10-01-2010 / PRR 301 – Clarification of MSS election options. New section 2.4.2.3 was added.
14 / 12-07-2010 / PRR 345 and 359 – Changes related to the Multi-Stage Generating Resource modeling implementation. Changes were made to sections 2.2.1, 2.4.5, 2.5.2, 4.3, 4.3.2, 4.5, 4.6, 6.5.1, 6.6, 6.6.1.2, 6.6.2, 6.6.2.1, 7.2.3.1, 7.2.3.6, 7.3.1.3, 7.5.3.2, 7.6, 7.6.3.1, 7.8.2.2, 7.11, 7.11.1 and appendix Attachments C and D. New sections 2.1.5, 7.6.3.3, 7.6.3.4, and 7.6.3.5 were added.
15 / 12-21-2010 / PRR 349 - Changes for Market Ops BPM in support of revised Scarcity Pricing Proposal. Changes were made to section 4.2. New section 4.4.1 was added.
15 / 12-21-2010 / PRR 354 - Implementation of Market Issues process in support of Post Five-Day Price Correction Process. New appendix Attachment G was added.
15 / 12-21-2010 / PRR 355 - Initial Condition for Day-Ahead Market Resources. New section 6.1.9 was added.
15 / 12-21-2010 / PRR 358 - Clarification of use of minimum effectiveness threshold. Changes were made to section 3.2.4.
16 / 01-26-2011 / PRR 342 - Market Operations BPM changes in support of convergence bidding. Changes were made to sections 2.1.2, 2.2.1, 2.2.3, 2.2.4, 2.3.1, 2.3.1.1-2.3.1.3, 2.3.2, 2.4.5, 2.5.2, 3.1, 3.1.4, 3.2.4, 6.1.3, 6.1.8, 6.3.1, 6.4.4, 6.4.6, 6.5.1, 6.6, 6.6.1.1, 6.6.3, 6.6.6, 6.6.7, 7.1, 8.1.5.4 and appendix Attachments D and E. New sections 2.5.2.4, 3.1.10, 6.6.5.4, and appendix Attachment F were added.
17 / 04-01-2011 / PRR 360 - Market Ops - Clarification of Power Balance Constraint Parameters. Entry added to Real Time Market Parameters table in section 6.6.5.
17 / 04-01-2011 / PRR 375 - RUC Availability bids for RA resources - conform Market Ops language to Market Instruments. Changes were made to section 6.7.2.6
17 / 04-01-2011 / PRR 378 - Change market parameter value for Ancillary Service Maximum Limit. An entry was changed in both the Integrated Forward Market (IFM) Parameter Values table and the Real Time Market Parameters table in section 6.6.5.
17 / 04-01-2011 / PRR 421 - Change market parameter values to reflect increased bid cap. Multiple entries were changed in both the Integrated Forward Market (IFM) Parameter Values table and the Real Time Market Parameters table in section 6.6.5.
18 / 05-18-2011 / PRR 385 - Open/isolated intertie handling companion language for Market Operations BPM. Detail provided in Market Instruments BPM. Changes made to sections 6.4.4 and 7.1
18 / 05-18-2011 / PRR 420 - Cleanup of sections 2.4.2.2 and 6.1.2. These sections changed to reflect most recent information.
19 / 06-13-2011 / PRR 426 - Forbidden Operating Region Compliance Feature. Changes made to section 7.2.3.7
20 / 08-12-2011 / PRR 443 - Market Ops companion changes to support new Direct Telemetry BPM. Changes made to appendix attachment A, section A.13.
20 / 08-12-2011 / PRR 445 - Virtual Bidding -- Interties With Zero ATC. Changes made to section 2.5.2.4.1 and 6.4.4
21 / 09-19-2011 / PRR 454 - Changes in support of RDRR initiative. Tariff effective 4/1/12. Changes made to sections 2.1.2, 4.6, 6.5.1, 6.7.2.6, 7.1, and 7.11.1
22 / 10-28-2011 / PRR 479 - Changes to support the 72 hr RUC initiative. Changes made to section 2.3, 2.3.1.3, 2.3.1.4, 6.4.7, 6.7 and subsections, 6.8, and 7.7.
22 / 10-28-2011 / PRR 482 - Changes to support grouping constraints initiative. Change made to section 2.1.6.1. New section 6.6.2.2 was added.
22 / 10-28-2011 / PRR 483 - Changes to support interim dynamic transfer functionality. New section 7.8.2.5 was added.
22 / 10-28-2011 / PRR 485 - Clarify telemetry requirements for Eligible Intermittent Resources. Changes made to appendix Attachment A, sections A.13.2.2 and A.13.3.3.
23 / 12-09-2011 / PRR 495 - Changes in support of Flexible Ramping Constraint initiative. New section 7.1.3 added.
24 / 03-08-2012 / PRR 523 - MSG Enhancement Dec 2011. Change made to section 7.6.3.3.
24 / 03-08-2012 / PRR 526 - Miscellaneous PIRP related changes. Changes made to Appendix Attachment A, sections A.13.6.1 and A.13.6.5.
25 / 04-09-2012 / PRR 532 - Changes to support local market power mitigation enhancements. Changes made to sections 2.3.1, 2.3.1.1, 2.3.1.2, 2.3.2.1, 2.3.2.2, 2.4.5, 6, 6.2, 6.3.1, 6.4.5, 6.4.6, 6.5, 6.5.1, 6.5.2, 6.5.3, 6.5.5, 6.6, 6.6.5, 6.7.2.6, 6.7.2.8.1, 7.2.1, 7.3.3, 7.4, 7.9, Appendix Attachment B, sections B and B.1 through B.12, Appendix Attachment C section C.2.1.1.25, and Appendix Attachment D sections D.3.1 and D.6.1. New sections 6.5.3.1 and 6.5.3.2 added.
25 / 04-09-2012 / PRR 535 - Changes to support Multi-stage generation enhancements functionality. Changes made to sections 2.1.5 and 6.6.2.


TABLE OF CONTENTS

1. Introduction 1

1.1 Purpose of CAISO Business Practice Manuals 1

1.2 Purpose of this Business Practice Manual 2

1.3 References 3

2. Market Operations Overview 4

2.1 Market Entities 4

2.1.1 CAISO 4

2.1.2 Scheduling Coordinators 5

2.1.3 Participating Generators 5

2.1.4 Constrained Output Generator 5

2.1.5 Multi-Stage Generating Resources 6

2.1.6 Participating Loads 7

2.1.7 Non-Participating Loads 15

2.1.8 Utility Distribution Companies 15

2.1.9 Metered Subsystems 15

2.1.10 Balancing Authority Areas 16

2.1.11 Participating Transmission Owners 17

2.1.12 System Resource 17

2.2 Products & Services 18

2.2.1 Energy 18

2.2.2 Ancillary Services 19

2.2.3 Residual Unit Commitment Capacity 19

2.2.4 Congestion Revenue Rights 19

2.3 CAISO Markets 20

2.3.1 Day-Ahead Market Processes 22

2.3.2 Real-Time Processes 24

2.4 Roles & Responsibilities 27

2.4.1 Utility Distribution Companies 27

2.4.2 Metered Subsystems 27

2.4.3 Participating Transmission Owners Information 29

2.4.4 Participating Generators & Participating Loads 30

2.4.5 Scheduling Coordinator Responsibilities 31

2.5 Market Information 33

2.5.1 Resource Static Data 34

2.5.2 Bids 34

2.5.3 Inter-SC Trades 41

2.5.4 Existing Transmission Contracts, Transmission Owner Rights, & Converted Rights 41

3. Full Network Model 42

3.1 Model Description 42

3.1.1 Real-Time Data 43

3.1.2 Generation Distribution Factors 44

3.1.3 Modeling Point 45

3.1.4 Load Distribution Factors 46

3.1.5 Aggregated Pricing Nodes 48

3.1.6 Losses 48

3.1.7 Nomograms 53

3.1.8 Transmission Element & Transmission Interfaces 55

3.1.9 Scheduling Points 57

3.1.10 Nodal Group Limit Constraints 58

3.2 Locational Marginal Prices 60

3.2.1 LMP Disaggregation 61

3.2.2 System Marginal Energy Cost 68

3.2.3 Marginal Cost of Losses 68

3.2.4 Marginal Cost of Congestion 68

3.3 Market Interfaces 69

4. Ancillary Services 70

4.1 Ancillary Services Regions 70

4.1.1 Ancillary Services Region Definition 70

4.1.2 Ancillary Services Region Change Process 74

4.2 Ancillary Services Requirements 74

4.2.1 Self-Provided Ancillary Services 77

4.2.2 Conversion of Conditionally Qualified SPAS to Energy 80

4.2.3 Conversion of Conditionally Unqualified SPAS to Qualified SPAS 81

4.2.4 Other Details of SPAS 81

4.2.5 Ancillary Service Award Allocation on Energy Bids 82

4.2.6 Regulation Up & Down Requirements 85

4.2.7 Operating Reserve Requirements 85

4.2.8 Maximum Upward Capacity Constraint 87

4.3 Ancillary Services Procurement 88

4.3.1 Ancillary Services Procurement in Day-Ahead Market 89

4.3.2 Ancillary Services Procured in Real-Time 90

4.4 Ancillary Services Marginal Prices 91

4.4.1 Ancillary Services Pricing in Event of Supply Insufficiency 93

4.5 Ancillary Services Considerations 100

4.6 Ancillary Services Certification & Testing Requirements 102

4.6.1 Regulation Certification & Testing Requirements 103

4.6.2 Spinning Reserve Certification & Testing Requirements 104

4.6.3 Non-Spinning Reserve Certification & Testing Requirements 104

5. Existing Transmission Contracts, Converted Rights & Transmission Ownership Rights 106

5.1 Continuation of Rights & Obligations 106

5.1.1 Existing Transmission Contracts 106

5.1.2 Converted Rights 107

5.1.3 Non-Participating Transmission Owners 108

5.1.4 Transmission Ownership Rights 108

5.1.5 TOR Scheduling Time Line Requirements 109

5.1.6 TOR Scheduling Requirements 110

5.1.7 ETC and CVR Scheduling Time Requirement 112

5.1.8 ETC and CVR Scheduling Requirements 114

5.1.9 Scheduling Priority for Transmission Rights 115

5.1.10 ETC, CVR & TOR Settlement 116

5.1.11 Transmission Rights & Curtailment Instructions (TRTC) 117

5.1.12 ETCs, CVRs and TORs Treatment in the Release of CRRs 119

5.2 Available Transfer Capability Calculation 119

5.2.1 ATC Calculation before DAM Closes 119

5.2.2 ATC Calculation After DAM Completes & Before RTM Closes 119

5.2.3 ATC Calculation After RTM Completes 120

6. Day-Ahead Market Processes 121

6.1 Pre-Market Activities 121

6.1.1 Congestion Revenue Rights 121

6.1.2 Full Network Model Build 121

6.1.3 Bid Information 121

6.1.4 Outage Information 121

6.1.5 CAISO Demand Forecast Information 122

6.1.6 Determine Operating Transfer Capability 122

6.1.7 Before Day-Ahead Market is Closed 122

6.1.8 Overgeneration Condition 124

6.1.9 IFM Initial Conditions 125

6.2 Day-Ahead Market Timeline 126

6.3 Scheduling Coordinator Activities 127

6.3.1 Submit Bids 127

6.3.2 Interchange Transactions & e-Tagging 128

6.3.3 Respond to Day-Ahead Market Published Schedules & Awards 129

6.4 CAISO Activities 129

6.4.1 Accept Day-Ahead Market Inputs 129

6.4.2 Disseminate Pre-Market Information 129

6.4.3 Disseminate Post Market Close Information 130

6.4.4 Procedures for Closing the Day-Ahead Market 130

6.4.5 Execute Day-Ahead Market Applications 132

6.4.6 Publish Reports to Scheduling Coordinators 132

6.4.7 Resource Commitment 134

6.5 Market Power Mitigation 135

6.5.1 Decomposition method 136

6.5.2 Treatment of RMR Resources in MPM 137

6.5.3 Competitive Path Criteria 138

6.5.4 Default Energy Bids 138

6.5.5 Bid Adder for Frequently Mitigated Units 139

6.6 Integrated Forward Market 140

6.6.1 IFM Inputs 140

6.6.2 IFM Constraints & Objectives 143

6.6.3 Co-optimization of Energy & Ancillary Services 147

6.6.4 Market Clearing 147

6.6.5 Adjustment of Non-Priced Quantities in IFM 148

6.6.6 IFM Outputs 158

6.6.7 Energy Settlement 159

6.7 Residual Unit Commitment 160

6.7.1 RUC Objective 162

6.7.2 RUC Inputs 163

6.7.3 RUC Execution 176

6.7.4 RUC Outputs 177

6.8 Extremely Long-Start Commitment 179

7. Real-Time Processes 180

7.1 Differences from IFM 181

7.1.1 Real-Time Market Timelines 183

7.1.2 Real-Time Dispatch Principles 184

7.1.3 Support of Flexible Ramping Constraint 185

7.2 Scheduling Coordinator Activities 186

7.2.1 Submit Bids 186

7.2.2 Interchange Transactions & e-Tagging 187

7.2.3 Respond to Commitment & Dispatch Instructions 187

7.3 CAISO Activities 191

7.3.1 Accept Hourly HASP & Real-Time Market Inputs 191

7.3.2 Close Real-Time Market 195

7.3.3 Execute Real-Time Applications 195

7.3.4 Publish Real-Time Market Reports to Scheduling Coordinators 197

7.4 MPM for Real-Time 197

7.5 Hour-Ahead Scheduling Process 199

7.5.1 Hourly Schedule Changes 199

7.5.2 Dispatch Priorities 200

7.5.3 HASP Inputs 200

7.5.4 HASP Constraints & Objectives 205

7.5.5 HASP Outputs 207

7.6 Real-Time Unit Commitment 209

7.6.1 Real-Time Unit Commitment Inputs 209

7.6.2 Real-Time Ancillary Services Procurement 209

7.6.3 Real-Time Unit Commitment Constraints & Objectives 211

7.6.4 Real-Time Unit Commitment Outputs 217

7.6.5 Real-Time Unit Commitment Pricing 217

7.7 Short-Term Unit Commitment 217

7.7.1 Short-Term Unit Commitment Inputs 218

7.7.2 Short-Term Unit Commitment Constraints & Objectives 218

7.7.3 Short-Term Unit Commitment Outputs 219

7.8 Real-Time Economic Dispatch 219