University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director: Zak Ovadia
Department: Campus Planning Design & Construction
Date: February 5, 2014
I. Selected Active Projects
note all schedules are tentative
1. Student Assembly Building (Sanctuary): Design and Construction of sanctuary building of approximately 6,500 square feet to serve as a venue for group events.
Tentative Schedule: Programming TBD
Conceptual Permitting TBD
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design August 2013
Design Development October 2013
Construction Docs. TBD
Construction TBD
Changes from last month: Design Committee attended a kick-off meeting on December 20, 2013. Follow-up meeting was held on January 29 to review design development.
2. New Housing Clubhouse Building: Design and Construction of a new Clubhouse to service the housing units in the core campus. Program calls for a 15,000 GSF building to contain a Convenience Store/Grill, a Multi-purpose Room, a Laundry facility for 450 students, an R/A Graphics Room, a Game Room and a Mail Distribution area for 2,900 students.
Tentative Schedule: Programming Complete
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design August 2012
Design Development October 2012
Select CM January 2013
Construction Docs. March 2013
Construction May 2013 to July 2014.
Changes from last month: Project is currently under construction and on schedule. There are no issues at this time.
3. Elevated Parking Deck: Feasibility, Design and Construction of a new elevated parking deck over part of an existing lot south of the FAC. Consultant tested the feasibility of adding additional parking levels to tie to the existing Fine Arts Garage. Program calls for a minimum of 170 stalls to serve the residential population. Currently the design provides over 550 stalls.
Tentative Schedule: Programming August 2013
RFQ for Consultants Completed
Short-listing & Interv. Completed
Program Verification Completed Schematic Design Completed
Design Development October 2013
Select CM January 2014
Construction Docs. March 2014
Construction Must be occupiable by January 2015
Changes from last month: CM short-listing concluded on January 23 with three firms invited for interviews.
.
6. Aquatic Center Re-purposing for Basketball: Design and construction of basketball courts and general extensive renovations to the Aquatic Center to eliminate the pool.
Tentative Schedule: Programming TBD
RFQ for Consultants TBD
Short-listing & Interv. November 2013
Program Verification December 2013
Schematic Design January 2014
Design Development February 2014
Select CM March 2014
Construction Docs. TBD
Construction TBD
Changes from last month: Project Committee attended a kick-off meeting on December 10. Schematic Design started. ZO reviewed concept with RDB on January 24 before the committee meeting.
7. New Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size pool and diving pool north of the existing Student Wellness Complex.
Tentative Schedule: Programming TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design TBD
Design Development TBD
Select CM TBD
Construction Docs. TBD
Construction TBD
Changes from last month: President endorsed the nomination of EMO Architects as prime consultant. Kick-off meeting will be scheduled shortly.
8. Skinner-Jones Hall NORTH: Programming and Schematic Design: Programming, Schematic Design, Feasibility Study to re-purpose this building. Program will include Skinner-Jones Hall SOUTH as well as other buildings having related departments (Math, Engineering, Health, etc).
Tentative Schedule: RFQ for Consultants August 2013
Short List for interview September 2013
Programming November 2013
Schematic Design TBD
Design Development TBD
Select CM TBD
Construction Docs. TBD
Construction TBD
Changes from last month: Kick-off meeting was held on Friday January 17. Discussion of space needs occurred. Meeting Minutes distributed for concurrence.
7. Library Learning Commons: Reconfigure First and Second Floors to create a student-centric learning commons. Co locate the Help Desk from Bldg 15, and remodel entry lobby.
Tentative Schedule: Programming February 2014
Program Verification March 2014
Schematic Design March 2014
Design Development April 2014
Construction Docs. May 2014
Construction July 2014
Changes from last month: This is a new space and function needs to be completed ASAP in 2014.
9. Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of magnitude cost for providing utility services to a grouping of four buildings.
Tentative Schedule: NO CHANGE.
10. Development of Greek Village: This project entails the programming and completing a feasibility study to develop 250-bed a Greek Village at Tech. Park
Tentative Schedule: Consultant Selection RFQ Released
Consultant Selection TBD
Programming TBD
Feasibility Study TBD
Report Due December 2012
Changes from last month: NO CHANGES
4
Zak Ovadia