Contract Manager’s Logo

Project Name

Section or Segment #

Contract Number PRECONSTRUTION MEETING

Day of Week Time MM/DD/YY

NTTA OFFICE at 5900 W. PLANO PARKWAY, MAIN BOARD ROOM

Project Description

Introduction: [insert Corridor Construction Manager’s name & company name]______

  1. PURPOSE: The purpose of the preconstruction meeting is to afford an opportunity for key members of the NTTA and Contractor’s organization to become acquainted, to establish lines of authority and communication, and to determine the responsibilities and duties of the Contractor and NTTA personnel. Emphasis is also directed towards promoting greater safety to the travelingpublic and personnel on construction projects.
  2. INTRODUCTIONS: NTTA Staff, Consultants and Contractor will introduce themselves, their organization, and their responsibilities for this project. Please sign the sign in sheet and provide your printed name, Company name, address, telephone number and e-mail address.
  3. REVIEW OF THE PROJECT:
  4. Project Identification: [Insert appropriate values from contract into Agenda for applicable items in contract (Liquidated Damage amount, substantial completion date, final completion or working days)]
  5. Project No. ______
  6. Highway: ______
  7. Section/Segment #: ______
  8. Limits: From ______to ______
  9. County(ies): ______
  10. Approximate Length: ______ft. (_____ miles) Sta._____ to_____
  11. Duration:

1)____Calendar Days for substantial completion of ______

($______/day LD)

2)____Calendar Days for substantial completion from ______($______/day LD)

3)____Calendar Days for final completion from ______

($______/day LD)

  1. Total Bid: $______
  1. TYPE OF WORK:[insert project description] ______
  2. CONTRACTOR’S WORK PLAN
  3. Contractor’s Project Manager______
  4. Discussion of Work Plan including start date, sequence of work, major road closings, and openings, etc.
  5. Start Date: ______
  6. Completion Date: ______
  7. Discuss project schedule
  8. Introduce Subcontractors and the work they will perform
  9. Contractor to submit a letter stating persons of responsibility

1)Project Manager:[insert Project Manager’s name & company name]______

2)Project Superintendent :[insert Superintendent’s name & company name]______

3)Others:

  1. CHANGE ORDERS: To be submitted in writing with drawings, calculations and supporting documentation to the Construction Manager (CM) for review and further handling, per -Standard Specification Item 4 and Special Provision to Item 4.
  2. SHOP DRAWINGS AND RFI’S
  3. All shop drawings from the Contractor will be submitted to the CM for processing, in accordance with Special Provision to Item 5.
  4. All RFI’s (Request for Information) are to be submitted to the CM for Processing.
  5. TRAFFIC CONTROL PLANS:
  6. Contractor is responsible to maintain traffic controls and safe access to all local residents and businesses at all times.
  7. Coordinate with TxDOT and local authority on Traffic Signals and Lane Closures/detours. The Local Authority will be:[insert Local Authority name – i.e. Plano Police Department] ______
  8. CM and Contractor will always be vigilant for TCP compliance.

1)[insert person’s name & company]______will be the responsible person for the CM.

2)The Contractor’s person will be[insert person’s name & company]______.

3)Traffic control devices shall be inspected daily.

4)Deficiencies must be corrected immediately.

5)Regularly scheduled monthly, daytime and nighttime inspections will be performed.

  1. Responsible for barricade checks:
  2. Construction Manager [insert person’s name& company]______
  3. Contractor [insert person’s name & company]______
  4. Barricade Contractor [insert person’s name & company] ______
  5. Alternate traffic control plans that are not specified in the contract plans must be prepared, signed and sealed by a Texas Professional Engineer and are to be approved by the Construction Manager prior to Implementation.
  6. All flagging personnel will have proper training, equipment, and clothing prior to working as a traffic flagger, in accordance with TxDOT Article 502.2.B. (Barricades, Signs and Traffic Control)
  7. TxDOT Contact for Frontage Road Issues:[If applicable, insertname & company ]______
  1. LAW ENFORCEMENT
  2. The Contractor will provide a full-time off-duty uniformed Police officer for traffic control as needed, as described in General Notes and Specification Data to Item 502.
  3. MATERIALS:
  4. All materials stored on the site that the contractor intends to get paid for as material on hand will be accessible for review at any time, in accordance withTXDOT Specification 9.7.
  5. Failure to supply all invoices with requests for payments of Materials-on-Hand will be grounds for denial of payment.
  6. No obstruction of sight distances or views shall be permitted on any active roadway.
  7. Ensure that all stockpiled materials are kept out of the clear zones of anactive roadway.
  8. SUBCONTRACTORS:
  9. The Contractor shall not subcontract any portion of the contract without the approval of the Engineer. No subcontractor will, in any case, relieve the prime contractor of his responsibility under the contract.
  1. PUBLIC INFORMATION OFFICE: Refer all media contacts to the NTTA, Director of Communication: Ms. Kimberly Jackson.
  2. EQUAL EMPLOYMENT OPPORTUNITY PROGRAM:
  3. [Insert name of person & company]______will assign EEO officer[Insert name of person & company]______.
  4. Contractor will conduct EEO meetings on a regular basis.
  5. Certified Payrolls shall be submitted to the CM on a regular basis as required in the contract.
  6. DBE REQUIREMENTS: DBE goal is______% for this project. The Contractor has identified several DBE companies to be utilized. Approval is required if Contractor intends to change DBE subcontractor companies.
  7. LEGAL RELATIONS AND RESPONSIBILITIES: The Contractor is reminded to comply with TxDOT Specification Item 7 and Special Provision to Item 7.
  8. SAFETY AND HEALTH:
  9. It is the contractual obligation of the Contractor to comply with the State and Federal construction safety standards. Further, it is the Contractor’s responsibility for seeing that the subcontractors also comply with safety standards.
  10. To document the Contractor’s accident program , the Contractor must answer the following questions:
  11. Does the Contractor have a defined safety program?
  12. Has responsibility for safety been assigned to a specific company official?
  13. Does the Contractor make frequent project safety inspections? Does this include subcontractor operations?
  14. Does the Contractor’s management support the safety program?
  15. Does the Contractor’s safety program include discussion with employees to promote safe conditions and practices in their work?
  16. Are periodic safety meetings held with employees?
  17. Are all job-related injuries and illnesses investigated, recorded and reported by the Contractor?
  18. OSHA Compliance. Does the contractor keep informed on Government safety regulations and standards?
  19. ENVIRONMENTAL:
  20. There will be a separate meeting scheduled and held with contractor and USACE to discuss the compliance with the 404 Permit requirements for the corridor. The meeting is scheduled for ______AM/PM at [Insert location of meeting]______
  21. Contractor must obtain proper environmental/ archaeological clearances pertaining to Project Specific Location (PSL).
  22. The Contractor is responsible for implementation and maintenance of the Storm Water Pollution Prevention Plan (SW3P).
  23. No mitigation requirements for this contract.
  24. The Contractor’s responsible person for SW3P is [Insert name of person & company] ______. The EC Team will monitor the SW3P for NTTA.
  25. The NTTA executed Notice of Intent (NOI) for overall program, However, Contractor is responsible to obtain project specific NOI for submission to the TCEQ (Texas Commission on Environmental Quality) in accordance with General Notes and Specification Data Item 7.
  26. GENERAL DISCUSION:
  27. All project communication will be on NTTA EPDS.
  28. Field office location and when it will be operational?
  29. Natural Grey Concrete TxDOT Specification 850 and Special Provision to 850.
  30. Smooth finished forms
  31. MSE Walls-Tricon is the sole source provider.
  32. Pay Estimate cutoff date is the 25th of each month. Forms are electronically available upon request.
  33. Regularly scheduled weekly meetings will be held to discuss Project Progress and Prosecution. The Contractor will submit the Two-Week Look-Ahead schedule at this meeting.
  34. A separate meeting to discuss schedule submittals, reviews, deadlines, and updates will be held at a later date.
  35. The Contractor is responsible for the damage to underground utilities located within the Right of Way. Reminder to review Special Provision SP-0.02.0 including submittals prior to construction operations in the area of existing utilities.
  36. Materials letter designating sources of all materials proposed to be used on project. STL will be the Materials Testing firm supporting the CM.
  37. Periodic utility coordination meetings will be held as the project progresses.
  38. Number all documents including submittals, RFI’s letters and schedules.
  39. QUESTIONS & CONCERNS