Application for Transmission Service

Procedures for initiating Network Service with Portland General Electric Company (PGE) are set forth in Section 29.2 of PGE’s Open Access Transmission Service Tariff. These procedures require submittal of an Application.
Applicants should submit the information identified below (refer to Section 29.2 of the Tariff). PGE is generally able to process a request for service expeditiously upon receipt of this information. Special requests or circumstances may require the provision of additional information. PGE will rely upon the information provided below in processing a customer's application.
COMPANY
NAME / DATE
STREET ADDRESS
PHONE NUMBER / FAX NUMBER
E-MAIL ADDRESS
CONTACT FOR SETTLEMENTS
NAME / E-MAIL ADDRESS
PHONE NUMBER / FAX NUMBER
CONTACT FOR INVOICING
NAME / E-MAIL ADDRESS
STREET ADDRESS (if different from mailing)
PHONE NUMBER / FAX NUMBER
CONTACT FOR PRESCHEDULING
NAME
TIME ZONE (circle one)
PST MST CST EST / WORK HOURS
PHONE NUMBER / FAX NUMBER
CONTACT FOR REAL-TIME OPERATIONS
NAME
TIME ZONE (circle one)
PST MST CST EST / WORK HOURS
PHONE NUMBER / FAX NUMBER
TYPE OF SERVICE REQUESTED
Network Retail Network Integration
LOCATION OF THE POINTS OF RECEIPT
DESCRIPTION OF NETWORK LOAD AT EACH DELIVERY POINT (MW)
THE AMOUNT AND LOCATION OF ANY INTERRUPTIBLE LOADS INCLUDED IN THE NETWORK LOAD:
DESCRIPTION OF NETWORK RESOURCES (CURRENT AND 10-YEAR PROJECTION) WHICH SHALL INCLUDE, FOR EACH NETWORK RESOURCE:
DESCRIPTION OF ELIGIBLE CUSTOMERS TRANSMISSION SYSTEM:
SERVICE COMMENCEMENT DATE / TERM OF TRANSMISSION SERVICE
DUNS NUMBER / NERC ID
PERSON SIGNING CONTRACT / TITLE
By signing below, applicant acknowledges that the party requesting service is an eligible customer under Section 1.11 of the Tariff.

______

Printed Name of Applicant

______

Applicant Signature

______

Title

______

Date

If you have any questions about this application please contact

Sandy Ness at Portland General Electric, 503-464-7155.

Description of Network Load

Description of Network Loads:

Delivery Point:

Ten year forecast of summer and winter load and resource requirements

Year / Summer MW / Winter MW / Resource Requirements
1
2
3
4
5
6
7
8
9
10

Amount and Location of any Interruptible Loads

Amount and location(s) of any interruptible load(s) included in the network load(s)
(please specify by location, etc.) Provide attachments for additional interruptible loads.
Winter Load:
Year / Location / Winter Load MW / Conditions for Interruption / Amount and Frequency Limitations
1
2
3
4
5
6
7
8
9
10

Amount and Location of any Interruptible Loads

Amount and location(s) of any interruptible load(s) included in the network load(s)
(please specify by location, etc.) Provide attachments for additional interruptible loads.
Summer Load:
Year / Location / Summer Load MW / Conditions for Interruption / Amount and Frequency Limitations
1
2
3
4
5
6
7
8
9
10
Description of Network Resources
(if applicable please attach 10-year projection):
Source of Supply:
Unit Size:
Control Area Location:
Transmission arrangements:
Delivery Point(s):
VAR capability (both leading and lagging) of all generators:
Operating restrictions
Any periods of restricted operations throughout the year:
Maintenance schedules:
Minimum loading level of unit:
Normal operating level of unit:
Any must-run unit designations required for system reliability or contract reasons:
Approximate variable generating cost ($/MWH) for redispatch computations:
Arrangements governing sales and delivery of power to third parties from generating facilities located in Portland General’s Control area, where only a portion of unit output is designated as a Network Resource:

PGE 98080 (Feb 2004) 6